Professional Documents
Culture Documents
DISCIPLINE CIVIL
DOC No HOS-QA-THA-ACWA-005
REV 00
Anwar Mukthar
Mukthar Ahmed Eyad Saffarini Ahmed Ba Harmi
Mohiuddin Ahmed
Prepared by Reviewed Verified by Concurred by Approved by
by
TABLE OF CONTENT
1|Page
100 Bed Isolation
Hospital for COVID-19
1 – Objective
2 – Scope of Work
3 – References
4 – Safety Requirements
5 – Key Personnel Duties and Responsibilities
6 – Job Safety Analysis
7 – Work Procedure
8 – Testing and Acceptance
9 – Equipment
10 – Material
11 – Drawings
1.0 Objective
2|Page
100 Bed Isolation
Hospital for COVID-19
3.0 References
Project Specifications
ASTM D 1556
ASTM D 1557
3|Page
100 Bed Isolation
Hospital for COVID-19
5.2 The Site Manager is responsible in the coordination with site supervisor and
foremen for a safe and proper execution of the works.
5.3 Site Engineer and General F/M are directly reporting to the Site Manager.
They should ensure that the works are carried out in accordance with the
approved drawings, applicable standards and this Method of Statement.
5.4 QC Inspector in close coordination with site personnel shall ensure that the
works are carried out based from the QC project requirements. He is
responsible in conducting and monitoring QC inspection works. Additionally,
he shall ensure that all pertinent QC documentations and records are
prepared and ready for approval.
5.5 Safety Officer is responsible in monitoring the full implementation of all
safety procedures and safety measures at site at all times. Communication
with the Safety Representative is also part of his responsibility.
6.1 An open cut type of excavation shall be applied with safe side slopes.
6.2 Shoring and bracing system shall be used whenever required to protect
adjacent structure if any, in an excavation site or when the excavation
side slope is steeper than those mention below.
6.3 Suitable and appropriate excavator and compacting equipment shall be
used to carry out the works.
6.4 Safe angle and clearance of excavation:
The entire excavation slope shall be as per project specification of
excavation specification. Angle =45° is applied to major soil strata found
in the Plant site. Clearance of 1.0 meter from excavation top edge to
barricade shall always be kept.
6.5 Excavated soil material will be removed immediately from the work site
and equipment shall be kept away from the excavation top edge.
6.6 All access walkways, Ramps, Stair & Bridges shall be equipped with guard
rails. All Walkway crossings shall be equipped with tightly secured
uniformly sized planking. There shall always be a safe access way for
entry and exit. For excavations that are long, there shall be an access
way as per requirements.
6.7 First aid facility will be available entire the period in the work site.
4|Page
100 Bed Isolation
Hospital for COVID-19
7.1 Verify the detail of excavation according to the latest Issued for Construction
(IFC) drawing before the start of the work. Conduct a survey and mark the location
and limits of the area to be excavated. Allowance should be provided to have
enough working space between the foundation to be constructed and the edge of
the bottom of the excavation for the personnel and forms, bracing and supports to
be installed. In marking the excavation limits, consideration should also be given for
additional area to accommodate side slopes of the excavation.
7.2 Determine the depth of the excavation from the existing ground taking
reference from the latest IFC drawing.
7.5 Use mechanical excavator whenever possible and if the site condition
permits. Excavation permit will be obtained before starting the work. Excavate
manually around existing structure or in congested area where the use of power
machines are not possible.
7.7 Where the excavation site is close to the existing structures, sufficient shoring
and bracing system shall be planned and approved by safety department and then
built against the excavation wall to prevent any possible collapse of the excavation
slope and also damage to the structures. Where the excavation extends below the
foundation of existing adjacent structures well planned and approved measures to
protect that structure must be provided.
5|Page
100 Bed Isolation
Hospital for COVID-19
7.8 Excavate up to the desired level, width and length as required to conform to
the latest IFC drawing. The vertical tolerance shall be as per specification.
7.9 When the desired bottom elevation is reached, level and compact the ground
by using an appropriate machine such as roller, jumper or plate compactors up to the
required density to confirm with the Project Specification requirements.
7.10 Remove and replace with compacted suitable fill, any sort of contaminated
soil, if any, found at excavation bottom.
7.11 Backfilling will commence only after completion of inspection and test of
below grade structures is complete
7.12 Structural fill or backfill placed beneath footings, grade beams, mat
foundations, or any settlement sensitive structure shall be compacted to at least 95
percent of maximum dry density as determined by ASTM D 1557
7.13 Backfilling adjacent to structures and not supporting any footing, grade
beams or mat foundations, shall be compacted and then tested for in-place density in
accordance with ASTM D1556. The tested density shall be at least 90 percent of the
maximum dry density as determined by ASTM D1557.
7.14 The moisture content of the material being compacted shall be within
percent of the optimum moisture content as determined by ASTM D1557.
7.16 Backfilling will be done using the approved fill material or select granular
material as per drawings. Each layer will be compacted to a dry density, depending
on the area of working when granular material is used, it will be compacted to a firm
6|Page
100 Bed Isolation
Hospital for COVID-19
and stable condition using an appropriate compacting device. Backfill material shall
conform to relevant project specifications.
7.17 Backfilling will proceed symmetrically about the structure, whenever possible
to do so.
7.18 The concrete sides will not be backfilled until the specified coatings are
applied and fully cured on the concrete surface.
7.19 The water for the compaction will be added uniformly. If required, the fill
material will be ploughed to uniform water content before compacting. If drying is
required, the same will be done by way of natural drying. In cases additional dry
material is added for drying, care will be taken to see that the layer thickness does
not exceed that specified.
9.0 Equipment
9.1 Backhoe (power excavator)
9.2 Loader
9.3 Dump Truck, Water Tanker, Fuel Tanker
9.4 Roller Compactor, Plate Compactor, Ram Compactor, Hand Shovel
9.5 Crowbar
9.6 Shoring Materials
10.0 Material
10.1 Excabated fill material if it is complying with Project Specification
10.2 Imported Engineering fill materials complying with Project Specification
7|Page
100 Bed Isolation
Hospital for COVID-19
11.0 Drawings
11.1 FHM-AR-001-00
8|Page