Renewable Energy 150 (2020) 616e623

Contents lists available at ScienceDirect

Renewable Energy
journal homepage: www.elsevier.com/locate/renene

Risk management in distributed wind energy implementing Analytic


Hierarchy Process
Shan Zhou, Pu Yang*
The Bartlett School of Construction and Project Management, University College London, London, WC1E 7HB, UK

a r t i c l e i n f o a b s t r a c t

Article history: Distributed wind power has received growing attention in recent years. However, high risks remain in its
Received 5 April 2019 investigation, which severely hindered its development. This study attempts to gather and identify risk
Received in revised form factors in distributed wind power through literature reviews and rank the risks based on expert opinions.
12 November 2019
Based on previous literature, we classified risk for distributed wind power investment into four types,
Accepted 27 December 2019
namely the political risks, economic risks, social risks, and technical risks. Analytic Hierarchy Process
Available online 28 December 2019
(AHP) method is used to assess risks in the life cycle of the distributed wind farm. Political, Economic,
Social and Technical methodology as the criteria hierarchy is introduced to classify the identified risks as
Keywords:
Distributed wind energy
the sub-criteria hierarchy in the AHP model. The result shows that the risk of changes in electricity price
Risk management policy is the most critical impact on the distributed wind power system to obtain sustainable devel-
PEST analysis opment and make profits. Therefore, the government needs to provide a long-term vision of electricity
Analytic hierarchy process (AHP) price policy to promote the development of distributed wind projects.
Quantitative risk analysis © 2020 Elsevier Ltd. All rights reserved.

1. Introduction energy system by itself cannot promise a maintainable develop-


ment due to the consideration of technical and financial factors [6].
China is forcing to change its energy development strategy to According to the latest plans and policies of the Chinese govern-
replace conventional power plants [1,2]. In China’s National 13th ment, the distributed wind power project can have a total capacity
Five-Year Plan for Renewable Energy, the government intends to of no more than 50 MW (MW) of grid connection points and an
increase the capacity of the wind power to 210 GW and adds the access voltage level of 110 kV (66 kV in Northeast China). Distrib-
capability of solar power to 110 GW by 2020 [3]. In 2017, China’s uted generation systems generally select the location close to the
total wind power production was 303,420 GWh, accounting for point of consumption, on the customer side of the metre or the
4.73% of the entire power generation and occupying about two- distribution network [7]. Distributed generation can apply its
thirds of power generation of all renewable energy (including so- advantage of the location to assist the distribution system in
lar, biomass and wind power) [4]. The present context of China’s decreasing the peak load capacity and delaying the demand for
wind power is that the rate of abandoned wind farms in the ‘Three substation capacity extension [8]. The location of the distributed
North’s region’ is high. The transmission expense increases the wind farm has the advantage of increasing land use and saving the
generation cost of wind farms as the wind parks are far away from cost of the transmission line [9]. According to the study of Zhu et al.
the load centre. Driven by technological progress, the growth of (2017), nineteen provinces in central, eastern and southern China
energy requirements and numerous incentive policies, especially possess the low-speed wind resources that can exploit the wind
the “Interim Measures for the Development and Construction of energy programs [60]. Meanwhile, the Chinese government
Distributed Wind Power Projects” published, the Chinese energy launches a set of policies that encourage the company and enter-
companies and relevant suppliers have been attracted by the prise exploring the potentials of the distributed wind power. The
distributed renewable energy (DRE). The development of the future latest policy released by the National Energy Administrator attracts
energy system is imperative for a country. However, the sustainable more non-power firms and private investments that ask the orga-
nisation to have a professional management system to pursue
sustainable development.
A few pieces of research focused on exploring the risk man-
* Corresponding author.
agement employed in the wind farm, and the papers about the risk
E-mail address: p.yang.18@ucl.ac.uk (P. Yang).

https://doi.org/10.1016/j.renene.2019.12.125
0960-1481/© 2020 Elsevier Ltd. All rights reserved.
S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623 617

management of the distributed wind power are much rarer Political risks are composed of the government regulations and
[10e13]. The research of Chou and Tu (2011) concentrates on a rules, the taxation rate policies (i.e. tax, exemptions), fiscal policies
particular case e the tower collapses [10]. However, many other and environmental laws that may affect the specific industry and
risks that may cause more cost and losses for the power companies business to a large extent [31]. The conventional power generation
have not been considered. The company that invests in this new technology still has its superiorities that wind power cannot sub-
type of energy project is more sensitive to the risks than the con- stitute. Pra€ssler and Schaechtele (2012) argue that the sustainable
ventional wind farm. According to the statistic latest of the National development of wind energy needs policy support from the gov-
Energy Administration, fifteen distributed wind parks are in com- ernment [32]. Renewable Energy Laws released by China’s
mission, and an additional three projects are in the planning [5]. commitment present a positive attitude to the electric power en-
Therefore, this paper systematically reviews the development terprises [33]. Fagiani et al. (2013) explore the impact of feed-in
status of existing distributed wind power in China through litera- tariffs and certificate markets on the sustainability of renewable
ture reviews, and issues questionnaires to eighty-five experts in the energy development [34].
wind power field. The risk factors associated with political, eco- Economic risks gauge the economic environment through ana-
nomic, social and technical fields of the distributed wind power lysing the macroeconomic such as supply and demand, exchange
system are gathered through literature reviews and interviews. The rates, interest rates, and credit risks [35]. The cost of electricity and
AHP method is used to evaluate the experts and comprehensively the capital expense (CAPEX) are used to evaluate the economy of
evaluate the existence of distributed wind risk points. The results wind power [36,37]. The investors pay attention to the profit, and
can assist enterprises in the distributed wind power industry to customers care about the price of electricity. Whereas the stake-
better identify risks and help the government in formulating rele- holders are more interested in lower CAPEX [38,39].
vant policies. Social risks are identified through in-depth investigations of
numerous social and environmental aspects including climate
2. Risk management in distributed wind power changes, the purchasing power of target customers, community
infrastructure, demographic, environmental damage and pollution
In the literature, various papers claim that the completed risk [40,41]. The well-designed circumstances and well-performed so-
management process involves four key phases which are risk cial planning can mitigate social conflicts, control the potential
identification, risk analysis, risk treatment and monitoring and risks for investors and protect the environment [41]. Zalengera et al.
review [14e16]. Distributed wind power is a new electricity pro- (2014) observes that the labour requirements, skill, and knowledge
duction model that has only emerged in recent years. The published training should be noticed in social risk management [40].
articles on the distributed energy systems focus on the definition of Technical risks distribute to various classes that involve tech-
this conception and the qualitative analysis of their barriers nological innovations, completed investment estimates, chal-
[17e19]. However, quantitative risk management research on lenging project management (i.e. construction, O&M and
distributed wind energy is difficult to find in publications. The connection issues) and efficiency and capacity factors [40e42].
distributed wind park settles closer to the end users than the Technical risks may cause a positive or negative consequence for
traditional wind farm. It leads to potential hazards not appearing in the operation of the wind turbine industry and distributed wind
the large-scale wind park, which is the objective of this research. power market. Modern living relies on electricity. Nevertheless, the
Therefore, this study purposes for identifying risks and analysing inappropriate form of energy may be hard to suit the local needs of
their influences in the distributed wind energy project. the electricity and cause the losses of the power company [12].
Risk identification is a systematic and continuous process that The risk analysis of the project is an effective method to make
identifies, classifies and evaluates all the potential hazards and decisions on the best strategies and ensure that the project is
damages which are learnt from the past projects or undetected profitable [43,44]. Risk analysis can estimate the period of the
events or consequences through keeping attention for documen- identified events and the extent of their influence through a sys-
tation of new risks during the through-life cycle of the project tematic investigation of available information [14]. Qualitative risk
[20e22]. Literature research and interviewing project personnel analysis assists the related organisation to figure out the most
who have experience with similar projects are effective methods to critical risks by rank-ordering them and pay attention to the solu-
gather correct risk elements [23]. SWOT analysis attempts to assess tion of the high-prioritised risks to enhance the performance of the
the sustainable development of an organisation by investigating project [45]. Whereas, quantitative risk analysis is a numerical
both the internal and external factors [24]. PEST analysis empha- analysis to calculate the probability and consequence caused by all
sizes the effect of external macroeconomic factors on a project or an the individual risks and other uncertain factors of the project
industry [25]. It is inappropriate to implement SWOT analysis to through implementing mathematical models and simulation tools
deliberate the distributed wind power industry. The consequence [41,46]. The implementation of the tools and techniques for the
of this research should be suitable for the whole DWP project in quantitative risk analysis can estimate the results under compli-
China. Previous publications implement Real Options Analysis cated scenarios and limited data [47]. PEST analysis covers the
(ROA), Failure Modes and Effects Analysis (FMEA) or Fuzzy Neural macroenvironmental factors that influence the sustainable devel-
Networks to assess the operational and financial risks in wind po- opment of the renewable energy sector [48]. The most versatile
wer project [26e29]. However, the ROA method is complicated for analysis approach in the energy area is the Analytical Hierarchy
managers to gather data that can support the assumption [30]. Process (AHP) as it can convert a complex issue into a simple hi-
FMEA needs to consider the Risk-Priority-Number (RPN) values. erarchy, flexibility and intuition [49,50]. AHP method expresses a
Various wind turbines have different structures, which leads that quantitative analysis of the risks that hides among the whole-life
the RPN values between different wind turbines cannot be con- cycle of the wind power project [51]. It is easy for decision-
trasted [27]. Large wind farms and distributed wind parks have makers to weight and compares two alternatives. It is also free to
several similarities. Hence, the risks that appeared in the large wind adjust in size to fit decision-making issues [52].
farms can present references to the distributed wind power project. Distributed wind power is a new electricity production model
The risk factors gathered from the traditional wind farm are clas- that has only emerged in recent years. The published articles on the
sified as political risks, economic risks, social risks, and technical distributed energy systems focus on the definition of this concep-
risks. tion and the qualitative analysis of their barriers [17e19]. However,
618 S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623

quantitative risk management research on distributed wind energy


is difficult to find in publications. The distributed wind park settles
closer to the end users than the traditional wind farm. It leads to
potential hazards not appearing in the large-scale wind park, which
is the objective of this research.

3. Research methodology

Systematic risk management can remove potential risks in the


renewable energy industry and create more benefits for the firm.
For research methodology, bibliography reviews can distinguish
what has been studied and figured out on the topic. This step is
impossible to be ignored for the determination of research topics as
it prevents researchers from repeating the study that has been done
[53]. The purpose of literature reviews is an extensive overview of
research focused on the fields that few people are involved [54].
This article proposes an MCDM-based approach to assess the risk of
distributed renewable energy.
The risk management in the distributed renewable energy in-
dustry is still blank. However, the dominant influence of income is
types of risks, such as policy risk, cost risk, construction risk, and
technical risk. Distributed renewable energy provides an unprece-
dented chance for developing countries to obtain clean energy. The
problem is how to offer an affordable electricity price for the
customer and guarantees that the distributed renewable energy
company has revenue. The total funding of distributed renewable
energy from various organisations and donors between 2012 and
2017 has reached approximate GBP 700 million [55]. The distrib-
uted renewable energy program is attracting investments from
government institutions and competitive enterprises. Fig. 1. An overview of the methodology of the research.
The contribution proposed by literature research is to verify that
the MCDM method, especially the AHP approach, is suitable for the
technical risk assessment phase. The fundamental steps of the Judgment Matrix and its corresponding eigenvector (W). The
study described in Fig. 1 display an overview of the methodology Judgment Matrix itself is the result of quantifying the qualitative
for discussing how to apply the AHP method to improve the sus- problem. Hence, the calculation of the maximum eigenvalue and
tainability of the distributed renewable energy project. eigenvector of the Judgment Matrix allows a specific error range.
The PEST analysis is the most common means to reflect the The relationship of weight vector (u), lmax and matrix A can be
external environment of the industry and a helpful strategic tool for presented as:
seeking business position, potential market and the trend of the
development [38,56]. Political analysis generally focuses on the Au ¼ lmax ,u (2)
changes in the domestic policies, local policies and government
subsidies on investment and taxation. The economic phase de- Then, the weight vector needs to be normalised to achieve the
termines whether the distributed wind power project is successful matrix for a priority order.
and profitable or not. The industry or organisation should consider The procedure of the pairwise comparison while filling the
the social influence of the new business appearance. Technology questionnaire survey involves the subjective judgment of the
changes result that the firm owns competitive advantages in the responder. Therefore, the situation of the inconsistency may
industry. happen. It is an essential stage for the AHP analysis as the wrong
AHP method mixes qualitative and quantitative criteria and Judgement Matrix causes the mistake of making decisions. The
internal and external effects to meet the requirement of the deci- consistency index (C.I.) demonstrates the degree of compatibility
sion maker. In this study, the AHP method is used to deal with the deviation. The expression of C.I. is presented as:
comparison, weighing and ranking of identified risks in a distrib-
uted wind energy project. The first step is to build the Judgement
Matrices that an element of the above layer as a criterion for lmax  n
C:I: ¼ (3)
judging the element value determined by the pairwise comparison n1
of the underlying components. The Judgement Matrix is an n n
Where n is the number of the evaluated factors in the Judgement
matrix, shown as the example of Matrix A below:
Matrix.
2 3 The largest eigenvalue is defined as:
a11 / a1j / a1n
6 « 1 « « « 7
6 7
A¼6
6 ai1 / aij / a11 7
7 (1)
4 « « « 1 « 5 1Xn
ðAuÞi
lmax ¼ (4)
an1 / anj / ann n
i¼1
ui
In the AHP analysis method, the most fundamental computa- Consistency Ratio (C.R.) is introduced as the criterion of the
tional task is to resolve the largest eigenvalue (lmax ) of the consistency index. The expression is defined as:
S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623 619

energy project. The cluster of the risks decomposes into four en-
C:I: tities (including Political, Economic, Social and Technical). The AHP
C:R: ¼ (5)
R:I: model is an entirely independent structure that owns substantive
If C:R: > 0 and C:R: < 0:10, then the weight vector u is an risk factors underlying the PEST groups. The sub-factors of the risk
appropriate solution and Judgement Matrix is a satisfactory con- factor are the descriptions of the risk reasons on the third level.
sistency matrix. When C.R. is zero, it means that the Judgement Fig. 2 demonstrates an overview of the AHP model for the risk
Matrix is a complete consistency matrix. management of distributed wind power projects.
The last step is to calculate the global weight which illustrates The delivery and collection of the questionnaire use the method
the influence level of sub-risk factors in the overall project. Global of emails. Then, summarise the data and calculate the magnitude of
weight is equal to the local weight of each sub-factors multiplied by pairwise comparison by the geometric mean way. The detailed
the local weight of its corresponding criteria of the element. treatment of these results will be discussed in section 0.
Risk identification is the first stage of risk management. It is
crucial for complete research as risk analysis is meaningful after 4.2. Questionnaire data collection
meeting the scenario of the correctly-identified risks. The means of
risk determination is through searching from the previous relative In this study, a total of eighty-five questionnaires were recov-
papers and interviews to collect the judgements of experts and ered from twenty-three provinces in China. Fig. 3 expresses that
associated practitioners. Political, Economic, Social and Technical twenty-six of the responders are the general manager and twenty-
factors are the four primary criteria that decompose the gathered seven persons are senior experts on the renewable energy industry.
risks into four groups. PEST technique is an analysis framework of The most portion of the respondents is the ones who are both
strategic management to recognise the risks and evaluate the in- manager and expert. The fifty-nine in eighty-five interviewees have
fluence of construction projects [42]. The distributed wind energy more than five years of experience in the wind power industry, as
is an emerging industry that leads to a lack of relevant reference. shown in Table 2. Thirty-five participants in this questionnaire have
Therefore, the most risks lesson from the experience of other sorts the job engaged in the distributed wind energy industry. From
of enterprises and organisations through a structured documen- another perspective, it emphasizes that the distributed wind power
tation review. The risks can be transferred from large-scale onshore is still in the beginning stage in China.
and offshore wind farms. The additional risks are gathered from the The errors of the judgment are inevitable since it is a process of
interview with general managers. The next stage is to summarise subjective evaluation by experts. In order to reduce the probability
the risks and implement the checklist technique. Then, a ques- of inconsistency of the matrix, the largest and the smallest as-
tionnaire is performed to invite the professionals and managers to sessments score in the cluster of the same pairwise comparison of
evaluate the influence of the risks to the system from the Political, the risks are removed before estimating the geometric mean.
Economic, Social and Technical perspectives. The criterion of the
judgement refers to the Saaty’s scale, as exhibited in Table 1. The 5. Results
results of the questionnaire set as the inputs of the AHP analysis.
Despite the many advantages of AHP, there are still many limi- The consequence of risk assessment debates depended on the
tations. it is difficult for participants to reach a unified standard that hierarchical groups. The identified risks divide into four clusters
they can map their own subjective opinion into a number [57]. Li (including Political risks, Economic risks, Social risks, and Technical
et al. (2008) argue that AHP cannot present the inherent charac- risks). Table 3 indicates that the Political risks are the most critical
teristics of complicated evaluation problems, which results in the cluster in this hierarchy, which takes approximately 38.96%. The
issue of incorrect rankings [61]. AHP lacks the capability of priori- impacts of Economic, Social and Technical risks for the project are
tizing two alternatives with different weights at a different time similarly equivalent, which occupy around 20%. The table indicates
[58]. that the stakeholders believe that the development of the distrib-
uted wind energy industry has a strong affiliation with the control
by the Chinese government. A definite incentive policy can
4. Data analysis by AHP method encourage more firms to invest in distributed wind energy projects.
The government has the responsibility to discipline and guide the
4.1. Risk identification of distributed wind power in China development scale, speed and operation management of the wind
power industry. However, the cancellation of the preferential policy
The purpose of this research is to aid with the DRE companies to may lead to income decrease. The current situation of China is that
obtain a sustainable development in the future of the Chinese the government inspires electric power companies or other firms
electricity market, which is the top hierarchy in the model. The about distributed wind power to notice this new industry. The
uncertain factor is the risks that hide in the through-life cycle of the second risk is the Social Risks. Two major risks in the political field
project. The risks found in the bibliography or discussed by in- are the risk “Changes in electricity price policy” and “Renewable
terviews are tailored to fit the conditions of the distributed wind Energy Policy Changes”. The net profit of a company is the differ-
ence between profit and taxation. The profit consists of the income
of the primary business and various subsidies minus cost and tax
Table 1
The criterion of the effect of risk [64]. expenses. The performance, income, and cost have almost fixed
when the project construction is completed and put into operation.
Intensity of Definition
Hence, the most sensitive content for the distributed wind parks
Importance
is the fluctuation of the electricity price and the changes in subsidy
1 Equal importance
policy. The issue of the lack of persistence for the government
3 Somewhat more important
5 Much more important subsidies results in a decrease in the profit of the firm or a loss of
7 Very much more important the company due to the uncertainty of wind power policy in China
9 Absolutely more important and the reform of the market mechanism. These risks mostly have
2, 4, 6, 8 Intermediate values between the two adjacent regular patterns. For example, the purpose of the RE policy changes
judgments
is to control the aggregate volume of wind energy or other
620 S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623

Fig. 2. AHP model for risk assessment.

renewable energy directly. The Chinese government would retard happens in the distributed generation system. The project manager
the speed of developing new wind farm projects if the current needs to perform an abundant investigation on the population
capacity exceeds the amount of government planning. The changes distribution, the payment ability, and credits of the clients and the
in investment subsidy and tax benefits are the indirect regulation enterprise during the design phase of the project. The other risks
measures to make investors lose interest in wind power projects. are the low risks that have a minor impact on the project. The risks
The wind turbine may have an impact on the natural scenery, of increased interest rate and the fee of the land lease are beyond
resulting in low acceptance of the project. There is a case that small the management control. The construction and logistics industries
wind power equipment was set up in the scenic spot in China. have been comparatively mature in China. Therefore, the core
However, the wind turbine ultimately demolished due to destroy- component damage during these phases is low occurrence
ing the original scenery. possibility.
Economic risks are concerned about the economic benefits of Social risk is the second vital risk among the PEST hierarchy. The
the project. These respondents have evaluated the critical reasons weight of “The tower collapses, fire or the blade break damage to
for weak profitability. The most significant risk factor is the risk the third parties or neighbours” risk reaches an astonishing 44.60%.
“Load hour is lower than the planning value due to the poor wind This risk can lead to the destruction of surrounding buildings and
resources”. The weak wind resource raises the capital cost per kW severe casualties as its location is closer to consumers than the
and causes low load factors in the small-scale wind turbine. It is large-scale wind park. The quantity of the wind turbine in the
more necessary for the low-wind-speed area, compared to rich distributed renewable energy system is limited. Therefore, the
wind resources and high-wind-speed region, to notice this risk losses caused by the breakdown of one wind turbine in a distrib-
while deciding on the wind farm site. The client turnover (R10) and uted wind park is more grievous than the same situation happened
electricity bill recovery (R11) issues are the potential risks that only in a large-scale wind farm. The noise and light pollution for natural
S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623 621

in technical risks. Most of the questionnaire participants agree that


the technology of wind blade transportation can reduce the con-
struction cost and fit the narrow roads in the urban or intensive
industrial park. However, transportation safety should retain
attention as any of the accidents may lead to massive losses.
The principal risks are from the political factor. However, these
risks are unpredictable, and the team cannot intervene previously.
Hence, the risk management strategy of the distributed wind po-
wer project is to mitigate or eliminate other three-group risks to
guarantee the maximum value delivering to stakeholders.

6. Discussion

The electricity price policy of wind energy in China appears


downtrend annually. According to the latest policy from the Na-
tional Development and Reform Commission, the net price of
onshore wind power in 2019 is from approximate 0.05 US dollars to
0.08 US dollars. To 2020, it will drop to around 0.04 to 0.07 US
dollars. Twelfth of thirty-four provinces have published their local
development plan on the distributed wind power. Encouragement
and openness attitudes towards distributed wind energy are such
good information guiding electricity firms to enlarge the market in
the era when the conventional wind energy market has been
saturated. Therefore, this study becomes essential to assist
renewable energy companies to figure out the potential risks of the
distributed wind farm project. The government should not imitate
Fig. 3. Occupation and tile of the respondents. the development model of a traditional wind power project. For
instance, the approval requirements and processes for traditional
wind power development waste a lot of time led to construction
livings and human beings is the next consideration. The noise inefficiency and raised initial costs of the distributed wind power
mostly comes from the wind blades and the gearbox of the wind project.
turbine. The wind park will directly affect the bird’s activity when it Another concern is the hidden dangers of the tower collapses,
is running since some birds including poultry are sensitive to noise fire and the blade break damage to the third parties or the neigh-
and light, which may result in civil compensation, increasing bours. The economic loss caused by the accidents described above
operating expenditures. may turn into an invisible and uncertain cost. More importantly,
The Technical risks are defined as the minimum influence in the the social issues associated with casualties of citizens or people in
distributed wind power system. The principal technical risk is the manufactory may result that the government has to stop the
risk “Yield and effectiveness are lower than the design value (R16)” development of the distributed wind power.
that causes the decline of the income. The reason may be the The distributed wind farm has the characteristics of scattered
mistake of the design engineer. The lousy weather for the period of layout and small scale. This study prefers that the government
the construction and operating phases can lead to an increase in should conduct centralized planning to reach economic and effi-
CAPEX, construction cost and the expense of the commissioning. cient management and ensure the well-ordered development of
The weight of the blade transportation problem ranks the last one the project. The Chinese government can refer to the experience of

Table 2
The basic statistic of the respondents.

Socio-economic characteristics of the respondents Observations (person)

Years of experience in the wind power industry 2-5 years 27


More than 5 years 58
Ever engaged in distributed wind power Yes 35
No 50

Table 3
The overview of risk Assessment.
622 S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623

the Danish community-owned wind project, which utilizes a distributed generation system. The interviewed company produced
public-private partnership (PPP) model to decrease the interest the new generation wind turbine that installs decades of sensors on
cost [59]. Distributed wind power proposes higher requirements on the wind turbine, blades, and towers to monitor operating status
the wind turbine in the technical field. A good-quality wind turbine around the clock. The sensors on the wind blades can detect the
can significantly save operation and maintenance costs. Long-tern degree of damage to prevent loss of the company and surrounding
financial subsidy policy is unstable in the future. However, the people due to blade breakage. The new wind speed detector en-
new technology could reduce the construction period and cut the ables the wind turbine to know the wind speed in advance to
cost of the distributed wind project. improve the efficiency of power generation.

7. Conclusions and future work 7.2. Future work

7.1. Conclusion 7.2.1. Risk treatment plans


The risk treatment stage of the risk management process was
Firstly, this article offers a detailed and comprehensive limited to the discussion of three actions (including risk mitigation,
description of the current status and the development of wind risk prevention, and risk transfer) for this study. The development
power in China. The common risks happened in both conventional of a well-qualified pool of maintenance contractors in a competitive
wind farm, and the distributed wind farm can be found from the market is a helpful recommendation for Technical risks. The better
literature review. The potential risks in the distributed wind energy performance of the maintenance contractors reduces the conse-
are identified through the interview with the managers of Chinese quence of the risk R7, R14, R21 and the probability (50%) to have
renewable energy companies. These risk factors are the problems the risk no. 20. Omitaomu et al. (2012) introduce a new approach
that need to resolve now or in the future or not exist in conven- based on geographical information systems (GIS) to develop deci-
tional wind power projects. Then, this study introduces an sion making on renewable energy resources [63]. An approach
approach to utilising PEST as criteria for the risk classification combined GIS-MCDM employs to select the optimal location for the
method to structure the AHP model. A questionnaire evaluates the distributed wind park through wind speed analysis and simulating
pairwise comparison of risk influence. The result of AHP for risk the effectiveness and yield of the wind parks in different places.
assessment determines that the risk of changes in electricity price
policy estimates as the most majority impact for the distributed 7.2.2. Monitoring and reviews system
wind power system to obtain sustainable development and make An accomplished risk management process includes risk
profits. It represents around 11.65% of global weights. The other two monitoring and feedback. The team needs to examine the outcome
sub-risks over 10% global weights are the “renewable energy policy of approved risk treatment and document in a table including the
changes” risk and the “tower collapses, fire and the blade break risk events, risk treatment methods, progresses and compliance
damage to the third parties or neighbours” risk. The reduction of reporting. When employing the risk treatment actions (including
financial subsidies and taxation benefits should be the trend of the modification of schedule, the means of work or contract terms) to
Chinese wind energy market. Therefore, they rank fourth and fifth mitigate risk impact, the project may appear a new risk. The
among all risks, which account for 6.17% and 5.75% respectively. emerging risk needs to be logged immediately. Then, the project
Four risks at the top five ones are political risks, which emphasizes team performs risk reassessment to prioritise the updated risk
the significance of the political issues in the distributed wind factors. Therefore, the risk management process in the distributed
project. This article possesses three contributions: First, through wind power project has formed a closed loop. The optimum solu-
literature review and experts interview, the risk factors checklist of tions for the risks that only occur in the distributed wind power
distributed wind park in China is provided; Second, this study has system will discuss in the future study.
provided a quantitative risk assessment of distributed wind farm
through the implementation of the multiple criteria decision- Author contributions
making methods (MCDM); Finally, future research topics of
distributed wind power has also been identified. Dallas (2008) S.Z and P.Y. designed the study. S.Z. performed the conceptual-
discusses that the purpose of risk management is to deliver the ization and prepared the methodology. S.Z. collected the data,
maximum value to the project [62]. It is impossible to get the performed the AHP analysis and prepared the manuscript. P.Y.
highest benefits by avoiding all risks in the project. The primary participated in the review and editing of the manuscript and su-
task of the project manager is to design a structured and disciplined pervised the project.
scheme for the team to response and control risks efficiently.
Wind energy as renewable and clean energy should be an Declaration of competing interests
indispensable piece for the future energy structure in China. Some
factors hinder the distributed wind power deployment such as The authors declare that they have no known competing
political issues, environmental pollution, safety and security financial interests or personal relationships that could have
problems, limitation of technology, etc. However, the booming appeared to influence the work reported in this paper.
development of distributed wind energy will be a future trend
under the severe threatening of traditional energy depletion and Acknowledgement
environmental issues. There are still several points that can be
improved such as another more precise method employed for the The author would like to extend thanks to the interviewed
assessment of the risk impacts, the influence of technological company to provide a unique opportunity for understanding the
development, other distributed wind power problems and so on. development of the distributed wind power in China. I am also
This research has covered and assessed most of the risk factors hugely appreciative of eighty-five respondents of the questionnaire
in the distributed wind power system in China. Political and reg- to support my research, especially one of China’s wind power in-
ulatory risks will remain affecting investors if policymakers cannot dustry leaders e Mr. Shuiqun Zhang. Special mention goes to my
publish reasonable policies and regulations. The application of new supervisor, Dr. Zhifu Mi, for his wholeheartedly for his tremendous
technology will enhance safety and maintain the stability of the academic support.
S. Zhou, P. Yang / Renewable Energy 150 (2020) 616e623 623

References [33] F. Wang, H. Yin, S. Li, China’s renewable energy policy: commitments and
challenges, Energy Policy 38 (2010) 1872e1878.
[34] R. Fagiani, J. Barquín, R. Hakvoort, Risk-based assessment of the cost-efficiency
[1] Z. Zhao, Z. Li, B. Xia, The impact of the CDM (clean development mechanism)
and the effectivity of renewable energy support schemes: certificate markets
on the cost price of wind power electricity: a China study, Energy 69 (2014)
versus feed-in tariffs, Energy Policy 55 (2013) 648e661.
179e185.
[35] C. Erb, C. Harvey, T. Viskanta, Political risk, economic risk, and financial risk,
[2] T. Tang, D. Popp, The learning process and technological change in wind po-
Financ. Anal. J. 52 (6) (1996) 29e46.
wer: evidence from China’s CDM wind projects, J. Policy Anal. Manag. 35 (1)
[36] T. Weaver, Financial appraisal of operational offshore wind energy projects,
(2016) 195e222.
Renew. Sustain. Energy Rev. 16 (7) (2012) 5110e5120.
[3] J. Mathews, China’s Electric Power: results for first half 2017 demonstrate
[37] C. Mone , et al., 2015 Cost of Wind Energy Review, National Renewable Energy
continuing green shift, Asia-Pacific Journal: Japan Focus 15 (18) (2017) 1e6.
Lab, Golden, CO, 2017. No. NREL/TP-6A20-66861.
[4] State Grid Energy Research Institute, 2017 China Renewable Energy Power
[38] A. Gupta, Environment & PEST analysis: an approach to external business
Generation Analysis Report, China Electric Power Press, 2017a.
environment, Int. J. Mod. Soc. Sci. 2 (1) (2013) 34e43.
[5] State Grid Energy Research Institute, Analysis of distributed wind power
[39] F.C. Barba, et al., A technical evaluation, performance analysis and risk
development prospects, in: China Renewable Energy Generation Report,
assessment of multiple novel oxy-turbine power cycles with complete CO2
China Electric Power Press, Beijing, 2017b, pp. 69e74.
capture, J. Clean. Prod. 133 (2016) 971e985.
[6] G. Guerrero-Liquet, et al., Decision-making for risk management in sustain-
[40] C. Zalengera, R.E. Blanchard, P.C. Eames, A.M. Juma, M.L. Chitawo,
able renewable energy facilities: a case study in the Dominican Republic,
K.T. Gondwe, et al., Overview of the Malawi energy situation and A PESTLE
Sustainability 8 (5) (2016) 455.
analysis for sustainable development of renewable energy, Renew. Sustain.
[7] G. Allan, et al., The economics of distributed energy generation: a literature
Energy Rev. 38 (2014) 335e347.
review, Renew. Sustain. Energy Rev. 42 (2015) 543e556.
[41] J. Michelez, et al., Risk Quantification and Risk Management in Renewable
[8] J. Del Monaco, The role of distributed generation in the critical electric power
Energy Projects, 2010 s.l.: Risk quantification and risk management in
infrastructure, Power Eng. Soc. Winter Meet. 1 (2001) 144e145.
renewable energy projects.
[9] D. Drugmand, V. Stori, Distributed Wind Energy Zoning and Permitting, Clean
[42] N. Rastogi, M. Trivedi, PESTLE techniqueea tool to identify external risks in
Energy States Alliance, 2017.
construction projects, Int. Res. J. Eng. Technol. (IRJET) 3 (1) (2016) 384e388.
[10] J. Chou, W. Tu, Failure analysis and risk management of a collapsed large wind
[43] U. Anca, B. Cezar, U. Adrian, Risk identification in project management, Int.
turbine tower, Eng. Fail. Anal. 18 (1) (2011) 295e313.
Conf. Econ. Sci. Bus. Adm. 2 (1) (2015) 259e266.
[11] C. Li, P. Li, X. Feng, Analysis of wind power generation operation management
[44] U. de Oliveira, F. Marins, H. Rocha, V. Salomon, The ISO 31000 standard in
risk in China, Renew. Energy 64 (2014) 266e275.
supply chain risk management, J. Clean. Prod. 151 (2017) 616e633.
[12] N. Gatzert, T. Kosub, Risks and risk management of renewable energy pro-
[45] S. Mojtahedi, S. Mousavi, A. Makui, Project risk identification and assessment
jects: the case of onshore and offshore wind parks, Renew. Sustain. Energy
simultaneously using multi-attribute group decision making technique, Saf.
Rev. 60 (2016) 982e998.
Sci. 48 (4) (2010) 499e507.
[13] Y. Rolik, Risk management in implementing wind energy project, Procedia
[46] Project Management Institute, Project risk management, in: A Guide to the
Engineering 178 (2017) 278e288.
Project Management Body of Knowledge (PMBOK® Guide), sixth ed., Project
[14] D. Cooper, S. Grey, G. Raymond, P. Walker, Project Risk Management Guide-
Management Institute, 2017, pp. 395e458.
lines: Managing Risk in Large Projects and Complex Procurements, Wiley,
[47] M. Modarres, Risk Analysis in Engineering: Techniques, Tools, and Trends, CRC
Chichester, 2005.
press, 2016.
[15] ISO, ISO 31000: Risk Management: Principles and Guidelines, International
 ski, et al., Renewable energy production in the Ło
[48] B. Iglin dzkie Voivodeship.
Organisation for Standardisation, 2009.
The PEST analysis of the RES in the voivodeship and in Poland, Renew. Sustain.
[16] T. Kendrick, in: Identifying and Managing Project Risk: Essential Tools for
Energy Rev. 58 (2016) 737e750.
Failure-Proofing Your Project, third ed., Amacom, 2015.
[49] S. Pohekar, M. Ramachandran, Application of multi-criteria decision making to
[17] G. Pepermans, et al., Distributed generation: definition, benefits and issues,
sustainable energy planningda review, Renew. Sustain. Energy Rev. 8 (4)
Energy Policy 33 (6) (2005) 787e798.
(2004) 365e381.
[18] K. Alanne, A. Saari, Distributed energy generation and sustainable develop-
[50] P. Linares, Multiple criteria decision making and risk analysis as risk man-
ment, Renew. Sustain. Energy Rev. 10 (6) (2006) 539e558.
agement tools for power systems planning, IEEE Trans. Power Syst. 17 (3)
[19] P. Perera, Constraints and barriers to deployment of distributed energy sys-
(2002) 895e900.
tems and micro grids in southern China, Energy Procedia 103 (2016)
[51] X. Jin, Z. Zhang, X. Shi, W. Ju, A review on wind power industry and corre-
201e206.
sponding insurance market in China: current status and challenges, Renew.
[20] E. Ameyaw, A. Chan, Risk ranking and analysis in PPP water supply infra-
Sustain. Energy Rev. 38 (2014) 1069e1082.
structure projects: an international survey of industry experts, Facilities 33 (7/
[52] M. Velasquez, P. Hester, An analysis of multi-criteria decision making
8) (2015) 428e453.
methods, Int. J. Oper. Res. 10 (2) (2013) 56e66.
[21] L. Tchankova, Risk identificationebasic stage in risk management, Environ.
[53] D. Budgen, P. Brereton, Performing systematic literature reviews in software
Manag. Health 13 (3) (2002) 290e297.
engineering, Proc. 28th Int. Conf. Software Eng. (2006) 1051e1052.
[22] C. Harland, R. Brenchley, H. Walker, Risk in supply networks, J. Purch. Supply
[54] A. Mardani, et al., A review of multi-criteria decision-making applications to
Manag. 9 (2) (2003) 51e62.
solve energy management problems: two decades from 1995 to 2015, Renew.
[23] M. Tadayon, M. Jaafar, E. Nasri, An assessment of risk identification in large
Sustain. Energy Rev. 71 (2017) 216e256.
construction projects in Iran, J. Constr. Dev. Ctries. (JCDC) 17 (2012).
[55] A. Zervos, R. Adib, Renewable 2018 Global Status Report, 2018.
[24] Z. Zhao, et al., A critical review of factors affecting the wind power generation
[56] D. Koumparoulis, PEST Analysis: the case of E-shop, Int. J. Econ. Manag. Soc.
industry in China, Renew. Sustain. Energy Rev. 19 (2013) 499e508.
Sci. 2 (2) (2013) 31e36.
[25] C. Barbara, et al., The European insurance industry: a PEST analysis, Int. J.
[57] C. Kwong, H. Bai, A fuzzy AHP approach to the determination of importance
Financ. Stud. 5 (2) (2017) 14.
~ oz, J. Contreras, J. Caaman ~ o, P. Correia, A decision-making tool for weights of customer requirements in quality function deployment, J. Intell.
[26] J. Mun
Manuf. 13 (5) (2002) 367e377.
project investments based on real options: the case of wind power genera-
[58] A. Ahmad, M. Goransson, A. Shahzad, Limitations of the analytic hierarchy
tion, Ann. Oper. Res. 186 (1) (2011) 465.
process technique with respect to geographically distributed stakeholders,
[27] M. Shafiee, F. Dinmohammadi, An FMEA-based risk assessment approach for
Proc. World Acad. Sci. Eng. Technol. 4 (9) (2010) 97e102.
wind turbine systems: a comparative study of onshore and offshore, Energies
[59] P. Maegaard, L. Gorron ~ o, The development model of Danish community-
7 (2) (2014) 619e642.
owned wind project, Wind Energy 7 (2016) 40e44.
[28] P. Pinson, G. Kariniotakis, Wind power forecasting using fuzzy neural net-
[60] R. Zhu, Y. Wang, X. Gong, et al., in: Development Potential of Low-speed Wind
works enhanced with on-line prediction risk assessment, 2003 IEEE Bologna
Energy Resources in China, DEStech Transactions on Engineering and Tech-
Powzer Tech Conference 2 (2003) 8.
nology Research, 2017.
[29] J. Munoz, J. Contreras, J. Caamano, P. Correia, Risk assessment of wind power
[61] C. Li, Y. Sun, Y. Jia, H. Li, et al., An improved ranking approach to AHP alter-
generation project investments based on real options, in: Selected Pro-
natives based on variable weights, in: 2008 7th World Congress on Intelligent
ceedings from the 13th International Congress on Project Engineering, IEEE
Control and Automation, 2008, pp. 8255e8260.
Bucharest PowerTech, Bucharest, 2009.
[62] M. Dallas. Value and Risk Management: A Guide to Best Practice, Blackwell
[30] J. Kind, J. Baayen, W. Botzen, Benefits and limitations of real options analysis
Publishing, Oxford, 2008.
for the practice of river flood risk management, Water Resour. Res. 54 (4)
[63] O.A. Omitaomu, B.R. Blevins, W.C. Jochem, G.T. Mays, R. Belles, S.W. Hadley,
(2018) 3018e3036.
T.J. Harrison, B.L. Bhaduri, B.S. Neish, A.N. Rose, Adapting a GIS-based multi-
[31] A. Kolios, G. Read, A political, economic, social, technology, legal and envi-
criteria decision analysis approach for evaluating new power generating sites,
ronmental (PESTLE) approach for risk identification of the tidal industry in the
Appl. Energy 96 (2012) 292e301.
United Kingdom, Energies 6 (10) (2013) 5023e5045.
[64] T.L. Saaty. Decision Making for Leaders: The Analytic Hierarchy Process for
[32] T. Pr€assler, J. Schaechtele, Comparison of the financial attractiveness among
Decisions in a Complex World, RWS publications, 1990.
prospective offshore wind parks in selected European countries, Energy Policy
45 (2012) 86e101.