Sr. No. Description Contractor Note
or-HVAC
(ACIL)
A Engineering & Drawings
Design, Engineering, Preparation of Shop Drawings, As built drawings including FIM
1 √
(Free issue material) if any.
SUBCONTRACTOR shall extend his support for the preparation of the coordinated shop
2 √
drawings.
B Technical Submittals
1 Mobilization plan for labour, MATERIAL and EXECUTION EQUIPMENT √
Detail execution program chart. (Including design, procurement, execution and
2 √
Handover).
All submittals, mock-ups, samples of materials for approval of PRINCIPAL
3 √
CONTRACTOR and Client (prior to start of installation works)
Submission of Technical data sheets, product catalogues of all materials and their
4 √
approval from client/consultant
5 Method statement before commencement of SUBCONTRACT WORK √
6 Operation & Maintenance Manuals/Plan √
C Temporary facilities/services
Further distribution is in subcontractor's
scope. Power charges @ 1% of basic contract
1 Construction Power at single point √
price shall be deducted from each running
bill of subcontractor on prorata basis.
2 Water for tesing, charging and other SUBCONTRACTOR'S works at single point √
3 Potable water √
4 Space & Infra for the labour camp including transportation for labor and staff. √
Construction of office and its watch and ward
5 Space for the SUBCONTRACTOR Site office as feasible and available at site. √
is in subcontractor's scope
6 Building, furnishing and maintaining the Site office & Store √
Cleaning, maintenance and upkeep of the TEMPORARY WORK, SITE FACILITIES and
7 √
Storage Area(s) provided.
Storage facility space at site as feasible and available for one month stock of all Construction of store and its security is in
8 √
Materials for SUBCONTRACTOR subcontractor's scope
9 On SITE sanitary facilities √
Relocation of SUBCONTRACTOR'S Site-Office, storage facility, etc. required time to
10 √
time during progress of work.
11 Communication facilities for day to day communication √
Principal
Subcontract
Sr. No. Description Contractor Note
or-HVAC
(ACIL)
Maintenance, Security of SUBCONTRACTOR'S facilities, materials, equipment etc. until
12 √
the successful HANDOVER of the SUBCONTRACT WORKS.
8 All test reports, calculations, shop drawings, samples and material certificates to be √
submitted by SUBCONTRACTOR for PRINCIPAL CONTRACTOR'S approval.
Provision for spare material in SUBCONTRACTOR'S own storage for successful
9 √
commissioning & HANDOVER of SUBCONTRACT WORKS.
10 Responsibility of system Operation & Maintenance as per Contract √
11 Presentation of installation methodology. √
12 Compliance to the standards mentioned in the technical specification. √
13 Monsoon protection for SUBCONTRACT WORKS √
Testing, Commissioning & HANDOVER of SUBCONTRACT WORKS with necessary
14 provision of materials, equipment’s, accessories etc. as per SUBCONTRACT √
DOCUMENTS
15 Compliance to the GRIHA-3 Requirements √
Openings as required for HVAC works in wall, Brick wall, floor, masonry and MAKE
16 √
GOOD in rough finishes as per pproved standards.
Application of fire sealant wherever the services are passing through the brick or
17 √
masonry /slab opening as per the SUBCONTRACT SPECIFICATIONS as required
18 Provision of sleeves for all service passing through masonry or gyproc walls or slabs. √