QA/QC DEPARTMENT

INTERNAL SURVEILLANCE REPORT

Date:
Report No:

To,
Jojo Tumpaga
Construction Manager.

Subject: Materials supplied against P.O ( P.O no 9598).


Drawing No:various
Location: Gcc site store, Dhahran.

Comments:
During material receiving inspection we found that the Reducer 2” * ¾” ,SS, class
3000# SCH 40, BW ASTM A182 is threaded in the inner face which is not mentioned
in the purchase order.

Issued By: QA/QC Manager:


R.U.Vattoli.
Name: Bakhtiar alam Sign:……………
Discipline: Mechanical Inspector Date:……………
Sign.. .……………..
Date:………………

Construction Department Comments:


…………………………………………………………………………………………….
…………………………………………………………………………………………….
……………………………………………………………………………………………
…………………………………………………………………………………………....

Responded By: Notified By:


Name:
Discipline: Construction Manager
Sign: Sign:
Date: Date: