MR SCAFFOLDING LTD.

RISK ASSESSMENT
FOR OPERATIVES OF MR SCAFFOLDING, AND PERSONS AFFECTED BY THEIR OMMISSIONS
WHILE WORKING AT HARRODS
TASK HAZARDS RISK BEFORE CONTROL MEASURES RESIDUAL RISK AFTER
CONTROL NEEDED TO REDUCE RISK IMPLEMENTING
MEASURE IN CONTROL MEASURES
PLACE

Access to and from Slips, trips and falls. Medium Keep all work areas clear from any Low
place of work on site. materials, removal all rubbish and
waste, ensure and enforce good
housekeeping. Provide designated
material storage areas and suitable
compounds, where deemed
necessary.

Manual Handling Injury to back and strains. Medium Instruction and information given to Low
operatives with regards to correct
lifting techniques. Individual loads
to be limited to 25kgs as advised by
HSE where possible or task specific.
Where loads are to be lifted
repetitively the weights, if
practicable to be no more than 20
kg. Move heavy objects with
mechanical means where possible or
enlist the help of others.

Possible collapse of the Injury possible fatality. High Only trained and competent persons Low
scaffold during erection. to erect, the scaffolding in
accordance with British and
European Standard guidelines
BSEN 12811-1

PRODUCED BY MICHAEL COLLIER OF MR SCAFFOLDING 28/05/2012


MR SCAFFOLDING LTD. RISK ASSESSMENT
FOR OPERATIVES OF MR SCAFFOLDING, AND PERSONS AFFECTED BY THEIR OMMISSIONS
WHILE WORKING AT HARRODS
TASK HAZARDS RISK BEFORE CONTROL MEASURES RESIDUAL RISK AFTER
CONTROL NEEDED TO REDUCE RISK IMPLEMENTING
MEASURE IN CONTROL MEASURES
PLACE

Erection of scaffolding. Fall of men and materials. High All Scaffolders will work to the Low
guidelines given by NASC in the
SG4:10 and training by the CITB,
thereby reducing the risk of falls of
men and materials.
Should a Scaffolder be suspended
following a fall the rescue plan will
come into action.

Being struck by moving Injury possible fatality. Med Site traffic plan to be complied with Low
plant or vehicles. and where necessary barriers to be
erected.

Falls From Height Injury possible fatality. High Safe systems of work, to include Low
working off a minimum of 3
properly supported boards, fix
ladder access with progression of
scaffold. Adopt company procedure
for use of safety harness i.e. work to
N.A.S.C Guidance. Work to method
statement.

PRODUCED BY MICHAEL COLLIER OF MR SCAFFOLDING 28/05/2012