Professional Documents
Culture Documents
Proj. No. :
Steel
Structures
ENGINEER : CONTRACTOR : Erection
For
Steel Structures Erection
Document Number:
00
PROJECT
Guardia Systems SENIOR QA/QC MANAGER
DIRECTOR
CONSTRUCTION
DATE REV MANAGER
``
`
1 / 43 Method Statement for
of Fill
Steel
Installation
Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
Contents
``
`
2 / 43 Method Statement for
of Fill
Steel
Installation
Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
1.1 The purpose of this method statement is to provide a step by step procedure in order to
define the procedure, responsibilities, implementation of correct practices, and risk
associated with supply and installation of the of steel structures, for the Construction to of
reefers, canopies and other steel structures.
1.2 The scope of work includes supply and installation of steel structures.
1.3 This method statement outlines the procedure to be followed for erection of steel structures
for the project.
1.4 This method statement describes the responsibilities, procedure, inspections and/or tests to
be carried out, associated with the works.
2- References:-
3- Definitions:-
Organize & deploy the manpower as per site requirements & making sure the required machines and
tools are in good working conditions.
CE will make sure all the foreman and labor involved in the activity have attend the HSE tool box prior
start working at site.
CE will make sure all the work is performed as per approved drawings and method statement.
Check the work at site prior QA/QC inspection making sure work is ready for inspection as per approved
drawings and project specification.
CE will check all the fabricated reinforcement and installed form work and make sure work is done as
per approved Design drawing and ready for QA/QC engineer inspection.
CE will make sure timely IR will be raised in coordination with QA/QC engineer to get timely approval to
proceed with next activity.
Work effectively with various departments throughout the project to resolve compliance issue.
Making sure proper lighting arrangements are in place at time of erection or delivery at night.
Organize and chair the Safety Toolbox Meeting with the Safety Officer before starting the work.
Organize the work for groups in day to day operation.
Performs 100% pre-checks and pre-inspections before the Site Supervisor do the official checks and
inspections.
HSE engineer will make sure the following precautions were taken prior start activity on daily basis:
Maintain a safe route for pedestrians/other labour involve in project to bypass by the works.
Where required lights to be attached to signing and guarding.
Plant vehicle and tool to be kept inside the work area.
Plant/Machine operators to be trained and competent in the use of the plant/machine they are using.
Keep plant & vehicles away from the edge of the excavation.
Ensure the correct PPE is used for the type of equipment.
Mechanical excavation equipment shall not be used in the vicinity of other utility services.
Ensure the adequate oxygen level in confined areas.
HSE Engineer/Inspector will ensure the following is worn at all times during the works
Hard Hat
Safety boots or wellingtons
High visibility jacket or jerkin
Coveralls
Safety chains
HSE Engineer/Inspector will ensure the following is worn as required during the works
Dust masks – grinding, sawing, cutting or conducting activities that involve airborne dust.
Gloves – when using power equipment or manual handling.
Waterproofs – in wet weather.
6- General Requirements:-
6.1 Materials
Anchor Bolts
Built Up Plates & Beam
Purlins
High Strength Bolt
Sag Rod
Bracing Rod
Welding Consumables
Chemical Anchor
Approved sub-contractor is responsible for erection of steel structures as per the approved execution /
fabrication and sequence drawings.
All the works will be carried out as per approved Design / shop drawing which are approved by the
Engineer and a controlled copy with “Issued for Construction Stamp” will be made available with site
team all the time.
7- Equipment:-
Mobile Cranes
Grinders
Drill Machine
Welding machines
Spanner
Acetylene for cutting
Man lifts
General PPEs
8- Methodology:-
Make sure there is space and firmed pathway for truck delivery, crane truck erection operation. The
suitable truck & crane capacity must be clarified (and listed in the equipment register).
Survey the wind direction to have plan for roof material storage and installation direction.
Decide the plan for unloading and material storage. Choose a firm and dry location. Materials shall
be stored in designated areas for each building and clearly identified for their location in that area.
Make sure that materials supply and storage schedule is appropriate and not conflict with the
installation schedule and other sub-contractors’ schedules.
Register the available power & water supply source locations at the site. Make sure there is a safe
method to lead the supply to the working area.
All delivery to site shall be informed by production people to the site manager 24 hours earlier to
have plan for unloading.
A delivery note is always enclosed with the supplied materials to clarify name of project, location,
building number, type of materials, quantity, date of delivery, etc.….
Upon arrival of materials at the storage yard, the material controller will match delivery notes and
shall verify the consignment. The material controller, then, report to the site supervisor the received
material list and quality condition.
Unloading can be done manually or with cranes. A spreader should be used for lifting long
components. Lifting nylon or cloth belts with suitable SWL (Safe Work Load) shall be used for
unloading the materials to minimize the damage. Be sure to hook belts to component with the right
no. of points and position so that the load of component itself do not damaged or broken.
Always attach a tag line to the lifting component.
All materials receipt at site shall be visually inspected by site supervisor for any damage. Remedial
works to the damage shall be taken immediately, if possible, to avoid any delay to erection.
There are certain erection practices which are in general use and have proven sound over the years.
Below is typical instruction applied for a single/double span structure.
Materials will be transported to job site separately or on the skid put in container and will be
unloaded by crane.
Temporary road in the job site must be prepared properly for heavy crane and trucks without
damage to the access roads.
Prior to unloading materials out of trucks or containers, it is required to take pictures of the
actual material status delivered to job site.
The conditions of each area, the material arrangement plan may different but in general,
materials will be arranging as following principle to ease moving, combination and erection after
later.
Members should be checked park mark as packing list enclosed before unloading for best
unloaded positions.
Columns should be arranged closed to their anchor bolt position.
Rafter members should be arranged to ensure easy assembly and movement.
Girts, purlins, eave struts and bracing are divided according to the requirements of each bay.
Nested parts (purlins, girts etc.) should be separated and blocked to allow drainage of collected
moisture to prevent rusting, prior to erection.
End wall material is laid out for each end.
Small components (nuts, bolts, clips, fasteners etc.) are stored in each area convenient to all
parts of the building.
Wall, roof paneling and other components which will not be used in the initial stage of erecting
the steel, are placed to the outside of the work area, and properly stored and protected from the
weather.
With purpose of preventing and protecting material damages during storage out of
environmental factors such as storm water, dust, etc. which cause rusty, stain, etc. Including
below tasks:
Air Air
Circulation Circulation
Block above
Tie leave Ground
1.5 m max
bottom open
- Tie down cover ends away from stack to permit air circulation. Do not wrap under or restrict air
movement.
- IMPORTANT! Do not use plastic sheeting as a cover because it will promote moisture.
- Sheeting, wire mesh, insulation should be installed right after delivering to job site, if not must be
kept indoors. Where indoor storage is not possible , the above procedure must be applied
8.7 Erection
GENERAL PRINCIPLE
- Do not conduct erection without last Erection drawings issued for Erection.
FLANGE BRACE
ROOF RAFTER
SLING
ROOF RAFTER
SPREADER BAR
SLING
- Only erect rafter after all connections bolts were tighten, rafter was cleaned, and rafter was signed
off.
- All connection joints must be completed bolt tightening before releasing lifting equipment.
MEMBER ASSEMBLANCE
- All assembled members should be bristled by timber bar, cleaned, painted touch up.
- Flange braces should be installed to rafter members then.
- Connection bolts must be tightened and checked on the ground by TURN OF NUT or Torque Wrench
method (see appendix 01).
Procedure for erection columns, rafters to be repeated until frames are completed.
Column Erection:
Preparation
- Columns materials were arranged closed to design position.
- Columns materials need to be cleaned, paint touching up and assembled before erection.
- Attach driven rope to column
- Check level and position of level nuts and anchor bolts with design.
- Check at least 03 temporary anchor points to ensure safe anchor points for column after erection.
These points should be adjacent casted concrete structures (stump, ground beam) where temporary
cable can be tied to. In case of no anchor point available, steel members that are not yet in use can
be temporary applied for temporary anchor point.
- Temporary anchor points should be arranged out of working area to avoid hanging materials can be
caught by temporary cable, this can cause collapse to erected structures.
- Check lifting weight, crane position with capacity of applied crane base on crane specification issued
by manufacturer.
Erection
RAFTER ERECTION:
Preparation
- Scaffolding should be prepared for workers to perform rafter-rafter, rafter column connection.
- Check at least 03 temporary anchor points to ensure safe anchor points for column after erection. These
points should be adjacent casted concrete structures (stump, ground beam) where temporary cable can
be tied to. In case of no anchor point available, steel members that are not yet in use can be temporary
applied for temporary anchor point.
- Temporary anchor points should be arranged out of working area to avoid hanging materials can be
caught by temporary cable, this can cause collapse to erected structures.
- Check lifting weight, crane position with capacity of applied crane base on crane specification issued
by manufacturer
Erection
ERECTION SEQUENCE
Braced bay erection
- Braced bay must be erected in priority
- After completion 02 frames of braced bay, all components such as brace rod , flange brace , etc. of this
bay must be completed as design, to set up the space stable place for next frames. Temporary bracing
should be applied for this bay during erection for safety.
- Braced bay frames must be temporarily aligned before installation purlins, bracings to avoid difficulties
may get if conducting alignment for remained frames after that.
- After completion frames alignment, request to have approval of Client before sheeting task
- Alignment Method is performed in Appendix 03
- Filling grouting should be done before sheeting.
- Remaining frames erection
- Proceed with the erection of the remaining frames and bearing end frames.
- In each braced bay shown on the erection drawings, repeat step 5.3.1 before proceeding with the
erection of additional bays.
- Eave struts and peak purlins may be installed in intermediate bays between braced bays to stabilize
frames, however, do not start more work than can be completed in a work day to ensure all structural
framing is completed in those days before leaving the site at the end of the day.
- As erection progresses, each braced bay must be fully completed as outlined in step 5.3.1 before
proceeding with the erection of additional bays.
- Finish Frames & Accessories
- Complete erection of main and secondary framing
- Upon Completion of all secondary framing in the braced bay, plumbing and squaring the braced bay,
installing secondary framing in the end bay, paneling may commence and be worked in conjunction with
the completion of the balance of the secondary framing. This could save time on larger buildings if
separate sheeting crews are used.
When the building reaches this stage of erection, sheeting should proceed immediately. The structure without sheeting
should not be left standing for prolonged periods of time without taking proper precautions (temporary bracing, blocking
etc.) to prevent wind damage especially to purlins and girts due to excessive vibration they are exposed to in the un-
sheeted condition.
¢ web L
L=L+ A = 3/8 “ 1/4 “/20’
Span L=L-A
A (Max) Theoretical
Support point (Min) span (A = 10cm) (6.3mm / 6m)
(Typical)
¢ web B
Adjacent F = 1/8 “
Beams NA
18`` / 43 Method Statement for
of Fill
Steel
Installation
StructuresF Erection (F =10cm)
`
Top running Under Hung
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
FRAME PLUMBING
By mean of Transit
Wall Brace
rod
Roof Rafter
Hillside
washer
Brace rod/Cable
Cable Flange
Base Plate
``
`
23 / 43 Method Statement for
of Fill
Steel
Installation
Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
9- Program:-
The work plan and time schedule of work will be submit prior to mobilization and commencement of each
activity.
10- QA/QC:-
All material control and above activity shall be controlled as per the approved project quality plan and
procedure.
As a record of joint inspection activity checklist will be provided for inspection and work certification by
contractor representative.
On the basis of activity checklist work inspection request will be submitted later with all supporting
documents.
All work places will be cleaned from waste materials and ensuring clean and healthy work environment as
well as maintain free access and egress in the event of emergency. All generated waste shall be shifted to
the centralized waste segregation area.
12- Safety:-
All the above operation shall be executed in according with the occupational health, safety and
environment plan.
Safety procedures are to be considered before, through and after the completion of the work to avoid any
possibility of danger to humans or the construction.
Movement of vehicles should be controlled to avoid any confusion with any other casual traffic.
All the above operations shall be executed strictly in accordance with Project Occupational Health, Safety,
Security and Environmental Plan, once it becomes an approved document.
Prior to the commencement of any activities, the workforce will receive a safety induction on the project
site safety requirements; this safety induction will include Project HSE Policy, project details and layout,
site management team, general site HSE requirements, emergency procedure including emergency
contact numbers, roles and responsibilities of the workers, site discipline, general environmental
awareness, PPE requirements.
``
`
24 / 43 Method Statement for
of Fill
Steel
Installation
Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
The HSE roles and responsibilities shall be delivered to all staff (construction manager, engineer,
supervisor, foremen, and charge hand).
All activities will be performed according to the control measures and instructions prescribed in the
attached Risk Assessment Sheets.
All Vehicles will have valid licenses and passes before entering the site.
PPE shall be issued to all personnel (Mandatory PPE’s: Hard hat, Safety glass, high visibility vest, Safety
shoes and cover all. Task specific PPE; Dust mask, goggles, hand gloves).
Specific training shall be given for task specific tools and equipment’s; records shall be kept in HSE
department.
Heat stress training will be provided during summer time, records shall be kept in HSE department.
Welfare facilities will be provided to all personnel (toilet, rest room, first aid room etc).
Adequate cool drinking water, shade and hydrolyte shall be placed.
Plant and equipment shall have back up alarms, lights and all other applicable safety devices.
Provide Banks man when operating equipment reverse and moving the equipment where pedestrian
movement is exist.
Risk assessment could be reviewed anytime followed the instructions of consultant or change in activity or
regulations.
Requirement of the Project Emergency Preparedness and Response plan shall be strictly followed.
In the event of an accident, contact the area HSE Supervisor.
Easy means of access/Rescue the workers will be available at all time.
Contact numbers of all emergency supervisors will be distributed to site personnel (Site engineer, Safety
officer, male nurse and concerned authorities and emergency services).
Injuries will have the highest priority to be directly dealt with at once.
There are different types of situations that we need to consider under this section. These are:
Basic first aid – approved first aider shall check for the required treatment.
Medical – to be taken to the nearest hospital if it’s not cleared from basic first aid.
Property damage – any damage to existing property or utility the respective authority shall be notified
Fatality – Call ambulance and police immediately
Fire – Call civil defense immediately
``
`
25 / 43 Method Statement for
of Fill
Steel
Installation
Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
``
`
Basra Multipurpose Terminal EEMMPPLLOOYYEERR:: Steel Structures Erection
Proj. No. :
ENGINEER : CONTRACTOR :
Responsibility1
Frequency of Applicable Control
Acceptance Inspectio Completion
SN Inspection / Test to be carried out Test / Specificatio Data / Contractor
Criteria n Method Engineer Third Party Date
Inspection n / Standard Forms
VMF ELM
Review,
ER C.5.2
Once for all check
Materials &
1 Material Approval proposed MAR
ER C.5.3
MAR and P R H,A N/A
materials approve
Testing
the MAR
Check,
ER C.5.14 Type ,
Delivery
Material Delivery, Storage & Transport, Qty &
2 Protection
100% MAR & TDS
Handling
Note &
Protection
P P A N/A
MIR
and Storage storage at
site
``
`
27 / 43 Method Statement for Steel Structures Erection
Basra Multipurpose Terminal EEMMPPLLOOYYEERR:: Steel Structures Erection
Proj. No. :
ENGINEER : CONTRACTOR :
Measurement
Receiving & Inspecting of Dimensions Approved
8 structural steel parts & Exactness
&
Drawing
MAR P S A N/A
Visual
Measurement
Location of anchor bolts (if Approved
9 applicable)
Dimensions &
Drawing
IR P S S N/A
Visual
Dimensions
Approved
10 Structural Steel Installation &Correctnes Visual
Drawing
IR P S H,A N/A
s
Correctness Measurement
Machine/Anchor Bolt Tightening Approved
11 Check
& Bolt &
Drawing
IR P S H,A N/A
Tightening Visual
Dimensions Dimensions
Approved
12 Grouting & &
Drawing
IR P S H,A N/A
Correctness Correctness
Note (1): H: Hold Point, W: Witness, R: Review, S: Surveillance, A: Approval, P: Perform / Execute
``
`
28 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR:: Steel
Proj. No. : Structures
Erection
ENGINEER : CONTRACTOR :
``
43`
29 / 17 Method Statement for
of Fill
Structural
Steel
Installation
Structures
Concrete
Erection
``
`
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
RISK ASSESSMENT
TITLE OF THE ACTIVITY: Installation of Steel Structure
5 4 20 3 1 3 YES
``
`
``
` 30 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
``
`
``
` 31 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
``
`
``
` 32 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
CRANE TO BE LOCATED ON LEVELLED
SURFACE & OUTRIGGERS TO BE FULLY
EXTENDED & PLACED ON PACKING.
PRE LIFT PLAN TO BE FILLED OUT PRIOR OF
EVERY LIFT
LIFTING AREA TO BE BARRICADED AS TO
AND SIGNED (KEEP OUT)
TRAINED, COMPETENT RIGGER SHALL BE
APPOINTED AND MUST BE AWARE OF
THE LIFTING PROCEDURE
``
`
``
` 33 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
``
`
``
` 34 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
``
`
``
` 35 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
EXTINGUISHERS SHOULD BE
AVAILABLE ONSITE.
ENVIRONMENT PAINTS / THINNER ENVIRONMENT 3 3 9 SEPARATELY AND PROPERLY DISPOSED OFF BY LICENSED 1 YES
AGENT.
DAILY INSPECTION OF EQUIPMENT FOR LEAKS
COMPETENT PERSONS
``
`
``
` 36 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
REQUIREMENTS
``
`
``
` 37 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
REQUIRED
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
OPERATOR TO FOLLOW THE EQUIPMENT LIFTING CHART
``
`
``
` 38 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
EQUIPMENT USE)
Reduced
Task Hazard Hazard effect(consequence) C L Risk Proposed Control Measures Alarm
Risk
``
`
``
` 39 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
REPLACED
OPERATIONS
Persons in danger
Persons passing the site location/ truck routes, e.g. members of the public and persons in the Vehicles.
All personnel in the team are to be made aware of the safe systems of work.
Emergency procedures
Site emergency procedures should make provision for the rescue of individuals from heights.
First-aid facilities should be available to cope with any significant injuries that may arise from the work.
``
`
``
` 40 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Work should be monitored by Erection Foreman and charge hand who are trained to ensure that any additional precautions or equipment required are provided.
``
`
``
` 41 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
RISK MATRIX
Consequence
Probability
Insignificant – 1 Minor – 2 Moderate - 3 Major - 4 Catastrophic - 5
Rare-1 1 2 3 4 5
Possible-2 2 4 6 8 10
Likely-3 3 6 9 12 15
Often-4 4 8 12 16 20
8 to 12 High Risk Activity or industry should be modified to include remedial planning and action and be subject to detailed OSH Assessment
4 to 6 Moderate Risk Activity or industry can operate subject to management and / or modification
``
`
``
` 42 / 43 Method Statement for Steel Structures Erection
BASRA MULTIPURPOSE TERMINAL EEMMPPLLOOYYEERR::
Proj. No. :
Quick, easy controls should be implemented immediately, and further action planned for when resources permit. Monitoring
1-4
required ensuring controls are maintained. Manage through routine procedures. Go for economic improvements where
Low
possible. Incident report must be completed.
Aim to reduce risks but costs of prevention may be limited. Undertake a risk assessment of the situation / task and implement
the appropriate actions. Actions should have a timescale and should be monitored. Where the risk involves work in progress
5-12 undertake a risk assessment as soon as possible to ensure the safety of the situation or task. Work should not start until the
Medium risk is reduced to an acceptable level. Considerable resources may have to be allocated. Contact your Manager and Risk
Manager by telephone about the actions that should be taken to reduce the risk/s. incident report must be completed. Incident
must be added to service risk register.
Do not commence the activity until a risk assessment has been completed to ensure the safety of the situation or task. If it is
15-25 not possible to reduce or eliminate the risk even with unlimited resources, work must remain prohibited. Inform your relevant
High Director, your Manager, and the Risk Manager immediately by telephone. Incident report must be completed. Incident must be
added to service risk register.
``
`
``
` 43 / 43 Method Statement for Steel Structures Erection