Kwh Summary Report

From: 30-Mar-20
Locations KWH
Utility ( SSC -1) 8.00
Plant ( SSC -1) 5.00
Difference 3.00
1)WBL-1 Feeder 0.00
2)Coil feed line 0.00
3)Press 0.00
4)Magnetic Stacker 0.00
5)Panel Ac(WBL-1) 0.00
WBL-1 Machine (TOTAL) 0.00
1)NBL-1 0.00
2)NBL-2 0.00
3)EOT 1/3 0.00
4)EOT 2/4 0.00
5)EH-01 0.00
6)Sharing-1 0.00
7)Tool room 0.00
8)Shade light 0.00
9) MBL(main) 0.00
WBL-01 Feeder Total 0.00
1)Slitting Line 0.00
2)PBL-1 0.00
3)EOT-5/6/7 0.00
4)PBL-2 0.00
5)CTL 0.00
6)New office light 0.00
Slitting Feeder Total 0.00
Total of Locations 0
Transmition Loss from Utility to Plant 37.50%
Transmition Loss from Plant to Machines 100.00%
Total Transmition 137.50%
Kwh Summary Report
To: 31-Mar-20
Locations KWH
Locations KWH
Utility(SSC-2) 0.00
1)Uncoiler+Leveller 0.00
2)MMC-2 Panel+OSL Shear Panel 0.00
3)Unico Drive System 0.00
4)Press 400 Ton 0.00
5)MCC-1 Panel 0.00
6)Piler Magnet 1&2 0.00
Total WBL-2 Machine 0.00
7)EOT-08 0.00
8)Lighiting Panel 0.00
Total 0.00
Total of 8 Locations 0.00
Total Transmition Loss SSC-2 (Utility to Machines) -
SSC-01 Compressor 0.00
Corporate office DG Room
256.00
8)Compressor (LPS A+SSC-I) 0.00
Diffrence 0.00