Schedule for Civil Work of NALCO BWR Foundation Grid (53-84)

SL No. Description Start Date End date

1 Grid 53-59 (29.000 M Span Type-2)


a Rebar Tying,Shuttering,Fixing of FDN. Bolts of Top Beam 24-04-2020 29-04-2020
b RCC of Top Beam 30-04-2020 30-04-2020

2 Grid 60-67 (40.000 M Span Type-1)


a Earth backfilling and Compaction 29-04-2020 08-05-2020
b Rebar Tying,Shuttering,Fixing of FDN. Bolts of Top Beam 09-05-2020 15-05-2020
c RCC of Top Beam 16-05-2020 16-05-2020
d Grouting of Top Beams (Grid 53-67) 15-05-2020 21-05-2020

3 Grid 68-75 (39.000 M Span Type-1)


a Excavation and RCC Dismantling upto B.O.F 26-04-2020 09-05-2020
b Sand Filling, PCC & Rebar tying of Foundation raft Beams and Columns 10-05-2020 17-05-2020
c Shuttering and RCC of Foundation Raft 17-05-2020 18-05-2020
d Shuttering and RCC of Foundation beams 19-05-2020 21-05-2020
e Shuttering and RCC of Columns (Upto bottom of Top Beams) 22-05-2020 26-05-2020
f Backfilling & Compaction upto bottom of top beams 27-05-2020 05-06-2020
g PCC,Rebar Tying,Shuttering,Fixing of FDN. Bolts of Top Beam 06-06-2020 12-06-2020
h RCC of Top Beams 13-06-2020 13-06-2020

4 Grid 76-84 (42.000 M Span Type-3)


a Excavation and RCC Dismantling upto B.O.F 08-05-2020 18-05-2020
b Sand Filling, PCC & Rebar tying of Foundation raft Beams and Columns 19-05-2020 26-05-2020
c Shuttering and RCC of Foundation Raft 26-05-2020 28-05-2020
d Shuttering and RCC of Foundation beams 29-05-2020 31-05-2020
e Shuttering and RCC of Columns (Upto bottom of Top Beams) 01-06-2020 03-06-2020
f Backfilling & Compaction upto bottom of top beams 04-06-2020 11-06-2020
g PCC,Rebar Tying,Shuttering,Fixing of FDN. Bolts of Top Beam 12-06-2020 19-06-2020
h RCC of Top Beams 20-06-2020 20-06-2020
i Grouting of Top Beams (Grid 53-84) 19-06-2020 25-06-2020
Duration (days) Remarks

6
1

10
7
1
1

14
8
2
3
5
10
7
1

11
8
3
3
3
8
8
1
7
Civil Work Quantities

Sl No. Span RCC PCC


8 MM 10 MM
1 Grid 53-59 (29.000 M Span Type-2) 47.02 -
2 Grid 60-67 (40.000 M Span Type-1) 64.16 9.48 0.251 3.76
3 Grid 68-75 (39.000 M Span Type-1) 227.519 37.21
4 Grid 76-84 (42.000 M Span Type-3) 227.975 39.28

Total Cement Requirement = 223.72 MT


Total Cement Available at Site = 34.80 MT
Balance Requirement = 188.92 MT
Steel
12 MM 16 MM 20 MM 25 MM 32 MM
-
0 1.277 0.252 4.381 3.82 13.745
34.57
35.169