DURATION

ITEM MODE DESCRIPTION COST


(DAY) REMARKS
1 1-2 Clearing/Grabbing/Move-in 2 30,240 CP

2 2-3 Excavation 12 24,750 CP

3 2-3 Fabrication of Steel Bars for Footing 4 32,900

4 3-5 Installation of Steel Bars for Footing 4 35,000 CP

5 3-6 Fabrication of Steel Bars for Column - 1 4 37,810

6 6-7 Installation of Scaffolding - 1 3 44,800

7 5-7 Installation of Steel Bars for Column - 1 4 29,400 CP

8 7-8 Pouring of Concrete for Footing 4 42,000 CP

9 7-8 Fabrication of Forms for Column - 1 4 30,800

10 8-10 Installation of Forms for Column - 1 4 31,500 CP

11 8-11 Installation of Electrical and Plumbing 3 203,000

12 11-12 Removal Forms for Wall Footing 1 11,200

13 3-4 Fabrication of Forms for Wall Footing 4 22,400

14 7-9 Installation of Forms for Wall Footing 4 32,200

Fabrication of Steel Bars for Wall


15 4-7 4 30,800
Footing

Installation of Steel Bars for Wall


16 9-10 4 40,600
Footing

17 10-11 Pouring of Concrete for Wall Footing 4 112,000 CP

18 11-12 Pouring of Concrete for Column – 1 4 34,720 CP

19 12-13 Removal Forms for Column – 1 1 19,005

20 13-14 Backfilling 2 72,500

21 11-12 Fabrication of Steel Bars for Beam – 1 4 31,430

22 12-14 Installation of Steel Bars for Beam -1 4 205,270 CP

23 12-14 Fabrication of Forms for Beam – 1 4 35,000

24 14-15 Installation of Forms for Beam – 1 4 35,000 CP

25 15-16 Pouring of Concrete for Beam – 1 4 29,400 CP

26 16-17 Removal of Forms for Beam – 1 1 14,000 CP

27 14-15 Installation of Scaffolding – 2 3 28,000

28 15-18 CHB Wall Laying – 1 6 25,200

29 15-17 Fabrication of Steel Bars for Slab – 1 4 33,600

30 17-18 Installation of Steel Bars for Slab – 1 4 30,800 CP


31 14-15 Fabrication of Forms for Slab – 1 4 37,800

32 17-18 Installation of Forms for Slab – 1 4 53,900

33 18-19 Pouring of Concrete for Slab – 1 4 49,840 CP

Fabrication of Steel Bars for Column –


34 18-19 4 35,000
2

Installation of Steel Bars for Column –


35 19-22 4 28,000 CP
2

36 18-21 Fabrication of Forms for Column – 2 4 14,000

37 21-22 Installation of Forms for Column – 2 4 21,000

38 22-24 Pouring of Concrete for Column – 2 4 25,200 CP

39 24-25 Removal of Forms for Column – 2 1 9,800

40 19-20 Fabrication of Steel Bars for Slab – 2 4 36,400

41 20-24 Installation of Steel Bars for Slab – 2 4 29,400

42 23-24 Installation of Forms for Slab – 2 4 36,000

43 24-26 Pouring of Concrete for Slab – 2 4 52,920 CP

44 21-23 Fabrication of Forms for Slab – 2 4 37,520

45 26-27 Removal of Forms for Slab – 2 1 10,360

Installation of Electrical and Plumbing


46 25-26 3 203,000
–2

47 23-26 Fabrication of Steel Bars for Stairs – 1 4 26,040

48 22-24 Fabrication of Forms for Stairs – 1 4 72,300

49 26-27 Installation of Steel Bars for Stairs – 1 4 64,400 CP

50 26-27 Installation of Forms for Stairs – 1 4 23,800

51 27-29 Pouring of Concrete for Stairs – 1 4 33,600 CP

Fabrication of Steel Bars for CHB Wall


52 26-28 4 30,800
–2

Installation of Steel Bars for CHB Wall –


53 28-29 4 28,700
2

54 29-30 CHB Wall Laying – 2 6 28,700 CP

55 29-33 Installation of Roofing 12 52,493.75

56 27-29 Excavation for Septic Tank 1 23,800

Fabrication of Forms for Wall Footing


57 30-31 2 21,000 CP
Septic Tank
Fabrication of Steel Bars for Slab Septic
58 31-33 2 19,600
Tank

Installation of Steel Bars for Slab Septic


59 33-34 2 21,700 CP
Tank

Pouring of Concrete for Wall Footing


60 32-33 2 21,840 CP
Septic Tank

Pouring of Concrete for Slab Septic


61 34-36 2 21,000 CP
Tank

Installation of Forms for Wall Footing


62 31-32 2 21,000 CP
Septic Tank

Installation of Steel Bars for Wall


63 29-31 2 21,000
Footing

64 33-35 Fabrication of Steel Bars for CHB Wall 2 35,624.01

65 35-36 Installation of Steel Bars for CHB Wall 2 35,624.01

66 36-37 CHB Wall Laying 2 35,624.01 CP

Fabrication of Forms for Slab Septic


67 36-38 2 18,200
Tank (cover)

Installation of Forms for Slab Septic


68 38-39 2 24,800 CP
Tank (cover)

Fabrication of Steel Bars for Slab Septic


69 36-37 2 15,600
Tank (cover)

Installation of Steel Bars for Slab Septic


70 37-38 2 23,800 CP
Tank (cover)

71 37-39 Installation of Plumbing 2 98,000

Pouring of Concrete for Slab Septic


72 39-40 2 18,200 CP
Tank (cover)

73 40-41 Removal of Forms for Slab 1 10,028

74 39-40 Backfilling 1 62,720

Installation of Decorative Interior


75 42-44 8 140,000
Design

76 40-41 Cement Plastering 12 72,940 CP

77 42-43 Installation of Doors 6 84,000 CP

78 42-43 Installation of Windows 6 59,600

79 41-42 Painting Works 12 65,650 CP

80 43-44 Demobilization 3 28,000 CP

Project close out Total 3,425,649