CONSTRUCTION DAILY REPORT

KAIZERN CONST. & DEV'T CORP.


Construction of Sump Pit, Pump Base, Pump Sunction Area, & Bunk House
Brgy. Tinoto, Maasim, Sarangani

Daily progress report no. SRN-001 Date: 11 Feb 20


Weather: Sunny

Works in progress
1. Excavation of the Sump Pit.
2. Connecting the steel flange unto the steel pipes.
3. Bending & fabrication of the 12 mm Ø bar reinforcement of the Sump Pit.
4. Drafting of the proposed plan of the Bunk House and Comfort Room as per Mr. Winston Ferolin with
Engr. Julie Ramos and Mr. Brian Osano (Listing of all the materials needed for the construction of the
bunk house and C.R.)

Issues, field problems encountered/solutions and recommendations, if any.

Manpower and equipment


Quantity Name Skill
1 Adolfo Montelde Back Hoe Operator
1 Gilbert Abadines Dump Truck Operator
1 Fidel Lascoña Welder

Highlights of events and activities.


Excavation of the Sump Pit.

Visitors at site, if any.


Mr. Winston Ferolin
Mr. Roger "Tot's" Lim Jr.
Mr. Potcholo Ticsay
Mr. Brian Osano

Additional information/queries

Remarks
BEFORE AFTER

Excavation of the Sump Pit

BEFORE AFTER

Connection of steel Flanges

Bending of reinforcement bar BEFORE

AFTER

Bending & Fabrication of Reinforcement for the Sump Pit

Prepared by: Checked by: Noted by:

Engr. Stephen Harold Engr. James Anthony Mr. Jay S. Llavan, COO
T. Rayoso, CPE Romaguera, OIC