BILL OF QUANTITIES
Consultant
Design Group Engineering Consultants LLC
P.O. Box: 1102, P.C: 131, Ruwi
Sultanate of Oman
Tel: +968 2481 9477 / Fax: +968 2481 9487
PROPOSED FARMS AT BARKA
Mobilisation
Client/Engineer's Facilities
TO COLLECTION
Site Supervision
Site Telephone/Facsimile
Site Transport
TO COLLECTION
Provide for all necessary small plants and tools for the
A Item
proper execution and completion of the contract.
D Providing and erecting site sign board as per the drawing Item
Testing of materials
Submittals
Final De-mobilization
K De-mobilization Item
TO COLLECTION
COLLECTION
Page 1/1
Page 1/2
Page 1/3
LABOUR
TO COLLECTION
LABOUR (Cont'd)
TO COLLECTION
PLANT
Rates for plant shall include for the use of the plant
inclusive of all fuel and consumable stores, depreciation,
servicing, overhauls repairs and replacements, all other
charges related to the plant including haulage to and from
the site and all establishment charges and profit, but
exclusive of driver and attendants who shall be paid for as
laid down in the Labour Schedule.
TO COLLECTION
PLANT (cont,d)
B Air Compressor 6 m3/min with hose and tools Hrs 25 Rate only
3
C Concrete mixers 0.3/0.2 m Hrs 25 Rate only
3
D Dumper 0.5 m capacity Hrs 25 Rate only
L Excavator, hydraulic full circle slew, CAT 245 or equivalent Hrs 25 Rate only
TO COLLECTION
MATERIALS
Local Materials
Imported Materials
TO COLLECTION
COLLECTION
3.All the materials which are identified by the Client for their
re-use, shall be packed in cartoon with the complete
inventory list, necessary marking on each cartoon and
handed over to the satisfaction of the Client .
TO SUMMARY
2 COMPOUND WALL
TO SUMMARY
3 GATES
MS Sliding Gate
MS Wicket Gate
TO SUMMARY
4 GUARD ROOM
TO SUMMARY
5 HOLDING TANK
TO SUMMARY
6 ADDITIONAL ITEMS
TO SUMMARY
SUMMARY
2 COMPOUND WALL
3 GATES
4 GUARD ROOM
5 HOLDING TANK
6 ADDITIONAL ITEMS
GRAND SUMMARY
SUB TOTAL