Professional Documents
Culture Documents
1. INTRODUCTION
Ever since beginning of the civilization, man has attempted to improve
productivity of his limited resources in order to maximize creation of wealth, which is
essential for survival and enjoyment of the life. His first resources were manpower
and animal power and then he created hand tool and later the machines and the
machine tool to improve the productivity of manpower. The continued pursuit of
higher productivity, Industrial engineer seeks to maximize the performance of
incentive man-machine-material.
Productivity Concept & Definition:
Productivity is a quantitative relation between what we produce, what we use
& a resource to produce them, i.e. arithmetic ration of amount of produce (output) to
the amount of resource (input).
Productivity refers to efficiency of the production system. It is the concept that
guides the management of the production system. It is the indicator of how well the
factors of production (land, capital, labour, energy, material) are utilized.
“Total Productivity is the ratio of the aggregate input. Partial productivity is the ratio
of the aggregate output to any single input.”
The basic objectives behind productivity measurement are:
To study performance of a system over time.
To attain a relative comparisons of the different system for a given levels.
To compare the actual productivity of a system with its planned productivity
IDENTIFING PROJECT
SCOOPE & METHODOLOGY
SLP
DATA TOOLS
COLLECTION
DATA ANALYSIS
Objectives:-
To increase the capacity of the assembly, Testing, Painting line from 180 compressors
per month to 300 compressors per month working on one-shift basis.
Specific Objectives:
To increase productivity in Assembly, testing and painting area.
To achieve due dates i.e. Lead time reduction.
To minimize backtracking & cross-traffic.
To achieve single piece flow.
To introduce safe working conditions.
Optimum utilization of manpower.
To minimize work in progress in inventory in the shop.
2. COMPANY PROFILE-
Kirloskar Pneumatic Co. Ltd was established in 1961 started with manufacture of Air
compressors and Pneumatic Tools. Thereafter, the company expanded its activities in
the field of Air Conditioning, Refrigeration and Hydraulic Power Transmission
equipment.
At present, the company has three Strategic Business Units (SBU) viz.:
1. Air Compressor SBU (ACD) for manufacture of Air & Gas Compressors.
2. Air Conditioning & Refrigeration SBU (ACR).
There are three business units in this SBU viz. ACR equipment, Process Gas
Systems & Refrigeration Systems which manufactures Refrigeration
Compressors /Packages.
3. Transmission SBU (TRM) which is engaged in manufacture Power Transmission
for Locos, Industrial Gearboxes, Marine Gearboxes, Windmill Gearboxes, Power
Packs.
Saswad plant was established in 1985, popularly known as KPCL; spread over 64
acres of land. KPCL is India’s leading manufacturing of the finest and widest range of
Refrigeration compressors.
1. Reciprocating Type Refrigeration compressors (KC Series) (50-500 TR).
2. Reciprocating Type Refrigeration compressors (KCX Series) (50-200 TR).
3. Reciprocating Type Refrigeration compressors (PC-2) (50 TR).
4. Air-conditioning compressors (AC-FK Series) (5-175 TR).
The Annual manufacturing volumes exceed 1800 Refrigeration Compressors and are
available in both air-cooled and water-cooled version.
Annual Turnover of the KPCL ACR Equipment Division in year 2010-2011 is
97.65cr.
KC 2,3,4,6,9,12
Water Cooled cylinders in Single
KC (50-500 TR)* or two-stage.
Total 15 in no.
Water Cooled
AC (50- 175TR)* 9 model
APPLICATION:-
1. Beverages, Breweries & Bottling units
2. Fish &Meat Processing
3. Vegetable cold Storages
4. Dairy & Milk Processing Units
5. Ice Plants / Chemicals / Pharmacy
To, alleviate complexity of design an assembly line; an assembly line is subdivided into
number of logical or physical sections. The design team usually include member from several
department; each responsible for one or more sections. The subdivision method and the
definitions of the section are the application dependent.
From analytical point of view it is convenient to sub divide a line a number of section,
and deal with individual sections separately. On the other hand a section must be designed in
integrated manner. To achieve design integration, interrelated components must be designed
in integrated components must be considered under the same design function. Five such
functions are identified:
The relation between line section and function is given below in table.
Process design X X
Line balance X
Test strategy X X X X
Yield management X X X
Material handling X X
Maintenance policy X X X
Line size X
Line layout X
Information system X X X X X
Line balancing is commonly technique to solve problems occurred in assembly line. Line
balancing is a technique to minimize imbalance between workers and workloads in order to
achieve required run rate. This can be done by equalizing the amount of work in each station
and assign the smallest number of workers in the particular workstation. Here the job is
divided into small portion called “job element” .The aim is to maintain production at an equal
rate. Line balancing operates under two conditions:
Precedence Constraint.
Products can’t move to other station if it doesn’t fulfill required task at that station. It
shouldn’t across other station because certain part needs to be done before others.
Cycle time is maximum time for products spend in every workstation. Different workstation
has different cycle time.
The mixed-model sequencing problem (MSP) aim to minimize work overload, finding
sequences where models with longer and shorter processing times alternates. In order to
develop an efficient sequence models are scheduled at each station and cycle, by explicitly
taking into account processing times, workers movements, station borders and further
operational characteristics of the line.
Approach Planning horizon Level of decision making Main concern and aim
Mixed Mid or long term High level, with consideration Installation of line,
model to the strategic goals of the rebalancing, dividing
balancing company and the production work between stations.
over a few years.
Finding a sequence of
models through a
Mixed Short term Operation level, with
detailed scheduling of
model consideration of shop floor
work content in order to
sequencing and the daily production.
minimize: work over
loaded or throughput
times etc. High intensive
models alternate with
less intensive models.
To assure that the line appropriately designed, line measurement is established to understand
design effectiveness. Measurement can be classified into two categories cost & line
performance.
Line measure is derived from workstation capacity, yield, line scheduling policy, job
dispatching policy, parts availability, and line layout and material handling method. Several
different measures should be used to complete line performance evaluation as follows.
Takt time = T / D
Where,
2. Through put time: - This is the total amount that a product spends in the line,
including waiting and rework. Lead time is also an important parameter for material
requirement planning..
3. Work station utilization:-This is the proportion of time that a station is busy doing
useful work. For a well balanced line, all workstation should have approximately the
same utilization. If the time line is running at full speed, workstations utilization will
be close to one. The average workstation utilization is defined by,
n
1
W = ∑ risi
n i=1
Where,
n = Number of workstations
V = (PS / NT)
Where,
N- Number of operators
5. Balance delay:
Balance delay is the efficiency index and is the amount of idle time expressed as a
percentage of actual production time of the line. Science the output of the line is
determined by the slowest workstation time multiplied by number of workstation
hence,
n
( n . Sm )−∑ Si
i=1
D=⌈ ⌉∗100 %
n . Sm
Where,
D= Balance delay.
n = Number of stations.
6. Line efficiency: - This will carried out to find effectiveness or utilization of line.
Higher the utilization percentage better is the resource utilization and efficiency.
Line Efficiency =
∑ of Task time
No . of workstation∗Takt time
3.3Ergonomics [7]
Ergonomics is the scientific study of people at work. The goal of ergonomics is to reduce
stress and eliminate injuries and disorders associated with the overuse of muscles, bad
posture, and repeated tasks. This is accomplished by designing tasks, work spaces, controls,
displays, tools, lighting, and equipment to fit the employee’s physical capabilities and
limitations. Proper ergonomic design is necessary to prevent repetitive strain injuries, which
can develop over time and can lead to long-term disability
Following are the protocols available for videotaping the task: [13]
To verify the accuracy of the video camera to record in real time, Videotape a worker
or job with a stopwatch running in the field of view for at least 1 min. The play-back
of the tape should correspond to the lapsed time on the stopwatch.
Announce the name of the job on the voice channel of the video camera before the
aping of any job. Restrict running time comments to the facts. Make no editorial
comments.
Tape each job long enough to observe all aspects of the task. Tape 5 to 10min for all
jobs, including at least 10 complete cycles.
Fewer cycles may be needed if all aspects of the job are recorded at least 3 to 4 times.
This term is related with flow of manufacturing. Batch & Queue Vs lean flow: Batch
and Queue is mass production approach and its opposite of the single piece of flow in the
lean environment. It is important to understand the activities which are the value added, Non
value added required non value added, waste to the product.
4. METHODOLOGY:
PQ Analysis
Operation sequence
Video analysis.
Fig.8 PQ analysis
Product (or material) means: (what is to be made or produced?). The products
produced by the company or area in question, the starting materials or purchased parts,
the formed or treated parts and the finished goods. Products may be termed as items,
varieties, models, styles. Part numbers, formulations, or product groups.
Sr.
No Description No. Compressor type
KC2 KC3 KC4 KC6 KC9 KC12
1 No. of Cylinder 2 3 4 6 9 12
2 Cylinder Bore mm 160 160 160 160 160 160
3 Piston Stroke mm 110 110 110 110 110 110
4 Cylinder Arrangement 1xv 1xw 2xv 2xw 3xw 4xw
5 Direction Of Rotation Anticlockwise Looking from Flywheel end
Quantity (or volume) means: (how much of each item is to be made?). The
amount of products or material produced or used. Quantity may be termed as number
of pieces, tons, cubic volume, or value of the amount produced or sold.
350
300
250
200
150
100
50
0
-2
KC 3
KC 4
KC 6
-9
12
84
93
KC 2
KC 3
KC 4
KC 6
9
1
KC 2
1
KC 3
2
-
X
-2
-3
-4
-5
-6
-7
X
X
X
X
KC
KC
KC
KC
KC
KC
KC
KC
KC
KC
P and Q are the two basic element on which the problem rests. These two elements
underlie all other Features and conditions in layout work. Therefore facts, estimated or
information about these two elements are estimates, or information about these two elements
are essential.
It is outline process chart. It gives us bird view of the entire products process. Whole process
is recorded only major process i.e. operation & inspection.
Fig.11 Exiting Layout of ATPP [Assembly, Testing, Painting, and Packaging] line
1. Operator movement.
2. Non value added activities
3. Activities that can be done in the sub assembly area or offline.
4. Activities in the assembly process that can be atomized
5. Mark the areas of improvement and possible solution for that activity.
6. Tool, gauges, equipment used.
7. Workstation layout
8. Unsafe activities from ergonomic point of view
9. Precedence of compressor assembly process
Table 6 Summary of Existing - Activity wise Work stations & Cycle time For KC4
50.00
Work station Time
40.00
35
30.00 28.70
20.00
10.00
0.00
1 2 3 4
Chart 2
5.2.2Line Balancing:
Therefore in this our case maximum production of compressor is of KC- 4 and out of total
production there is 70% is of up to KC – 4. So Line is balance for averaged model is KC 4
Production volume:
Summary of Proposed - Activity wise Work stations & Cycle time For KC4 (Table
9):
40.00
35.00
30.00
Work Station Time
25.00
20.00
WS Time
15.00
Takt Time
10.00
5.00
0.00
1 2 3 4
Work station No.
Chart 3
Summary of Proposed - Activity wise Work stations & Cycle time For All models
(Table 10)
Activity
KC2 KC3 KC4 KC6 KC9 KC12
A ORV fitting
B Stud fitting on B'Cover Pump & FW end
C B'cover tight ting FW end
D C'shaft-fitting
B'cover tight ting pump end & check
28.5 31.8 34.7 40.0 45.2 52.7
E clearance
F counter weight fitting
P Oil level glass fitting
Q Stud fitting on Pump & shaft seal
R oil pump & shaft seal Tightening
G check clearance by depth gauge
H Gasket selection & put gasket in cly head
I Manual Liner fitting
J Liner fitting to c'case 18.7 25.3 32.0 45.3 78 89.9
K VLD fitting
O Safety valve fitting
S strainer side cover fitting
L piston con rod assy fitting on c'case
M Inspection top clearance of piston
N Inspection con rod 18.4 27.5 34.3 52.0 68.8 96.4
T stud fitting on cly head
W side cover fitting
U Remain. Stud fitting on cyl head
10.6 22.9 34.9 43.4 64.0
V cylinder head fitting 15.3
X Piping
In order to develop an efficient sequence models are scheduled at each station and
cycle, by explicitly taking into account processing times, workers movements, station
borders and further operational characteristics of the line.
If several work intensive models follow each other at the same station, the cycle time
might be exceeded and an overload occurs, which needs to be compensated by some kind of
reaction. These overloads can be avoided if a sequence of models is found where those
models which cause high station times alternate with less work-intensive ones at each station.
Work Activity
station KC2 KC3 KC4 KC6 KC9 KC12
A ORV fitting 28.5 31.8 34.7 40.0 45.2 52.7
Panting line:
At KPCL, All models of compressor and accessory painting are carried out on single paint
booth. These panting of compressor is done in batches, cause in crisscross movement and
backtracking of man as well as material which is manual and unsafe for material handling.
Thinner application for cleaning of compressor and accessory which is unsafe in condition
and also from environmental act, So to avoid this introduction of water base spray
degreasing and stage wise panting should be done.
Following are the areas of improvement in future assembly line with reference to present
assembly line:
1. With reference to the time study there is further scope in line balance improvement
2. Maximum sub assemblies can be done in sub assembly area outside the main line
therefore saving operator time on line
3. At present almost all component excluding c-class items e.g. fasteners, washers etc
are supplied in two service trolleys on booth side of main assembly line. This material
supply can be improved by increasing line side storage area
Snapshot 1
Snapshot 2
Snapshot 3
All common parts for compressor models are kept on line side storage area, the model
specific parts are placed in single trolley. The single kit trolley for each compressor can be
placed on main line. For finalization of the concept both kit trolley behind the operator & kit
trolley on main line are compared as under
Sr.
No.
Kit trolley behind operator Cat Kit trolley on main line Cat
4 Additional power required driving D Power required will 50% less than A
kit trolley system slat conveyor
7 Floor spaced get blocked with kit D Floor spaced is not getting blocked A
trolley at the backside of stage
Expected
Sr. No. Activity Concern Recommendations benefit
Elimination of
Wastage of lot of NV activity of
1 Selection of liner time in selection measuring the
gasket of required of required size Colour Coding as thickness of
size gasket pre size gasket
2 Storage of gasket Sagging of gasket Non metallic ID NO sagging of
locator for gasket gasket
Supply of Supply crankshaft Reduce
3 crankshaft to Supply of crank by dedicated Fatigue
assembly shaft by pallet trolley
Storage of common
Storage of Reduction in
components into
7 common Stored in rack plastic Bin located work content
components kept away from near individual (parts collection
work station stations. time)
Introduction of
Use of pneumatic electric, hydro
impact wrench pulse, Clutch shut Better joint
8 Fasting process
almost at all off tools &torque accuracy
location wrenches based on
the torque sheet
data
Use of mallets.
Non- Elimination of
9
Tapping on use of metallic metallic(nylon) dents, chips &
components hammer hammer unsafe act
Use of dedicated
trolley for Fly Safe & Quick
10 Fitment of Use of hoist wheel with up fitment of
flywheel on crank down & sliding flywheel on
shaft for testing arrangement crank shaft
Use of thinner for Unsafe condition
11 cleaning of & act, Introduce water Elimination of
compressor prior Environmental based spray thinner for
to painting aspects degreasing. cleaning purpose
Basic
12 Facilities for No facility for provide eye wash requirement of
cleaning eyes eye wash facility paint facility
One of the most powerful tools can use for improving productivity is that of Work study aims
at examining the way an activity is being carried out, simplifying the method of operation to
reduce unnecessary or excess work, or the wasteful use of resources.
Line balancing focus on avoiding inefficiencies and station times of variants have to be
smoothed for each station, horizontal balancing for improve productivity.
Chart 4
Chart 5
Chart 6
Chart 7
Chart 8
8. REFERENCES:
2 Bill Carreir, “Lean manufacturing that works. Powerful toll for dramatically reducing
waste & maximizes profits”, American management association New York, 2005.
4 JHF Sawyer, “Line Balancing”, first edition, The machinery publishing Co. Ltd.
1970.
8 Nils Boysen, Malte Fliedner, Armin Scholl (2007), “Assembly line balancing: Which
model to use when?” Science Direct Int. J. Production Economics 111. PP. 509–528.
10 Productivity Development Team “Cellular Manufacturing one piece flow for work
team” Productivity press Portland, Oregon 1999
12 We - Min chow, “Assembly line Design”, Marcal Dekker, And INC New York. 1999
.
13 Webliography:
ANNXEURE-A
ANNXEURE-B
ANNXEURE-C