SISON JIMENEZ AND GROUP

PROPOSED 3-STOREY RESIDENCE COMPANY LOGO


Brgy Malimpuec, Lingayen
DAILY PROGRESS REPORT
Weather SUNNY CLOUDY RAINY Report Date: 20-Apr-22
Wind STILL MID HIGH Report No.: DR No.008
Temp °C 0-20 20-35 35-50 Type of Work: Structural
Start date: 8-Apr-22 No. of days completed:

TARGET ACTUAL
SN DESCRIPTION REMARKS
Qty Unit Qty Unit
1 Rebar installation for Footings kgs kgs In Progress
2 Rebar installation for Columns kgs kgs In Progress

3 Stripping of formworks for neck columns 7.02 m2 7.02 m2 In Progress


4 Preparation of formworks for neck columns 4.68 m2 4.68 m2 In Progress
Concrete pouring for neck colums (located at 0.36 m3 0.36 m3 In Progress
5 A2, A3)
6 Concrete pouring for footings (located at C2, 3.60 m3 3.60 m3 In Progress
C3, C4)

MANPOWER UTILIZATION
Time No. of
MANPOWER DESIGNATION Qty Remarks
Start End Hours
Skilled 1 7:00 4:00 8
Labor 4 7:00 4:00 8

EQUIPMENT/MACHINERIES IN USE
EQUIPMENT/TOOLS Qty Unit Area Remarks
Shovel 3 item Foundation
Nylon 1 roll Foundation
Cutter 1 Item Foundation
Handsaw 1 Item Foundation
MATERIALS SUMMARY
DESCRIPTION Qty Unit Area Remarks
16 mm dia. rebar Pcs Foundation
12 mm dia. rebar Pcs Foundation
10 mm dia. rebar Pcs Foundation
Metal wire roll Foundation
Phenolic board Pcs Foundation
KEYPLAN AND ACTUAL PHOTOS

Legend:
Excavation of Foundation

Concrete pouring as of today

Concrete pouring (previously done)

Installation of reinforcement steel bars

Stripping of formworks

Concrete Mixing

Excavation of foundation

Concrete pouring for footings and neck columns


Concrete pouring for footing

Stripping of formworks Backfilling of soil

Installation of reinforcements