Coal USA

Coal Dust Mitigation Update

Surface Transportation Board – RETAC


September 10, 2009

Material from this presentation may not be used or reproduced without prior written consent of the BNSF
R il
Rain Impact on Ballast Contaminated
with Coal Dust

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 1
R il
Undercutter Work – Normal Ballast is
not Black

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 2
R il
Schematic of Typical BNSF/UP Dustfall
Collector Orin Subdivision Site

Service                     Road
Service                    Road
5 2 1

4 3

12’ 12’

35’

60’ 60’

Note: Distances
from centerline
of track will vary
N
slightly due to site
geography

Western  Eastern 
Track Track
Material from this presentation may not be used or reproduced without prior written consent of the BNSF 3
R il
Dustfall Collectors

z Measure amount of dust deposited in the railroad right-


of-way

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 4
R il
Trackside Monitor (TSM)

Propeller
MP 90.7 TSM Anemometer

Dust Monitor

Temperature/
Relative Humidity
Sensor

Data Logger

Precipitation Gauge

Dustfall Collector

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 5
R il
Trackside Monitors

z Measures dust emission of each passing train

z Locations:
z MP 90.7 on Orin Sub
z Towers on East and West sides of tracks
z Approximately 50% of trains useable
z MP 558.2 on Black Hills Sub
z Towers on North and South sides of tracks
z Approximately 75% of trains useable
z MP 693.4 on Big Horn Sub
z Data collection only at this time

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 6
R il
Post-Processing of Train Data

z Train Removal Criteria for Compliance Analysis


z Additional train (loaded or empty) passing TSM
site within 6 minutes
z High/Erratic background dust

z Bin data into proper wind components


z e.g., East dust monitor uses data with westerly
wind component
z e.g., West dust monitor uses data with easterly
wind component

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 7
R il
Coal Dust Train Measurement

Dust Values for Passing Train at


TrackSide Monitor
120
100
Dust Value

80
60
40
20 Train arrives at MP 90.7
0
-60 0 60 120 180 240 300
Time (Seconds)

Environmental
Train Passage at
Background
MP 90.5 According to
Dust
BNSF Train Data 8
Material from this presentation may not be used or reproduced without prior written consent of the BNSF
R il
Integrated Dust Value (IDV.2)

Dust Values for Passing Train at


TrackSide Monitor
120 Integrated Dust Value
Version 2 = 412
100
Dust Value

80
60
40
20
Train arrives at MP 90.7
0
-60 0 60 120 180 240 300
Time (Seconds)

Dust Value Threshold = 10 + Background Average


Front Diesel: Ignore
Environmental Train Passage at first 30 seconds of Rear Diesel: Ignore last
Background MP 90.5 According to values once dust signal 15 seconds of dust
Dust BNSF Train Data exceeds threshold signal > threshold
Material from this presentation may not be used or reproduced without prior written consent of the BNSF 9
R il
Improved Loading Profile

Redesigned Chute Normal Chute


Flared to 7 ft. wide 5 ft. wide
Same height as normal chute Promotes center peaked load
Promotes bread loaf shape Allows loading heights 3’ to 4 ‘
Limits height chute can be raised
above sill

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 10
R il
Impact of Modified Chutes

BEFORE AFTER
Note Peaked Loads, Sharp Lines, Note Rounded Contour, No Sharp
Steep Angle of Repose and other Angles, Flatter Angle of Repose and
irregular surfaces which are few irregular surfaces which are
susceptible to erosion susceptible to erosion

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 11
R il
Field Profile Audits

z Monthly unannounced audits


z Trains found not in compliance, provide mines
z Written report

z Photograph

z Video of train

z Audited 225 trains year to date

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 12
R il
RTEPS and Passive Collectors

RTEPS typically applied on last car of 
train with Passive Collector to 
determine external forcings (Wind 
Speed/Direction, Precipitation, Ambient 
Temp/RH, Coal Surface Temp, and Airborne 
Dust)

Passive Collectors applied in sets of 5 – 10 
to test effectiveness of dust suppression 
method compared to control technique

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 13
R il
Instrumentation

z Rail Transit Emission


Profiling System
(RTEPS)
z Airborne Dust Monitor
z Precipitation Gauge
z Ambient
Temperature/Relative
Humidity Sensor
z Propeller Anemometer
z Infrared Sensor for Coal
Surface Temperature
z Global Positioning System
z Passive Dust Collector
(PC)

Material from this presentation may not be used or reproduced without prior written consent of the BNSF 14
R il
Nacco Bridge – Undercut 2006

Coal has filtered down to the top of the bridge deck


Material from this presentation may not be used or reproduced without prior written consent of the BNSF 15