ODP-Infrastructure Package

BOQ Pricing Summary

Price
General Requirments 614,257
Electrical - Power 104,746,641
Electrical - Communication 5,876,538
Mechanical - Utilites 27,841,290
Total 139,078,726

REV-0 Page1 of
6TH OCTOBER DRY PORT PROJECT

at

October, Egypt

InfraStructure
BILL OF QUANTITIES

E2032

REV-0

REV-1 Page2 of
October Dry Port ( ODP )
October Dry Port-Execution of Infrastructure Networks.
DP6-P03
General Requirements
Package
Included
Item INFRA TOTAL
Description Unit P03
ODP-contractor Notes
no. Qty.
U/P Total
GENERAL REQUIREMENTS
The Contractor is required to insert prices in the General
Requirements section of the BOQ, which are deemed to include
the Engineer’s facilities (site accommodation, transportation,
offices, etc.) and all such facilities are to be dismantled by the
Contractor and carted away at project completion.
EMPLOYER'S FACILITIES
Site Offices
Rooms to be sized, furnished, equipped and airconditioned to fit for
A purpose adequate
Provide in addition3m
to toilets, buffet/pantry and
X 9m pre-fabricated site all other facilities
Caravans to as
Including :
approved by the Employer / Consultants
accommodate: Caravan (4 Care) , 2 Acs , 2 Desks , 2 Cubboards , 2
- 2 Employer Representative office nr 1 1 121,286 121,286 Movable Chairs,4 Waiting Chairs(Not Including
Computers Or Printers Or Water Dispanser)

B Provide adequate 3m X 9m pre-fabricated site Caravans to nr 0 0 0


C accommodate:
Supply, install, and maintain one photocopier machine (including nr 0 0 0
- 1 Meeting
copying, Room
printer and
D Digital Camera as perscanner), equipped to be connected to
specifications nr 0 0 0
computer network.
Site Transportation for Employer 0
G Provide One (1) new car 1600 cc (on rental basis & the car brand month 0 0 0
G to be approved
Provide One (1)by thecar
new Employer)
1600 cc including
(on rentallicense,
basis &fuel
theand
car brand month 15 15 15,650 234,750
maintenance
to be approved during theEmployer)
by the project. WITHOUT DRIVERfuel and
including license,
ENGINEER FACILITIES 0
maintenance during the project. WITH DRIVER
Consultants' Site Offices 0
I Provide adequate pre-fabricated site Caravans ( 3m X 9m) to Including :
accommodate offices, (Rooms to be sized, furnished, equipped Caravan (4 Care) , 2 Acs , 2 Desks , 2 Cubboards , 2
and airconditioned to fit for purpose) in addition to toilets, nr 1 1 121,286 121,286 Movable Chairs,4 Waiting Chairs(Not Including
buffet/pantry and all other facilities as approved by the Employer / Computers Or Printers Or Water Dispanser)
Consultants
IT Requirements 0
L Internet connection facilities with all requiremets as per item 0 0 0
N specifications
Supply, install,and
andthe Employer
maintain oneapproval-VODAFONE- 30GB
photocopier machine (including nr 0 0 0
P copying, printer as
Digital Camera andperscanner), equipped to be connected to
specifications nr 0 0 0
computer network.
Site Transportation for Consultants 0
S Provide One (1) Site Cars for the Consutlant's staff for daily works month 0 0 0
T on rentalOne
Provide basis
(1)) Microbus
including driver
H-1 for,license, fuel and
consultant's staffmaintenance
transportation
during
from the project.
Cairo to Sadat and vice versa (on rental basis) including month 0 0 0
license, fuel and maintenance during the project.
RUNNING COSTS 0
Maintenance 0
U Generator maintenance and fuel month 0 0 0
V Emptying of septic tank month 0 0 0
W Consultants' Office Maintenance nr 0 0 0
Security 0
X Provide 2 security personnel working on a 24-hr basis for
month 0 0 0
Consultants' and employer's offices
House Keeping 0
Y Provide 2 housekeeping person for Consultants' and employer's
month 15 15 9,129 136,935
offices on a monthly basis
Office Consumables 0
Z All required stationary including, but not limited to paper for printer,
photocopier papers, toner and CDs, calculators, pens etc. month 0 0 0
AA Kitchenette with required facilities and consumable material as tea,
coffee, milk, water, etc. month 0 0 0
PPE 0
AB Personal Protective Equipment including, but not limited to safety
item 0 0 0
boots, hard hats, vests, etc. to cover all Employer's
Representatives/Consultants
Total General Requirements 614,257

REV-0 Page3 of
TOTAL Rate Amount
Description Unit
Qty (EGP) (EGP)

DIVISION 26 - ELECTRICAL

A SECTION 261200 - POWER TRANSFORMER


PACKAGE SUBSTATION

Supplying, installing, connecting and testing of Package Substation (500 KVA, 11/0.4 KV ) complete with RMU,
A01 Dry type Transformer, Low tension Panel, Busbars and all other necessary accessories and ancillary works as No 2 1,537,620 3,075,240
specified and as indicated on the drawings in comliance with the public distribution Co. rules.

Supplying, installing, connecting and testing of Package Substation (1000 KVA, 11/0.4 KV ) complete with
A02 RMU, Dry type Transformer, Low tension Panel, Busbars and all other necessary accessories and ancillary works No 5 1,696,856 8,484,280
as specified and as indicated on the drawings in comliance with the public distribution Co. rules.

STEP DOWN TRANSFROMERS

Supply, install, connect and test of dry step down transformer as specified and as indicated on the drawings
A03 including all necessary accessories and ancillary works and materials required for complete installation No 2 4,428,743 8,857,486

B 26 35 33-POWER FACTOR CORRECTION CAPACITORS


Install in compliance with the tender specifications & drawings :-
B-1 POWER FACTOR CORRECTION CAPACITOR PANEL No 7 256,768 1,797,376

C 26 32 13- PACKAGED ENGINE GENERATORS

Supply , Installing, connecting and testing of a 500 KVA. (at 45°C ambient) 0.8 p.f., 380 V Diesel outdoor
generator set all in accordance with detailed technical specifications complete with all necessary accessories and
C01 ancillary works such as, but not limited to the following : Silencer, flexible joints, exhaust pipes, daily fuel tank No 2 1,520,701 3,041,402
for 24 hours continuous operation at rated load, fuel tank lines, foun-'dation accessories, monitoring and
protection equipment. Also including a set of complete erection material and special tools

Supply , Installing, connecting and testing of a 1000 KVA. (at 45°C ambient) 0.8 p.f., 380 V Diesel outdoor
generator set all in accordance with detailed technical specifications complete with all necessary accessories and
C02 ancillary works such as, but not limited to the following : Silencer, flexible joints, exhaust pipes, daily fuel tank No 5 3,619,626 18,098,130
for 24 hours continuous operation at rated load, fuel tank lines, foun-'dation accessories, monitoring and
protection equipment. Also including a set of complete erection material and special tools

D 26 36 00 - TRANSFER SWITCHES
Supply, install, connect and test of the automatic transfer switch complete with all control, monitoring and
protection equipment including control cabling and all necessary auxiliary components and ancillary works
required for complete operative system.
D01 ATS (1250A) Nr 2 462,779 925,558

D02 ATS (2000A) Nr 5 577,230 2,886,150

E MEDIUM VOLTAGE CABLES

Supplying, installing, connecting and testing 11 K.V. Cables (3x240) mm² AL/XLPE/STA/PVC
between the medium voltage switchgear and transformes including handing over to electricity authority,
m 2500 1,344 3,360,000
terminations, cable ladder, all necessary accessories, ancillary works and materials required for complete
installation as specified and as indicated on the drawings.

F CABLES AND WIRES


Supplying, installing, connecting and testing multicore copper cables XLPE/PVC insulated including
terminations, vertical risers, cable ladder, cable trays, trunking , seismic supports, all necessary
accessories, ancillary works and materials required for complete installation as specified and as indicated
on the drawings for the following sizes:-
F01 4x16+1X16 AL-XLPE/STA/PVC m 6700 160 1,072,000

F02 (3x25+1X16) +1X16 AL-XLPE/STA/PVC m 1450 182 263,900

F03 (3x35+1X16) +1X16 AL-XLPE/STA/PVC m 550 223 122,650

F04 (3x50+1X25) +1X25 AL-XLPE/STA/PVC m 150 245 36,750

REV-0 Page4 of 10
TOTAL Rate Amount
Description Unit
Qty (EGP) (EGP)

F05 (3x70+1X35) +1X35 AL-XLPE/STA/PVC m 150 314 47,100

F06 (3x95+1X50) +1X50 AL-XLPE/STA/PVC m 70 379 26,530

F07 (3x120+1X70) +1X70 AL-XLPE/STA/PVC m 500 488 244,000

F08 (3x150+1X70) +1X70 AL-XLPE/STA/PVC m 550 543 298,650

F09 (3x185+1X95) +1X95 AL-XLPE/STA/PVC m 850 613 521,050

F10 (3x240+1X120) +1X120 AL-XLPE/STA/PVC m 200 732 146,400

F11 4x16+1X16 AL-XLPE/PVC m 300 180 54,000

F12 (3x25+1X16) +1X16 AL-XLPE/PVC m 1200 209 250,800

F13 (3x35+1X16) +1X16 AL-XLPE/PVC m 270 246 66,420

F14 (3x50+1X25) +1X25 AL-XLPE/PVC m 2050 289 592,450

F15 (3x70+1X35) +1X35 AL-XLPE/PVC m 3150 355 1,118,250

F16 (3x95+1X50) +1X50 AL-XLPE/PVC m 3500 405 1,417,500

F17 (3x120+1X70) +1X70 AL-XLPE/PVC m 420 488 204,960

F18 (3x185+1X95) +1X95 AL-XLPE/PVC m 1500 634 951,000

F19 (3x300+1X150) +1X150 AL-XLPE/PVC m 200 871 174,200

G (26 56 00) -(26 09 43 ) EXTERIOR LIGHTING.

Supply, install, connect and test light fixtures including all lamps, mounting 10m steel poles, mounting
devices and brackets as shown on the drawings, specification and as scheduled. The item shall include all
necessary wiring, earthing, conduits & termination of the luminaires to their respective circuits. The
works include the necessary pole concrete base, excavation, backfilling & removal of the excess soil
outside the site. All light fixtures will be supplied and installed by Contractor . The light fixtures models
are included in the tender drawings.

G01 Light Pole P1 No.S 188 19,905 3,742,140

G02 Light Pole P2 No.S 52 24,881 1,293,812

G03 Light Pole P3 No.S 11 24,881 273,691

Supply, Install, tet & hand-over in compliance with the tender specifications & drawings Lighting Mast (H01)
G04 including Lighting Control Panels and lighting fixtures as Indicated in the Design Drawing No.S 25 1,200,239 30,005,975

Supply, Install, tet & hand-over in compliance with the tender specifications & drawings Lighting Mast (H02)
G05 including Lighting Control Panels and lighting fixtures as Indicated in the Design Drawing No.S 4 898,687 3,594,748

( 26 24 16)- (26 24 19) BRANCH CIRCUIT DISTRIBUTION


H
PANEBOARDS
H01 EFP-ODP-16 No.S 1 118,930 118,930

H02 EFP-ODP-17 No.S 1 92,556 92,556

H03 EFP-ODP-18 No.S 1 79,618 79,618

H04 EFP-ODP-19 No.S 1 66,183 66,183

H05 UFP-ODP-C1 No.S 1 66,183 66,183

H06 UFP-ODP-C2 No.S 1 66,183 66,183

H07 UFP-ODP-C3 No.S 1 66,183 66,183

REV-0 Page5 of 10
TOTAL Rate Amount
Description Unit
Qty (EGP) (EGP)

H08 UFP-ODP-C4 No.S 1 66,183 66,183

H09 UFP-ODP-C5 No.S 1 66,183 66,183

I [SECTION 261300]- MEDIUM VOLTAGE SWITCH GEAR


Supply, install, connect and test of 11kV medium voltage SF6 or vacuum switch gear including feeding &
interconnecting all circuit breakers, measuring instruments protective relays, control wiring, and all necessary
accessories , Switch Gear Shall be In compliance with Electrical Distribution Company Regulation and should be
approved by it's representative

I-1 The Switch gear shall be (17 Cell) with [2 incoming + 1 couplers + 1 Riser + 8 Outgoing + 1 Spares) No.S 1 4,246,617 4,246,617

I-2 The Switch gear shall be (17 Cell) with [2 incoming + 1 couplers + 1 Riser + 2 Outgoing ) No.S 1 2,436,306 2,436,306

J Furnishing,
GROUNDING supplying, installing and
AND BONDING testing
FOR a complete protective
ELECTRICAL SYSTEMS earthing (PE) system complete with
earthing pits, earthing electrodes, equalizer bars, earth continuity conductor, and earthing conductor to
RMU, switchboards, diesel generator set and transformers in each package substation complete with all
No.S 7 47,274 330,918
accessories, fixing brackets, test links, complete with all accessories, fixing brackets, test links
Earthing impedance
suspensions, drillingmust be <= 5for
and cutting ohm
complete installation all in accordance with technical specifications
and drawings
DIVISION 26 - ELECTRICAL
TOTAL 104,746,641
To Summary Exclude Unit Rates

REV-0 Page6 of 10
TOTAL Rate Amount
Description Unit
Qty (EGP) (EGP)

DIVISION 27 - COMMUNICATIONS

A TELECOMMUNICATION SYSTEM

Design Supply, install, connect and test telecommunication system including all ancillary work required for
complete the work as duct bank , cables , …. ,

Supply install, connect and test of Light Current Duct Back including (3No. of 80 mm DIA) to connect
A01 Telecommunication system as specified and indicated in the drawings with all necessary m 2800 565.00 1,582,000.00
termination, and all necessary accessories required to complete operative system

Supply install, connect and test of Light Current Manhole to connect Telecommunication system as specified
A02 and indicated in the drawings with all necessary termination, and all necessary accessories required to complete No 46 16,919.00 778,274.00
operative system

Supply install, connect and test of Light Current Handhole to connect Telecommunication system as specified
A03 and indicated in the drawings with all necessary termination, and all necessary accessories required to complete No 36 13,934.00 501,624.00
operative system

Supply, install, connect and test 6 core M.M fiber cable The item shall include raceways, splicing , splicing
A04 closures ,,media converter, pig tails fiber SC connectors ,fiber cable pulling & all necessary sleeves. The works Mt 1100 906.00 996,600.00
shall be complete as per the project specifications

Supply, install, connect and test 4 core M.M fiber cable The item shall include raceways, splicing , splicing
A05 closures ,,media converter, pig tails fiber SC connectors ,fiber cable pulling & all necessary sleeves. The works Mt 1020 667.00 680,340.00
shall be complete as per the project specifications

Supply, install, connect and test 2 core M.M fiber cable between outdoor racks The item shall include raceways,
A06 splicing , splicing closures ,,media converter, pig tails fiber SC connectors ,fiber cable pulling & all necessary Mt 2100 637.00 1,337,700.00
sleeves. The works shall be complete as per the project specifications

DIVISION 27 - COMMUNICATIONS
To Summary Exclude Unit Rates
TOTAL 5,876,538.00

REV-0 Page7 of
Item Description QTY Unit Rate Amount

MECHANICAL
1ST DIVISION 33 - UTILITIES
A HDPE piping(33
SECTIONS of 25
PN1030) for underground
SEWER DRAINAGEsewer drainage network. The item shall
PIPE NETWORK:
be include with pipe supports, testing & Handing over. The works include
A-1 Supply ,install,
excavation & backtest filling
& handto. the
Over :-
pre-excavation FFL as per the contract
documents and site supervision instructions. The item shall be complete with
A-1-1 removal
- HDPE of excess
pipe soil of
dia 1000 mm.the backfilling process to their approved destinations 115 MT 11,868 1,364,820
A-1-2 outside
- HDPEthe site.
pipe diaThe
900item
mm.shall be complete & adequate as per tender drawings & 75 MT 9,651 723,825
specification .
A-1-3 - HDPE pipe dia 800 mm. 130 MT 7,825 1,017,250
A-1-4 - HDPE pipe dia 700 mm. 350 MT 6,652 2,328,200
UPVC piping of PN6 for underground sewer drainage network. The item shall be
A-1-5 include
- HDPEwith
pipepipe
dia 650 mm. testing & Handing over. The works include
supports, 90 MT 5,347 481,230
excavation & back filling to the pre-excavation FFL as per the contract
documents and site supervision instructions. The item shall be complete with
A-1-6 removal
- UPVC of excess
pipe soilmm.
dia 600 of the backfilling process to their approved destinations 280 MT 3,587 1,004,360
A-1-7 outside
- UPVCthe site.
pipe diaThe
550item
mm.shall be complete & adequate as per tender drawings & 130 MT 2,935 381,550
specification .
A-1-8 - UPVC pipe dia 500 mm. 190 MT 2,544 483,360
A-1-9 - UPVC pipe dia 450 mm. 250 MT 2,152 538,000
A-1-10 - UPVC pipe dia 400 mm. 280 MT 1,761 493,080
A-1-11 - UPVC pipe dia 350 mm. 776 MT 1,305 1,012,680
A-1-12 - UPVC pipe dia 300 mm. 1034 MT 979 1,012,286
A-1-13 - UPVC pipe dia 250 mm. 850 MT 718 610,300
A-1-14 - UPVC pipe dia 200 mm. 1410 MT 522 736,020
A-1-15 - UPVC pipe dia 150 mm. 1200 MT 424 508,800
A-1-16 Excavation of rocky soil as per specifications. 1 M3 261 261

SECTIONS (33 25 30) Circular Manhole

A-2 Supply, erect, test & hand - over:-

Supply ,install, test & hand-over Sewer manhole constructed of concrete cast-in
manhole base & manhole riser. The item includes manhole steps & benching.
Excavation, back filling & excess soil removal to it's approved destinations are
included in the item works. The Sewer manhole structure shall be treated againest
water leakage. The item cast iron cover shall be approved by the state authority of
jurisdiction. The sewer construction shall comply with the tender attached design
drawings & specifications. The works shall be complete with all accessories as
specified & shown in the tender drawings The sewer manhole cover shall
Complete with 40ton bearing capacity. If under roadways 600x600mm.

A-2-1 '-Sewer manhole with depth higher than 1.51m & less or equal to 2,5m 66 NO 26,083 1,721,478
A-2-2 '-Sewer manhole with depth higher than 2.51m & less than 4m 19 NO 45,645 867,255

Inspection chamber (IC)


A-2.3 Supply, erect, test & hand-over:- drainage inspection chamber (IC) complete with 20 NO 10,434 208,680
Supply, erect, test
40 Ton bearing & hand-over
capacity, ductilerain
castwater catch basin
iron double complete
seal cover and with 40 Ton
frame.
bearing strength&ductile
(600x600)mm all cast iron
necessary cover c/w The
accessories. gratting covershall
chamber & allbenecessary
constructed of
Rain WaterThe
accessories. Catch Basin shall
chamber (CB)be constructed of 250mm thickness brick walls,
250mm thickness brick walls, plain concrete base & reinforced concrete top slab.
A-2.4 plain concrete
The item shall base & reinforced
include excavation,concrete top slab.
backfilling & theThe item shall
removal of theinclude
excess soil to 60 NO 12,390 743,400
excavation, backfilling & the removal of the excess soil to approved
approved destinations outside the site. The item shall include all necessary destinations
outside the site. The item shall include all necessary accessories
accessories to maintain adequate completion as per specifications & tender to maintain
adequate
drawings.completion
SECTIONS (33 25 10) as per specifications
DOMESTIC & tender
& FIRE drawings WATER SUPPLY
FIGHTING
B
NETWORK:-
HDPE
SECTION piping of 20
( 33 PN1080) for
(33underground
25 10 )WATERdomestic
SUPPLYwaterPIPE
piping supply network
NETWORK :- .
The item shall include pipe fittings & all necessary concrete thrust blocks.
Excavation, backfilling to the pre-excavation FFL as per the contract documents
B-1 Supply,
and install, test &
site supervision hand-over:-
instructions & excess soil removal to approved destinations
are include within the item works. The item shall include the installation from the
B-1-1 Main
HDPEcentral water
pipe dia. reservoirs up to each plot area underground service isolating
110mm. 2900 MT 555 1,609,500
B-1-2 valves.
HDPE pipe dia. 75mm. service isolating valves are included within the item
The underground 30 MT 431 12,930
works. The item shall be complete with all necessary accessories as per the
specifications & tender drawings.

REV-0 Page8 of
Item Description QTY Unit Rate Amount

B-1-3 HDPE pipe dia. 63mm. 90 MT 359 32,310


B-1-4 HDPE pipe dia. 50mm. 120 MT 294 35,280
B-1-5 HDPE pipe dia. 40mm. 30 MT 261 7,830
B-1-6 HDPE pipe dia. 32mm. 60 MT 248 14,880
B-1-7 HDPE pipe dia.25mm. 90 MT 229 20,610

Supply, install, test & hand-over:-


Isolating valves of different diameters.The item shall include gaskets, bolts, nuts,
adaptors, flanges & all necessary accessories as per specifications & as shown in
the tender drawings.
Dia. 110mm. 3 NO 7,173 21,519

B-2 Dia. 75mm. 1 NO 4,565 4,565


Dia. 63mm. 3 NO 3,587 10,761
Dia. 50mm. 5 NO 1,631 8,155
Dia. 40mm. 1 NO 1,174 1,174
Dia. 32mm. 2 NO 783 1,566
Dia. 25mm. 3 NO 587 1,761

Supply, construct & hand over: 2000x2000mm valve chamber to include main
B-3 water
Valve supply
Chamber pipe network isolating valves. The chamber shall be constructed of
brickwork
3000x2000mm shall Water
be constructed of brickwork
valve chamber complete
to include with rein
main water forced
supply concrete
isolating
B-3-1 4 NO 52,166 208,664
ceiling slab. Excavation, backfilling & excess soil removal to approved
valves & accessories. The chamber shall be constructed of brickwork complete
destinations are include
with rein forced concretewithin
ceilingtheslab.
itemExcavation,
works.The backfilling
item shall be
& complete with
excess soil
B-3-2 40ton bearing capacity.ductile cast iron double seal cover and frame.
removal to approved destinations are include within the item works. The item
- Main
shall beproject
completeWater
withmeter
40tonvalve
bearingchamber as per detail
capacity.ductile drawings
cast iron double seal cover 1 NO 71,728 71,728
and frame.
B-4 Air release valve manhole.
Supply, erect, test & hand-over the item including-

1- Valve manhole 1000x1000mm shall Complete with 40ton bearing


capacity.ductile cast iron double seal cover and frame. If under roadways
4 NO 18,258 73,032
600x600mm. . Excavation, backfilling & removal of outside the site is included
within the item works.
B-4-1 2- 110mm dia. Isolating gate valve. (Water Supply) 3 NO 7,825 23,475
B-4-2 3- 65mm double ball air valve. (Water Supply) 3 NO 4,565 13,695

B-5 Washout chamber manhole


Supply, erect, test & hand-over the item shall including :-
1- Valve manhole 1000x1000mm complete with 40ton bearing capacity. If under
B-5-1 3 NO 18,258 54,774
roadways 600x600mm.
B-5-2 2-110mm dia. Isolating gate valve. (Water Supply) 3 NO 8,477 25,431
Supply, install, test & hand-over HDPE piping of PN16 for underground Fire
fighting piping supply network The item shall include pipe fittings & all
necessary concrete thrust blocks. Excavation, backfilling to the pre-excavation
C SECTION ( 33contract
FFL as per the 25 10 ) documents
FIRE FIGHTING PIPE NETWORK
and site supervision :- & excess soil
instructions
removal to approved destinations are include within the item works. The item
shall
HDPEinclude the 150mm.
pipe dia. installation from the Main central water reservoirs up to each 6545 MT 887 5,805,415
plot area underground service isolating valves. The underground service isolating
HDPE pipe dia. 100mm. 720 MT 692 498,240
valves are included within the item works. The item shall be complete with all
necessary accessories as per the specifications & tender drawings
C-1 Siamese Connection

Supply, install, test & hand-over siamese connection with 4 outlets dia 2.5"
complete with isolating, check valves, pipe connections to the pipe network and
2 NO 11,412 22,824
controls. The units shall be in compliance with NFPA rules & UL listed & as
shown in the tender documents.
Supply, install, test & hand-over: 150mm Fire hydrant with two hose nozzles.
The hydrant Interior shall be removable without digging up hydrant. The hydrant
C-2 shall be complete with 150 mm bell connection;with nozzle caps securely chained
Fire hydrant
to barrel. The item includes excavation, back filling & soil removal to approved
54 NO 50,210 2,711,340
destinations outside the site. Concrete thrust block under the valve shall be
employed as per the respective specification detail. The item components shall be
rated for fire protection duties as per NFPA & Egyptian fire codes. The item shall
include all necessary accessories for the piping connection.
REV-0 Page9 of
Item Description QTY Unit Rate Amount

C-3 Valve Chamber

Supply, install, test & hand-over 2000x2000mm valve chamber to include main
water supply pipe network isolating valves. The chamber shall be constructed of
brickwork shall be constructed of brickwork complete with rein forced concrete
6 NO 52,166 312,996
ceiling slab. Excavation, backfilling & excess soil removal to approved
destinations are include within the item works. The item shall be complete with
40 Ton bearing capacity, ductile cast iron double seal cover and frame.

Summary
MECHANICAL
To Summary 27,841,290

REV-0 Page10 of