Professional Documents
Culture Documents
Standard No.
ENGINEERING STANDARD AL-LIN-50002
Design Philosophy for Determination of Right-Of-Way
Width Page 2 of 25
Table of Contents
1.0 Introduction...................................................................................... 3
2.0 Factors Influencing Right-Of-Way Width ....................................... 3
2.1 Risk and Right-of-Way Widths ....................................................................... 3
2.2 Conductor Swing ............................................................................................ 4
2.2.1 General ........................................................................................................ 4
2.2.2 Allowable Swing for Right-of-Way ............................................................... 5
2.2.3 Legal Minimum Requirements ..................................................................... 6
2.2.4 Five Year Return Period Criterion ................................................................ 9
2.3 Vegetation and Tree Falling Considerations .............................................. 10
2.3.1 Clearance to Windbreaks and Shelter Belts .............................................. 10
2.3.2 Design of VCE Width for Tree Falling ........................................................ 11
2.4 Construction and Maintenance Considerations ......................................... 13
2.5 Parallel Circuit Separation ........................................................................... 14
2.5.1 Conductor Swing ....................................................................................... 15
2.5.2 Legal Minimums ........................................................................................ 16
2.5.3 Maintenance Considerations ..................................................................... 18
2.5.4 Tower Fall Over ......................................................................................... 18
2.6 Other Considerations ................................................................................... 19
2.6.1 Electrical Effects ........................................................................................ 19
2.6.2 GPR Protection and Pipeline Coordination ................................................ 19
3.0 References ..................................................................................... 21
4.0 Sample Calculation ........................................................................ 22
4.1 Hardware Configuration ............................................................................... 22
4.1.1 Length of Insulator Hardware .................................................................... 22
4.2 Conductor Specifications & Sag ................................................................. 22
4.3 Legal Minimum Requirements (Section 2.2.3) ............................................ 23
4.4 Return Period Gust Criterion (Section 2.2.4) .............................................. 23
4.5 Conclusion .................................................................................................... 25
5.0 AltaLink’s Right-of-Way Calculator .............................................. 25
6.0 Conductor Sag Criteria.................................................................. 25
1.0 Introduction
This document is intended to provide guidelines and criteria for consideration when determining
right-of-way widths. Right-of-way selection, to a large extent, is a risk decision that properly
belongs with each TFO individually. AltaLink’s philosophy is to strategically minimize right-of-
way requirements and landowner impacts associated with new facilities while maintaining all
technical codes and performance requirements (e.g., safe working, swing out, electric field,
induction, etc.). It must be recognized that there is always a degree of risk that drives right-of-
way sizing.
This design philosophy shall be used for determining all right-of-way widths for AltaLink
transmission line facilities. It should be followed by all personnel involved with design,
construction, and maintenance of transmission lines for AltaLink.
When assessing risk, the right-of-way designer must consider that AltaLink transmission
structures are designed to accommodate insulator and conductor swings for a maximum wind
gust of a 5 year return period. This means that if a wind return period greater than 5 years is
used (e.g., 50yr or 100 yr) for determining right-of-way widths, the conductor may be de-
energized when in its fully swung out position, therefore reducing the risk of flash over to
objects adjacent to the right-of-way (note: this may not be the case with double circuit lines
where one circuit is free to swing away from the tower). 5 year return period wind gusts are
typical industry criterion and should be used for determining right-of-way widths at AltaLink.
Other areas to consider are Transportation Utility Corridors where AltaLink’s transmission lines
will be paralleling other right-of-ways (e.g., pipelines). The risk associated with the conductor
swinging out over a pipeline’s right-of-way during a high wind event is much different than the
risk associated with the conductor swinging out over the edge of right-of-way in urban areas.
AltaLink may decide to allow the conductor to swing out over a pipeline’s right-of-way only
after consideration is made in assessing the risk and is strictly on a case by case basis. In these
situations further consideration must be made regarding maintenance and construction practices
for both the pipeline owner and AltaLink.
AltaLink’s philosophy is to maintain all conductors within the right-of-way (where practicable)
with the applicable assessment of risk, swing criterion, clearances and safety factors set out in
this document.
Where lines are constructed along road allowance, the following easements may be obtained by
AltaLink when circumstances warrant:
− 10 - 15 meter access easement for construction and maintenance of the line, and
− Overhang easements to guarantee the conductor cannot swing beyond the boundary of the
right-of-way.
To ensure safe operation of the transmission line, the designer must allow for possible horizontal
movement of the conductor toward obstacles which may be nearby. They must also consider the
nature and potential hazards created by this event as well as legal requirements of the Alberta
Electrical Utility Code (AEUC).
Early planning and design of the transmission line facility must take this horizontal swing into
account. The consequence of a right-of-way with a constrained width can have substantial
economic impact to line construction projects by limiting the conductor spans to uneconomical
lengths, or requiring uneconomical structure configurations to maintain necessary electrical
clearances.
AltaLink requires the application of two criterions to determine conductor swing for the purposes
of designing right-of-way width:
i. AEUC/CSA requirements
The AEUC/CSA requirements are legal minimums which must be maintained under the Alberta
Safety Codes Act. The 5 year return period swing out criterion may be used depending on the
location of the line, the risk associated with development at right-of-way edge, and voltage class
of the line. A typical example for using the 5 year gust criterion may be when the transmission
line is located in a Transportation Utility Corridor (TUC) or when longer spans are considered.
The designer must document the risk decisions backing the reasoning for using the 5 year gust
criterion (example: located in TUC). In all cases the right-of-way width shall meet or exceed the
minimum legal requirements.
High wind areas, mountainous and heavily rolling areas are typically where special
considerations should be made. When estimating ruling span lengths in these areas, common
sense should be taken when assessing the probable maximum span lengths.
In the absence of better information, for typical construction in Alberta, the maximum span for
computing right-of-way width may be approximated as:
where,
The Alberta Safety Codes Act requires, via the AEUC, that horizontal clearances be maintained
to objects adjacent to the transmission line right-of-way. These clearance values can be found in
Table 2-1. AltaLink requires a safety factor of 600mm be added to account for minor errors in
the placement of the transmission structure.
Table 2-1 - Minimum Design Clearance from Wires and Conductors Not Attached to Buildings, Signs, and
Similar Plant including AltaLink’s safety factor of 600mm(AEUC 2007 Table 9 + 600mm)
Maximum
Nominal Voltage Minimum clearance in any direction between
Operating Phase to
Phase to Phase conductors of one line and structures of another line
Ground Voltage
(kV) (mm)
(kV)
25 15.9 3600
69 43.9 3820
Notes:
1. Voltages listed are nominal phase to phase operating voltages.
2. For parallel circuits less than 25kV phase-to-phase (14.4kV phase-to-ground) they must meet 25kV requirements.
3. The clearances above are calculated using the Alberta Electrical Utility Code 2007 Table 9 plus a 600mm safety factor and
assuming the line to be operating 10% above nominal voltage level. AEUC Table 9 requires the following clearances: (Voltages
are listed as rms line to ground)
> 7.5kV ≤ 22kV – 3000mm
>22kV– 3000 + 10mm/ kV over 22kV
Example:
240kV– Max Operating for 240kV x 1.1 = 264kV
264/√3=152.4kV - rms line to ground voltage
Clearance requirement for 152.4kV is 3000mm + [(152.4-22) x 10mm] ≈ 4310mm + 600mm safety factor = 4910mm
The maximum horizontal deviation as defined in CSA-C22-3 No.1-06 Clause 5.2.7 shall be used
for determining the minimum legal requirement. For the purpose of determining conductor
swing, the sag of the maximum span shall be taken as the final unloaded sag at a conductor
temperature of 40°C (see Section 6.0 for detailed conductor sag criteria to be used with this
standard). Where suspension insulators that are not restrained from swinging transversely are
used, the length of the insulator string shall be added to the conductor sag. [10]
where,
Figure 2-3 - C22-3 No. 1-06 - Table 1 Wire and conductor swing for horizontal design clearance
where,
Return period gust winds can be found using the wind pressure map which accompanies AL-
LIN-20006 for five year gusts.
Conductor swing out is calculated using the insulator swing method outlined in AL-LIN-20006
for the designated wind pressure. The sag at the point under consideration shall be taken as the
ten year final creep sag at a conductor temperature of 4°C with 650 Pa of wind pressure acting on
the conductor (see Section 6.0 for detailed conductor sag criteria to be used with this standard).
Where suspension insulators that are not restrained from swinging transversely are used, the
length of the insulator string and hardware shall be added to the conductor sag.
where,
Where the conductor is supported by line posts, V-string configuration, or is dead ended, the
length of insulator is taken as zero. However, any hanging hardware which is free to swing must
be included.
In conjunction with the 5year return period swing-out, the High Wind flashover values from AL-
LIN-20005 – “Minimum Air Gaps” - Table 2-1 are to be used. A minimum safety factor of
300mm is required to be added to the minimum air gaps when determining right-of-way widths
for AltaLink facilities.
Since it is not normally possible to arrange for complete tree clearing where shelter belts are
concerned, the following conductor swing criteria are to be applied:
The more stringent of the two conditions will govern. The return period criterion is not generally
applied to shelter belts, nor are tree falling clearances typically obtained.
While consideration of tree falling clearances may not impact the basic transmission line right-
of-way, it is standard practice to obtain an additional VCE beyond the boundaries of the line
right-of-way easement to deal with trees which could conceivably fall and pass within a
flashover distance to energized conductors (see Figure 2-4).
where,
The conductor is always assumed to be operated at its maximum temperature, at rest position for
computing VCE width. In the absence of design or other known thermal limits, this should be at
100°C, 10 year final creep, unloaded sag (see Section 6.0 for detailed conductor sag criteria to be
used with this standard).
For purposes of determining the VCE width, tree height is determined as an “average maximum”
tree height – it should not be set by the tallest tree in the forest. Individual trees outside the VCE
can be removed on a negotiated basis if defined as a “danger tree” based on the previous tree
falling computation. This is typically more economical and has reduced environmental impact
over sizing the VCE for the tallest group of trees on the transmission line route.
AltaLink generally assumes that tree growth will vary depending on the maturity of the forest
canopy. Shorter trees often imply a less mature forest. On that basis, AltaLink applies growth
factors that are to be applied to trees depending on their average height as shown in Table 2-2.
These factors are intended to allow for inaccuracies in determining average tree height and to
allow a reasonable margin for tree growth between brushing operations.
8 to 12 m 4.0
12 to 16 m 3.5
16 to 18 m 3.0
18 to 24 m 2.0
24 to 30 m 1.0
These growth factors are meant to be applied to general forest canopy, not to individual trees.
In using tree falling clearances to determine VCE width, a level ground surface is to be assumed.
The separate process of “danger tree” identification will deal with specific areas where side slope
may be a significant clearance factor.
This concern is illustrated by Figure 2-5, where a 240kV tower is shown laid out on a typical
240kV right-of-way. A minimum passageway of 3.66 meters must be allowed to permit
movement of personnel and equipment around transmission structures which have been framed
but not erected. Typically transmission structures would be placed as follows:
− Single Pole Structures: Framed to one side of the right-of-way centerline. Center of
working area is adjacent to the setting location.
− H-Frame Structures: Framed on the right-of-way centerline. Pole bases are longitudinally
adjacent to their setting location.
− Towers: Placed on an angle across the footing location for ease of crane location and
erection. See Figure 2-5 for a typical double circuit tower configuration.
Structure framing and required working space for transmission structures should be reviewed
with experienced line construction personnel to ensure that right-of-way boundaries proposed on
the basis of conductor swing provide sufficient space for their operations.
Other barriers on the right-of-way (e.g., water, embankments, muskeg, etc.) need to be
considered during the line layout phase of design. If these prevent travel around structure
working sites, then alternative access points will need to be arranged. Off right-of-way access
can be difficult and/or expensive to obtain if left until construction is under way.
− Conductor Swing
− Legal Requirements of CSA and ECUC
− Maintenance considerations
− Tower fall over distance
The conductor of the up-wind circuit is considered in a fully swung position while the conductor
of the leeward circuit is considered in an at rest position. Circuit-to-circuit flashover clearances
must be maintained as shown in Table 2-3. AltaLink includes an additional 300mm safety factor
in the flashover distance to allow for errors in placement of structure.
Winds from both sides must be considered. One circuit usually swings further than the other,
and that will govern the required circuit spacing.
Table 2-3 - Circuit to Circuit Flashover Distances (mm) for return period gusts (safety factor of 300mm
included)
Notes:
1. Voltages listed are nominal phase to phase operating voltages.
2. For parallel circuits less than 25kV phase-to-phase (14.4kV phase-to-ground) they must meet 25kV requirements.
3. The clearances above are calculated using the CSA C22.3 No.1-06 – Overhead Systems recommendation of 2.54mm/kVcrest for
voltages up to 500kV and 3.81mm/kVcrest for voltages above 500kV. Both circuits were assumed to be operating at a maximum
operating voltage of 10% above nominal. The higher voltage circuit also included a switching overvoltage. Switching
overvoltages used are those recommended in the CSA C22.3 No.1-06. 240kV – 2.75pu, 138kV – 3.0pu, 69kV- 4.0pu, 25kV –
4.0pu. An additional 300mm was added to as a safety factor.
Example:
240kV to 138kV – CSA switching overvoltage for 240kV is 2.75pu – Max Operating is 240kV x 1.1 = 264kV
264/√3=152.4kV x (√2 x 2.75) = 592.8kV switching surge crest (peak) voltage
138/√3=79.67kV x (1.414 x 1.1) = 123.9kV crest (peak) voltage
Therefore, 592.8kV + 123.9kV = 716.7kv
Clearance requirement for 716.7kV is 2.54mm/kv for first 500kv + 3.81mm/kv for greater than 500kv
= (2.54mm x 500) + (3.81mm x 216.7) ≈ 2100mm + 300mm safety factor = 2400mm
Table 2-4 - Minimum design clearance between conductors of one line and supporting structures of another
line including AltaLink’s 600mm safety factor(CSA C22.3 No.1-06 - Table 16 + 600mm)
Maximum
Nominal Voltage Minimum clearance in any direction between
Operating Phase to
Phase to Phase conductors of one line and structures of another line
Ground Voltage
(kV) (mm)
(kV)
25 15.9 1600
69 43.9 1600
Notes:
4. Voltages listed are nominal phase to phase operating voltages.
5. For parallel circuits less than 25kV phase-to-phase (14.4kV phase-to-ground) they must meet 25kV requirements.
6. The clearances above are calculated using the CSA C22.3 No.1-06 – “Overhead Systems” Clause 5.8.3 and CSA Table 16 plus a
600mm safety factor and assuming the line to be operating 10% above nominal voltage level. CSA Table 15 requires the following
clearances: (Voltages are listed as rms line to ground)
> 5kV ≤ 22kV – 1000mm wherever practicable, but in no case less than 500
>22kV ≤ 50kV – 1000mm
> 50kV – 1000 + 10mm/ kV over 50kV
Example:
240kV– Max Operating for 240kV x 1.1 = 264kV
264/√3=152.4kV - rms line to ground voltage
Clearance requirement for 152.4kV is 1000mm + [(152.4-50) x 10mm] ≈ 2030mm + 600mm safety factor = 2630mm
Table 2-5 - Clearance requirements to be added to horizontal displacement plus AltaLink’s 600mm safety
factor (CSA C22.3 No.1-06 - Table 15 + 600mm)
Notes:
1. Voltages listed are nominal phase to phase operating voltages.
2. For parallel circuits less than 25kV phase-to-phase (14.4kV phase-to-ground) they must meet 25kV requirements.
3. The clearances above are calculated using the CSA C22.3 No.1-06 – “Overhead Systems” Clause 5.8.2 and CSA Table 15 plus a
600mm safety factor and assuming both lines are operated 10% above nominal. CSA Table 15 requires the following clearances:
(Voltages are sum of rms line to ground)
> 750V – 300 + 10mm/ kV over 750V
Example:
New 240kVline paralleling an existing 240kV line– Max Operating for 240kV x 1.1 = 264kV
264/√3=152.4kV - rms line to ground voltage
Sum of two lines is 152.4kV + 152.4kV = 304.8kV
Clearance requirement for 304.8kV is 300mm + [(304.8-0.75) x 10mm] ≈ 3350mm + 600mm safety factor = 3950mm
Experienced maintenance personnel should be consulted any time parallel circuits are
contemplated to ensure that sufficient access space is provided between the circuits.
current transmission line, then neither the structures nor wires of the failed lower
voltage transmission line will come into contact with the structures or wires of the
500 kV alternating current or +/- 500 kV high voltage direct current transmission line;
(b) where two (2) or more 500 kV alternating current or +/- 500 kV high voltage direct
current transmission lines are located in a common right of way, the spacing must be
such that, if the structures of any one (1) 500 kV alternating current or +/- 500 kV
high voltage direct current transmission line fail and fall toward another 500 kV
alternating current or +/- 500 kV high voltage direct current transmission line, then
neither the structures nor wires of the failed transmission line will come into contact
with the structures or wires of any adjacent 500 kV alternating current or +/- 500 kV
high voltage direct current transmission line.
Where the failed structure referenced in subsections 2.5.4 (a) or (b) is a lattice tower, the
structure may be assumed to fail at the waist if analysis indicates this will be the point of failure
under high wind and combined wet snow and wind loadings. Towers that will fail at the waist
include L, LL, and M. For information on additional towers contact AltaLink Asset
Management.
Pipeline parallels and crossings provide additional concerns which have a greater impact on
routing decisions than on right-of-way width. Transmission line easement width is not usually
an effective method to mitigate pipeline induction; particularly in the case of lengthy parallel
routes. Where pipelines cannot be avoided, consult AltaLink’s AL-LIN-20008 - “Pipeline
Coordination Philosophy”.
3.0 References
1. “Insulator Swing”, Transmission Lines, Asset Management, Standard AL-LIN-20006,
AltaLink Management Ltd.
2. “Minimum Air Gaps for Transmission Structures”, Transmission Lines, Asset
Management, Standard AL-LIN-20005, AltaLink Management Ltd.
3. “Limits and Measurement Methods of Electromagnetic Noise from AC Power Systems,
0.15 to 30 MHz”, CSA CAN3-C108.3.1-M84 (R2005), Canadian Standards Association,
1984.
4. “Alberta Electrical Utility Code”, 3rd edition, Safety Codes Council 2007
5. CSA C22-3 No 1-06 – “Overhead Systems”, Oct 2006, Canadian Standards Association.
From AL-LIN-20006 Table 2-4 the 5 yr gust for Double Circuit Tower in Zone A is 1350 Pa.
H – Horizontal (Transverse) forces acting on conductor: (assume wind span = max span)
Ignore wind on insulator and hanging hardware
4.5 Conclusion
The return period requirement (57.6m) would dictate the width of the required right-of-way for
this example.
Tension
Temperature Radial Ice Load Wind Cable
Limit
°C (mm) (Pa) Condition
(% UTS)
1 -20 12.5 400 60 Final
2 -50 0 0 35 Initial
3 -30 0 0 25 Initial
4 4 0 0 20 Final
5 4 0 0 Creep
6 100 0 0
7 40 0 0
8 4 0 650
Note:
1. Consideration should be given to the aluminum in the conductor going into compression. The sag values in
Al-LIN-50002-2 – “Right-of-Way Width Calculator” use Sag10 with the default aluminum compression
value of 1500.
2. Wet snow constraints that are considered for line design can be ignored for ROW width calculations.