QS SHAREEF CONSTRUCTION TOPLINE ASSOCIATES BHARAT BUILDERS MKMS BUILDERS PERFECT BUILDERS CRYSTAL BUILDERS
Sl.No Description of Items Unit Quantity
Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount
A EXCAVATION & EARTH WORK
Excavation
1.1 At all levels and depths Cft 17,724.58 15.00 265,868.68 12.00 212,694.95 13.00 230,419.52 8.00 141,796.63 12.50 221,557.23 13.00 230,419.52 23.00 407,665.31
Filling - -
2 Back filling with available excavated earth Cft 13,273.74 8.00 106,189.92 5.00 66,368.70 8.00 106,189.92 4.00 53,094.96 7.50 99,553.05 15.00 199,106.11 10.00 132,737.40
Supply and fill with approved quality earth brougth out
Cft 4,901.82 30.00 147,054.71 35.00 171,563.82 20.00 98,036.47 26.00 127,447.41 - 45.00 220,582.06 73.00 357,833.12
3 from outside
4 Supply and fill with manufactured sand Cft - 75.00
5 Supply and fill with approved quarry dust -
5.1 For Foundations ans earth beams Cft 855.59 55.00 47,057.66 175.00 149,728.91 50.00 42,779.69 55.00 47,057.66 68.00 58,180.38 55.00 47,057.66 73.00 62,458.34
5.2 For Plinth / Floors Cft 1,336.38 55.00 73,500.63 155.00 207,138.13 50.00 66,818.75 55.00 73,500.63 70.00 93,546.25 55.00 73,500.63 73.00 97,555.38
Surface treatment -
7 Anti Terminte treatment Sft 6,138.00 10.00 61,380.00 15.00 92,070.00 7.00 42,966.00 10.00 61,380.00 12.50 76,725.00 7.00 42,966.00 8.00 49,104.00
-
SUB TOTAL 701,051.59 899,564.50 587,210.35 504,277.28 549,561.91 813,631.97 1,107,353.55
B CONCRETE WORKS -
Plain Cement Concrete 1:4:8 (Grade M 10), as described
-
1 using 40 mm metal
i Under Foundations & Earth Beams Cft 1,139.65 140.00 159,551.12 180.00 205,137.16 120.00 136,758.11 160.00 182,344.14 145.00 165,249.38 150.00 170,947.63 154.00 175,506.23
ii Under Floors Cft 1,780.05 140.00 249,207.21 175.00 311,509.01 120.00 213,606.18 160.00 284,808.24 148.00 263,447.62 155.00 275,907.98 154.00 274,127.93
Page 1 of 5
PROPOSED RESIDENTIAL APARTMENTS IN THE CAMPUS OF MASJID-E-ABDUL ALI AT THANDAVARAYAN STREET, PURASAIWAKKAM.
ARCHITECT: M.S.MUSHTAQ AHMED, CHENNAI
BILL OF QUANTITIES
QS SHAREEF CONSTRUCTION TOPLINE ASSOCIATES BHARAT BUILDERS MKMS BUILDERS PERFECT BUILDERS CRYSTAL BUILDERS
Sl.No Description of Items Unit Quantity
Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount
i At Stilt Floor Cft 2,886.44 250.00 721,609.03 225.00 649,448.12 240.00 692,744.66 220.00 635,015.94 245.00 707,176.84 270.00 779,337.75 257.00 741,814.08
ii At First Floor Cft 2,886.44 250.00 721,609.03 225.00 649,448.12 245.00 707,176.84 230.00 663,880.30 255.00 736,041.21 280.00 808,202.11 260.00 750,473.39
iii At Second Floor Cft 2,886.44 250.00 721,609.03 230.00 663,880.30 250.00 721,609.03 240.00 692,744.66 265.00 764,905.57 290.00 837,066.47 263.00 759,132.69
v At Terrace Floor Cft 206.63 250.00 51,656.25 235.00 48,556.88 255.00 52,689.38 250.00 51,656.25 275.00 56,821.88 300.00 61,987.50 266.00 54,962.25
3 For Lintel - - - -
i At Stilt Floor Cft 5.63 250.00 1,406.25 250.00 1,406.25 235.00 1,321.88 250.00 1,406.25 240.00 1,350.00 260.00 1,462.50 268.00 1,507.50
ii At First Floor Cft 118.31 250.00 29,578.13 255.00 30,169.69 240.00 28,395.00 250.00 29,578.13 245.00 28,986.56 270.00 31,944.38 271.00 32,062.69
iii At Second Floor Cft 118.31 250.00 29,578.13 260.00 30,761.25 245.00 28,986.56 250.00 29,578.13 250.00 29,578.13 280.00 33,127.50 274.00 32,417.63
v At Terrace Floor Cft 8.44 250.00 2,109.38 265.00 2,235.94 250.00 2,109.38 250.00 2,109.38 255.00 2,151.56 285.00 2,404.69 277.00 2,337.19
3.1 For Sunshade, Loft & Counter slabs - - - - -
i At Stilt Floor Cft 272.44 250.00 68,109.38 250.00 68,109.38 240.00 65,385.00 240.00 65,385.00 245.00 66,747.19 260.00 70,833.75 268.00 73,013.25
ii At First Floor Cft 272.44 250.00 68,109.38 255.00 69,471.56 245.00 66,747.19 250.00 68,109.38 250.00 68,109.38 270.00 73,558.13 271.00 73,830.56
iii At Second Floor Cft 272.44 250.00 68,109.38 260.00 70,833.75 250.00 68,109.38 260.00 70,833.75 255.00 69,471.56 280.00 76,282.50 274.00 74,647.88
v At Terrace Floor Cft 8.00 250.00 2,000.00 265.00 2,120.00 255.00 2,040.00 270.00 2,160.00 260.00 2,080.00 290.00 2,320.00 277.00 2,216.00
3.2 For Facia - - - - - -
i At Stilt Floor Sft 110.03 90.00 9,902.25 260.00 28,606.50 200.00 22,005.00 250.00 27,506.25 250.00 27,506.25 200.00 22,005.00 268.00 29,486.70
ii At First Floor Sft 81.00 90.00 7,290.00 270.00 21,870.00 210.00 17,010.00 250.00 20,250.00 275.00 22,275.00 210.00 17,010.00 271.00 21,951.00
iii At Second Floor Sft 81.00 90.00 7,290.00 270.00 21,870.00 220.00 17,820.00 250.00 20,250.00 300.00 24,300.00 230.00 18,630.00 274.00 22,194.00
-
SUB TOTAL 5,086,813.60 5,040,436.41 4,930,040.91 4,870,869.54 5,301,775.62 5,629,559.44 5,448,705.40
C REINFORCEMENT WORKS -
Steel reinforcement of Fe-500 grade in concrete works
MT 63.20 75000.00 4,740,257.39 68000.00 4,297,833.36 75000.00 4,740,257.39 68000.00 4,297,833.36 79500.00 5,024,672.83 70000.00 4,424,240.23 70000.00 4,424,240.23
1 including hooks, cranks, etc. as described.
The contractor shall submit his prices for the
reinforcements (fix only) for the steel supplied by the MT 22.00
Employer (Including cutting, bending, lifting and laying)
2
Page 2 of 5
PROPOSED RESIDENTIAL APARTMENTS IN THE CAMPUS OF MASJID-E-ABDUL ALI AT THANDAVARAYAN STREET, PURASAIWAKKAM.
ARCHITECT: M.S.MUSHTAQ AHMED, CHENNAI
BILL OF QUANTITIES
QS SHAREEF CONSTRUCTION TOPLINE ASSOCIATES BHARAT BUILDERS MKMS BUILDERS PERFECT BUILDERS CRYSTAL BUILDERS
Sl.No Description of Items Unit Quantity
Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount
i At Stilt Floor Sft 268.00 60.00 16,080.00 55.00 14,740.00 50.00 13,400.00 45.00 12,060.00 50.00 13,400.00 50.00 13,400.00 40.00 10,720.00
ii At First Floor Sft 268.00 60.00 16,080.00 60.00 16,080.00 52.00 13,936.00 45.00 12,060.00 55.00 14,740.00 55.00 14,740.00 42.00 11,256.00
iii At Second Floor Sft 268.00 60.00 16,080.00 65.00 17,420.00 55.00 14,740.00 50.00 13,400.00 60.00 16,080.00 60.00 16,080.00 44.00 11,792.00
1.7 For Sill slabs at all levels Sft 145.00 60.00 8,700.00 70.00 10,150.00 52.00 7,540.00 55.00 7,975.00 65.00 9,425.00 60.00 8,700.00 25.00 3,625.00
1.8 For Suspended Beam 60.00 - - - - -
i At Stilt Floor Sft 2,727.75 60.00 163,665.00 48.00 130,932.00 50.00 136,387.50 45.00 122,748.75 45.00 122,748.75 60.00 163,665.00 40.00 109,110.00
ii At First Floor Sft 2,727.75 60.00 163,665.00 53.00 144,570.75 52.00 141,843.00 50.00 136,387.50 50.00 136,387.50 65.00 177,303.75 42.00 114,565.50
iii At Second Floor Sft 2,727.75 60.00 163,665.00 56.00 152,754.00 55.00 150,026.25 55.00 150,026.25 55.00 150,026.25 70.00 190,942.50 44.00 120,021.00
v At Terrace Floor Sft 244.00 60.00 14,640.00 60.00 14,640.00 57.00 13,908.00 60.00 14,640.00 60.00 14,640.00 75.00 18,300.00 46.00 11,224.00
1.9 For Suspended Slab 60.00 -
i At Stilt Floor Sft 5,969.57 60.00 358,174.03 46.00 274,600.09 50.00 298,478.36 45.00 268,630.52 45.00 268,630.52 60.00 358,174.03 40.00 238,782.69
ii At First Floor Sft 5,969.57 60.00 358,174.03 50.00 298,478.36 52.00 310,417.49 50.00 298,478.36 50.00 298,478.36 65.00 388,021.87 42.00 250,721.82
iii At Second Floor Sft 5,969.57 60.00 358,174.03 54.00 322,356.63 55.00 328,326.20 55.00 328,326.20 55.00 328,326.20 70.00 417,869.70 44.00 262,660.96
v At Terrace Floor Sft 592.75 60.00 35,565.00 60.00 35,565.00 57.00 33,786.75 60.00 35,565.00 60.00 35,565.00 75.00 44,456.25 46.00 27,266.50
2 For Lintel
i At Stilt Floor Sft 20.25 60.00 1,215.00 60.00 1,215.00 50.00 1,012.50 45.00 911.25 50.00 1,012.50 60.00 1,215.00 40.00 810.00
ii At First Floor Sft 557.06 60.00 33,423.75 60.00 33,423.75 52.00 28,967.25 50.00 27,853.13 55.00 30,638.44 65.00 36,209.06 42.00 23,396.63
iii At Second Floor Sft 557.06 60.00 33,423.75 60.00 33,423.75 55.00 30,638.44 55.00 30,638.44 60.00 33,423.75 70.00 38,994.38 44.00 24,510.75
v At Terrace Floor Sft 33.75 60.00 2,025.00 65.00 2,193.75 57.00 1,923.75 60.00 2,025.00 65.00 2,193.75 75.00 2,531.25 46.00 1,552.50
2.1 For Sunshade, Loft & Counter slabs
i At Stilt Floor Sft
ii At First Floor Sft 1,089.75 60.00 65,385.00 60.00 65,385.00 50.00 54,487.50 40.00 43,590.00 45.00 49,038.75 60.00 65,385.00 40.00 43,590.00
iii At Second Floor Sft 1,089.75 60.00 65,385.00 63.00 68,654.25 52.00 56,667.00 50.00 54,487.50 50.00 54,487.50 65.00 70,833.75 42.00 45,769.50
v At Terrace Floor Sft 27.00 60.00 1,620.00 67.00 1,809.00 55.00 1,485.00 60.00 1,620.00 55.00 1,485.00 65.00 1,755.00 44.00 1,188.00
2.2 For Facia -
i At Stilt Floor Sft 110.03 70.00 7,701.75 65.00 7,151.63 50.00 5,501.25 50.00 5,501.25 50.00 5,501.25 110.00 12,102.75 40.00 4,401.00
ii At First Floor Sft 81.00 70.00 5,670.00 65.00 5,265.00 52.00 4,212.00 60.00 4,860.00 55.00 4,455.00 110.00 8,910.00 42.00 3,402.00
iii At Second Floor Sft 81.00 70.00 5,670.00 65.00 5,265.00 55.00 4,455.00 70.00 5,670.00 60.00 4,860.00 110.00 8,910.00 44.00 3,564.00
-
SUB TOTAL 2,653,130.10 2,382,091.71 2,333,917.74 2,180,314.77 2,223,851.02 2,753,483.67 1,652,129.09
E MASONRY WORKS
First quality machine moulded chamber brick masonry
1 230 mm thick
i In Sub-Structure Cft 511.45 170.00 86,947.03 160.00 81,832.50 160.00 81,832.50 180.00 92,061.56 190.00 97,176.09 190.00 97,176.09 244.00 124,794.56
ii In Stilt Floor Cft 359.81 175.00 62,967.19 170.00 61,168.13 165.00 59,369.06 190.00 68,364.38 200.00 71,962.50 200.00 71,962.50 244.00 87,794.25
iii In First Floor Cft 2,961.47 180.00 533,064.38 175.00 518,257.03 170.00 503,449.69 200.00 592,293.75 210.00 621,908.44 210.00 621,908.44 247.00 731,482.78
iv In Second Floor Cft 2,961.47 185.00 547,871.72 175.00 518,257.03 175.00 518,257.03 210.00 621,908.44 220.00 651,523.13 220.00 651,523.13 250.00 740,367.19
vi In Terrace Floor Cft 1,154.25 195.00 225,078.75 180.00 207,765.00 180.00 207,765.00 220.00 253,935.00 230.00 265,477.50 230.00 265,477.50 253.00 292,025.25
vii For Stairs & Steps Cft 160.00 200.00 32,000.00 190.00 30,400.00 200.00 32,000.00 200.00 32,000.00 215.00 34,400.00 250.00 40,000.00 256.00 40,960.00
First quality machine moulded chamber brick masonry
2 115 mm thick
Page 3 of 5
PROPOSED RESIDENTIAL APARTMENTS IN THE CAMPUS OF MASJID-E-ABDUL ALI AT THANDAVARAYAN STREET, PURASAIWAKKAM.
ARCHITECT: M.S.MUSHTAQ AHMED, CHENNAI
BILL OF QUANTITIES
QS SHAREEF CONSTRUCTION TOPLINE ASSOCIATES BHARAT BUILDERS MKMS BUILDERS PERFECT BUILDERS CRYSTAL BUILDERS
Sl.No Description of Items Unit Quantity
Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount
i In Stilt Floor Sft 105.00 - 110.00
ii In First Floor Sft 1,671.88 110.00 183,906.25 75.00 125,390.63 110.00 183,906.25 120.00 200,625.00 80.00 133,750.00 130.00 217,343.75 162.00 270,843.75
iii In Second Floor Sft 1,671.88 115.00 192,265.63 80.00 133,750.00 115.00 192,265.63 130.00 217,343.75 90.00 150,468.75 140.00 234,062.50 165.00 275,859.38
v In Terrace Floor Sft 457.50 125.00 57,187.50 85.00 38,887.50 120.00 54,900.00 140.00 64,050.00 100.00 45,750.00 150.00 68,625.00 168.00 76,860.00
QS SHAREEF CONSTRUCTION TOPLINE ASSOCIATES BHARAT BUILDERS MKMS BUILDERS PERFECT BUILDERS CRYSTAL BUILDERS
Sl.No Description of Items Unit Quantity
Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount
Providing and laying granolithic flooring 25mm thk in CM
Sft 6,071.81 40.00 242,872.50 110.00 667,899.38 50.00 303,590.63 45.00 273,231.56 55.00 333,949.69 120.00 728,617.50 265.00 1,609,030.31
11 1:4