Professional Documents
Culture Documents
Hospital for
COVID-19
CONTRACT No. 259359-100
DISCIPLINE CIVIL
DOC No HOS-SQM-MOS-05
REV 00
Anwar Mukthar
Mukthar Ahmed Eyad Saffarini Ahmed Ba Harmi
Mohiuddin Ahmed
Prepared by Reviewed by Verified by Concurred by Approved by
1|Page
100 Bed Isolation
Hospital for
COVID-19
CONTRACT No. 259359-100
TABLE OF CONTENT
2|Page
100 Bed Isolation
Hospital for
COVID-19
CONTRACT No. 259359-100
1.0 Objective
The objective of generating this method statement is to ensure that the procedure
step by step to implement the correct practices for welding at fabrication yard
and/or project site.
This procedure is issued to describe the work processes involved in construction for
welder and welding qualification procedures. The latest revision of the PROJECT
specifications shall be used as references and is part of this Method Statement in the
execution of work.
3.0 References
i) ASTM A 307
ii) ASTM A 325
iii) AISC
4.1 All safety precautions required shall be fully implemented and observed
during work execution.
4.2 Only authorized and designated personnel shall conduct and complete
the work as required.
4.3 All signboards, barricades and warning signs shall be posted and
Maintained in the working areas as required.
4.4 Personnel protective equipment (PPE) shall be provided and used at all
the time.
4.5 Safe entry and exit access shall be provided and always free from any
obstructions at all times.
3|Page
100 Bed Isolation
Hospital for
COVID-19
CONTRACT No. 259359-100
5.1 The Project Manager is the over-all in-charge for the implementation of
this procedure and ensures that his team is aware of this Method
Statement. He should also ensure that all resources needed in the work
execution shall be available and carry out the work as planned without
delays and in a safe manner and in compliance with EPC HSSEMP
requirements.
5.2 The Site Manager is responsible in the coordination with site supervisor
and foremen for a safe and proper execution of the works.
5.3 Site Engineer and General F/M are directly reporting to the Site
Manager. They should ensure that the works are carried out in
accordance with the approved drawings, applicable standards and this
Method of Statement.
5.4 QC Inspector in close coordination with site personnel shall ensure that
the works are carried out based from the QC project requirements. He is
responsible in conducting and monitoring QC inspection works.
Additionally, he shall ensure that all pertinent QC documentations and
records are prepared and ready for approval.
5.5 Safety Officer is responsible in monitoring the full implementation of all
safety procedures and safety measures at site at all times.
Communication with the Safety Representative is also part of his
responsibility.
5.6 The safety officer to coordinate with EPC HSSE representative for all
matters relevant to EPC HSSEMP requirements.
4|Page
100 Bed Isolation
Hospital for
COVID-19
CONTRACT No. 259359-100
5|Page
100 Bed Isolation
Hospital for
COVID-19
CONTRACT No. 259359-100
8.1 RFI will be initiated for inspections of bolting, as per approved ITP,
Quality Control Plan and Project Specification listed under Technical
Specification or as stated on the latest IFC drawings.
9.0 Equipment
9.1 Spanner
9.2 Spud Wrench
9.3 Impact Wrench
10.0 Material
10.1 Bolts, Nuts & Washers
11.0 Drawings
11.1 FHM-AR-001-00
6|Page