The daily report from the Power Grid Company of Bangladesh provides key information from April 17th, including:
- Maximum generation was 9,358 MW at 19:30 hours while maximum demand was 9,800 MW (expected for the evening).
- No load shedding occurred across areas like Dhaka, Chittagong, Khulna, etc.
- Forced outages included units at Barapukuria, Siddhirganj, Ghorasal, Ashuganj power plants, and transformers at Kaptai and Meghnaghat.
- Planned maintenance resulted in temporary power interruptions for areas like Sylhet, Naogaon and Bogura.
The daily report from the Power Grid Company of Bangladesh provides key information from April 17th, including:
- Maximum generation was 9,358 MW at 19:30 hours while maximum demand was 9,800 MW (expected for the evening).
- No load shedding occurred across areas like Dhaka, Chittagong, Khulna, etc.
- Forced outages included units at Barapukuria, Siddhirganj, Ghorasal, Ashuganj power plants, and transformers at Kaptai and Meghnaghat.
- Planned maintenance resulted in temporary power interruptions for areas like Sylhet, Naogaon and Bogura.
The daily report from the Power Grid Company of Bangladesh provides key information from April 17th, including:
- Maximum generation was 9,358 MW at 19:30 hours while maximum demand was 9,800 MW (expected for the evening).
- No load shedding occurred across areas like Dhaka, Chittagong, Khulna, etc.
- Forced outages included units at Barapukuria, Siddhirganj, Ghorasal, Ashuganj power plants, and transformers at Kaptai and Meghnaghat.
- Planned maintenance resulted in temporary power interruptions for areas like Sylhet, Naogaon and Bogura.
DAILY REPORT Page -1 Reporting Date : 17-Apr-20 Till now the maximum generation is : - 12893 MW 21:00 Hrs on 29-May-19 The Summary of Yesterday's 16-Apr-20 Generation & Demand Today's Actual Min Gen. & Probable Gen. & Demand Day Peak Generation : 6516.4 MW Hour : 12:00 Min. Gen. at 8:00 5703 MW Evening Peak Generation : 9358.0 MW Hour : 19:30 Available Max Generation : 15845 MW E.P. Demand (at gen end) : 9358.0 MW Hour : 19:30 Max Demand (Evening) : 9800 MW Maximum Generation : 9358.0 MW Hour : 19:30 Reserve(Generation end) 6045 MW Total Gen. (MKWH) : 160.8 System Load Factor : 71.61% Load Shed : 0 MW EXPORT / IMPORT THROUGH EAST-WEST INTERCONNECTOR Export from East grid to West grid :- Maximum -149 MW at 5:00 Energy MKWHR. Import from West grid to East grid :- Maximum - MW at - Energy - MKWHR. Water Level of Kaptai Lake at 6:00 A M on 17-Apr-20 Actual : 79.79 Ft.(MSL) , Rule curve : 84.80 Ft.( MSL )
Gas Consumed : Total = 1083.76 MMCFD. Oil Consumed (PDB) :
HSD : Liter FO : Liter
Cost of the Consumed Fuel (PDB+Pvt) : Gas : Tk141,019,577
: Coal : Tk70,483,155 Oil : Tk62,381,004 Total : Tk273,883,736
Load Shedding & Other Information
Area Yesterday Today
Estimated Demand (S/S end) Estimated Shedding (S/S end) Rates of Shedding MW MW MW (On Estimated Demand) Dhaka 0 0:00 3474 0 0% Chittagong Area 0 0:00 1178 0 0% Khulna Area 0 0:00 1055 0 0% Rajshahi Area 0 0:00 953 0 0% Cumilla Area 0 0:00 861 0 0% Mymensingh Area 0 0:00 695 0 0% Sylhet Area 0 0:00 393 0 0% Barisal Area 0 0:00 179 0 0% Rangpur Area 0 0:00 536 0 0% Total 0 9324 0
Information of the Generating Units under shut down.
Additional Information of Machines, lines, Interruption / Forced Load shed etc.
Description Comments on Power Interruption
a) Sylhet 132/33 kV T-2 transformer was under shut down from 10:10 to 10:20 for ICSR testing. About 8 MW power interruption occurred under Sylhet S/S area from 10:10 to 10:20. b) Naogaon 132/33 kV T-2 transformer was under shut down from 09:35 to 12:10 for red hot maint. About 18 MW power interruption occurred under Naogaon S/S area at 33 kV out going Y-phase . from 09:35 to 12:10. c) Bogura(old) 132/33 kV T-3 transformer was under shut down from 09:32 to 13:14 for red hot maint. at 132 kV CT. d) Bogura(old) 132 kV main Bus was under shut down from 10:25 to 14:22 for maintenance work. e) Ishurdi 230/132 kV T-01 transformer was under shut down from 11:36 to 12:23 for C/M. f) Meghnaghat-Aminbazar 230 kV Ckt-1 was under shut down from 08:20 to 13:12 for C/M. g) Jessore-Noapara 132 kV Ckt-2 tripped at 08:26 showing no relay and was switched on at 10:03. h) Bagerhat-Mongla 132 kV Ckt tripped at 13:06 showing dist.Z2,ABC-phase from Bagerhat end and About 26 MW power interruption occurred under Mongla S/S area was switched on at 13:26. from 13:06 to 13:26. i) After maintenance Haripur-412 MW CCPP ST was synchronized at 15:30. j) Cumilla(N)-Chandpur 132 kV Ckt-2 was under shut down from 17:39 to 21:06 for breaker maintenance. k) Aminbazar 230/132 kV T-2 transformer was under shut down from 13:33 to 17:40 for C/M. l) B.Baria 132/33 kV T-2 transformer was under shut down from 20:48 to 21:34 for red hot maintenance About 50 MW power interruption occurred under B.Baria S/S area at 33 kV Bus coupler. from 20:48 to 21:48. m) Jamalpur 132/33 kV T-4 transformer was under shut down from 21:34 to for red hot maintenance About 12 MW power interruption occurred under Jamalpur S/S area at 33 kV incomer R-phase Bus isolator. from 21:34 to 23:49. n) Sylhet-Chatak 132 kV Ckt-2 tripped at 01:04(17/4/20) showing dist.Z1,B-phase at Chatak end & dist.Z2,B-phase at Sylhet end. o) Kulaura 132/33 kV T-1 transformer tripped at 01:40(17/4/20) showing O/C & E/F relays and was About 16 MW power interruption occurred under Kulaura S/S area switched on at 03:33(17/4/20). from 01:40 to 03:33(17/4/20). p) Fenchuganj-Sreemangal 132 kV Ckt-2 tripped at 02:41(17/4/20) showing dist.C-phase at Sreemangal end and was switched on at 02:57(17/4/20).
Sub Divisional Engineer Executive Engineer Superintendent Engineer
Network Operation Division Network Operation Division Load Despatch Circle