• Construction Services
• Post-construction Services
• Comprehensive Services
• Design-build Services
ARCHITECT’S
THE NATIONAL
ARCHITECT’S CODE
NATIONAL CODE
PRE-DESIGN SERVICES
Activities include
• architectural programming
• feasibility study
• project financing
• site selection and analysis
• site utilization and land-use
studies
• space management studies
• promotional services
PRE-DESIGN SERVICES
Method of Compensation
• multiple of direct expense
(cost per technical hour
with a multiplier)
DESIGN SERVICES
Design Development
• prepares plans, elevations and other
drawings, outline specifications
• illustrate the size and character of the project
• submits a further statement of probable
construction cost
Construction Phase
• prepares forms for contract letting, documents for
bidding and for construction
• assists owner in obtaining proposals from contractors
• decides on claims of owner and contractor
• periodically visits the project site to monitor general
progress
• issues Certificates of Payment
DESIGN SERVICES
Basic Fees based on Project Classification
Group I:
Group V:
exposition, fair buildings specialized decorative buildings
mausoleums, memorials, monuments structures of similar nature or use
museums
DESIGN SERVICES
Basic Fees based on Project Classification
Group VI :
Group VII:
housing projects- several units on a single site
Group VIII :
projects involving extensive detail such as furniture design, built-in equipment, special
fittings, screens, counters, interiors and other detailed parts of appurtenances of
buildings or structures and landscaping designs
DESIGN SERVICES
Group X:
opinions, advice, clarifications or explanation on
technical matters pertaining to the profession
DESIGN SERVICES
Payment Schedule
periodic cumulative
upon signing of agreement - 5% 5%
upon completion of schematic design services - 15% 20% based on
construction
upon completion of design development services - 15% 35% cost estimate
services include:
• interior design services
• acoustic, communication and electronic engineering
services
• landscape design services
• physical planning services
• comprehensive planning services
SPECIALIZED ALLIED SERVICES
interior design services
scope of services
full-time supervision
Quality control
Evaluation
• interpretation of contract documents
• getting information from the client • design modifications
• on-site observation • review change orders
• notify contractor of deviations • review payment requisitions
• follow-up corrective works • target project schedule vis actual
schedule
• storage, handling of materials
• samplings, tests
CONSTRUCTION SERVICES
full-time supervision
Rccords
• agreements, permits, licenses • daily inspection reports that include:
• progress and accomplishment reports - weather conditions
• change orders - manpower availability/distribution
• payments processed - construction activities
• as-built drawings/information - equipment utilization
• samplings, tests - correspondences
- decisions made
- official visitors
- observations/ recommendations
CONSTRUCTION SERVICES
legal responsibility
construction supervision group has none under the civil code
compensation
construction management
Coordination and supervision Cost and time control
• recommends general and specialty • programming, planning, scheduling
contractors
• on-site observation
• coordinates and supervises all
construction groups • pert cpm and cashflow
• approves methods and systems of • reviews change orders and payments
construction • storage, handling of materials
Quality control and keeping of records • samplings, tests
• functions of construction supervision
group become functions of the
construction manager
CONSTRUCTION SERVICES
construction management
legal responsibility
compensation
compensation
• salary basis
• management fee based on percentage: 4-6% of gross rentals
COMPREHENSIVE ARCHITECTURAL SERVICES
project management
pre-construction
• advice owner re design and cost implications
• periodic cost estimates
• early purchase of materials
• bidding documents; check bid packages for overlapping
jurisdictions; pre-bid conference; review owner’s stipulations with
the bidders
• sequencing and phasing of construction works
• general requirements and temporary facilities
COMPREHENSIVE ARCHITECTURAL SERVICES
project management
construction
• general coordination and scheduling of work
• supervision and inspection
• ensures compliance with drawings and specifications
• confer with architect for interpretation of documents
• conduct conferences among successful bidders and clarify matters
in dispute
• set-up organizational charts, lines of authority and communication
COMPREHENSIVE ARCHITECTURAL SERVICES
construction
• revise/refine estimates as construction proceeds
• establish procedures for processing shop drawings, catalogs, samples
• scheduling of material and cash requirements
• check adequacy of contractor’s labor and equipment
• be aware of contractor’s safety programs
• develop with owner and contractor labor relations program
• maintain records including cost accounting
COMPREHENSIVE ARCHITECTURAL SERVICES
construction
• progress reports, review applications for progress payments
•review requests for changes
•implement special client requirements regarding processing forms or job
conditions
•supply documents for handling claims or disputes
•advise owner to obtain site survey data
•set up joint interval and final inspections
COMPREHENSIVE ARCHITECTURAL SERVICES
legal responsibility
• project management group has none under the civil code
MANNER OF PAYMENT
• percentage of construction cost
• multiple of direct personnel expenses
• professional fee plus expenses
• lump sum or fixed fee
• per diem plus reimbursible expenses
• mixed methods of compensation