Exercise 5 - Network Diagram and Critical Path PDF
Exercise 5 - Network Diagram and Critical Path PDF
Questions:
Mark the critical path and state it’s length for each of the following cases.
Case 1:
predecessor
No Task name Durations/Days Start Finish
5 B 5
10 M 4 B
15 N 9 B
20 Q 15 B
25 A 1 M,N
30 F 4 N,Q
35 X 9 Q
40 C 9 Q
45 Y 9 A,F,X
50 S 6 F
55 J 5 X,F
60 T 10 C
65 V 5 Y,S
70 U 10 V,T,J
CCQ Page 1 of 4
Case 2:
predecessor
No Task name Durations/Days Start Finish
5 A 1
10 B 8 A
15 C 4 A
20 P 7 A
25 L 2 B
30 M 4 C
35 Q 4 P,C
40 N 9 P
45 Y 5 L,Q
50 F 10 M
55 J 2 Q
60 S 2 N
65 V 5 Y,F,J
70 Q1 1 V,S
CCQ Page 2 of 4
Case 3:
predecessor
No Task name Durations/Days Start Finish
5 B 5
10 M 4 B
15 N 9 B
20 X 15 B
25 A 5 M,N
30 F 6 N,X
35 Q 2 X
40 C 4 X
45 Y 10 A
50 S 10 F,A
55 R 2 Q,F
60 T 5 C,Q
65 K 7 Y,S,R
70 U 3 K,T
CCQ Page 3 of 4
Case 4:
predecessor
No Task name Durations/Days Start Finish
5 A 9
10 B 1 A
15 C 10 A
20 P 10 A
25 L 2 B,C
30 F 10 C,P
35 Q 8 P
40 N 6 P
45 Y 7 L
50 T 4 F,L
55 R 9 F,Q
60 S 1 N,Q
65 V 10 Y,T,R
70 U 1 V,S