TOYOTA GATEWAY PHANOM SARAKHAM
SUBSTATION SUBSTATION
SD 2×400 = 33 km
1YB‐01
600 ms
ZONE3 100% OF SECTION1 + 120% OF SECTION2 TIME OPERATE = 600 ms
300 ms
ZONE2 100% OF SECTION1+ 50% OF SECTION2 TIME OPERATE = 300 ms
0 ms
ZONE1 85% OF SECTION1 TIME OPERATE = 0 ms
SYSTEM DATA
LINE IMPENDANCE
Z1 = 0.271121357 Ohm/km
Z0 = 1.346430021
Z0 = 26.1207424 Ohm
= 1606.5 A
LOAD BLINDING
ZONE 1 REACH
So set :
GROUP 1 DIST. ELEMENTS
ZONE 2 REACH
So set :
GROUP 1 DIST. ELEMENTS
ZONE 3 REACH
So set :
GROUP 1 DIST. ELEMENTS
ZONE 4 REACH
So set :
GROUP 1 DIST. ELEMENTS
ZONE PSB
UNDER CURRENT
POLEDEAD VOLTAGE
V< (3V0) = 30 % Un
AUTORECLOSE
Dead Time 1 = 1 S
AR CBHealthyTime = 5 S
Reclaim Time = 5 S
AR Inhibit Time = 10 S
AR CheckSyncTime = 10 S
VT Fail
VT Fail Timer = 5 s
V0 detaction = 10 % Un
3V0 detaction = 30 % Un
SOTF
SOTF Delay = 10 s
SYSTEM DATA
Direction = forward
Direction = forward
20 OF 27
CT AND VT RATIOS
Main VT Primary 115 kV
Main VT Sec'y 115 V
CS VT Primary 115 kV
CS VT Secondary 115 V
Phase CT Primary 1200 A
Phase CT Sec'y 1 A
SEF CT Primary 1200 A
SEF CT Secondary 1 A
MComp CT Primary 1200 A
MComp CT Sec'y 1 A
CS Input BN
Main VT Location Line
CT Polarity Standard
SEF CT Polarity Standard
M CT Polarity Standard
VT Connected Yes
WI Inhibit Disabled