Professional Documents
Culture Documents
Final Drainage Design Project
Final Drainage Design Project
LIST OF TABLES................................................................................................................iii
LIST OF FIGURES..............................................................................................................iii
DECLARATION......................................................................................................................iv
ACKNOWLEDGEMENT.........................................................................................................v
ABSTRACT..............................................................................................................................vi
1.0 INTRODUCTION................................................................................................................1
1.1 Background:.....................................................................................................................1
1.2 Problem Statement...........................................................................................................2
1.3 Project Justification:.........................................................................................................2
1.4 Objectives.........................................................................................................................2
1.4.1 Main objective:..........................................................................................................2
1.4.2 Specific Objectives:..................................................................................................2
1.5 Scope:...............................................................................................................................2
1.6 Summary of Methodology...............................................................................................3
2.0 LITERATURE REVIEW.....................................................................................................4
2.1Introduction.......................................................................................................................4
2.2 Types of drainage.............................................................................................................4
2.3 Hydrological study...........................................................................................................5
2.4 Determination of runoff...................................................................................................5
2.5 Estimating the design flow:..............................................................................................6
2.6 Hydraulic design..............................................................................................................6
2.7 Culvert design..................................................................................................................7
2.8 Open drainage channels...................................................................................................8
2.8.1 Types of open drainage channels..............................................................................8
2.8.2 Factors to be considered for selection of channel type.............................................8
2.9 Culverts............................................................................................................................8
3.0 DATA COLLECTION AND ANALYSIS........................................................................10
3.1 Introduction....................................................................................................................10
3.2 Frequency Analysis........................................................................................................10
3.3 Estimation of design rainfall intensity:..........................................................................14
3.4 Channel design...............................................................................................................14
3.4.1 Determination of channel dimensions.....................................................................14
3.4.2 Culvert design.........................................................................................................19
4.0 CONCLUSION..................................................................................................................20
i
5.0 RECOMMENDATIONS...................................................................................................20
REFERENCES.........................................................................................................................22
APPENDICES..........................................................................................................................23
APPENDIX 1.......................................................................................................................23
APPENDIX 2: BOOKING SHEETS FOR LEVELLING...................................................24
APPENDIX 3: DETAILS OF THE CULVERT..................................................................26
APPENDIX 4: NORMOGRAPH........................................................................................27
APPENDIX 5: TABLE FOR MANNING’S n VALUES....................................................28
ii
LIST OF TABLES
Table 3.1:Maximum daily rainfall 10
LIST OF FIGURES
Figure 3.1: Plot of daily maximum rainfall against return period 11
Figure A4 – Normograph 26
iii
DECLARATION
We, the undersigned, hereby declare that this report is our original work. All errors and
omissions are solely our responsibility.
iv
ACKNOWLEDGEMENT
First of all we would like to sincerely thank Mr. F. Mukasa and Dr. Umaru Bagampadde
for the guidance and encouragement during the entire project period
We are also grateful to Mr. John Clifton of the Civil Engineering Surveying department
for having allowed us to use their equipment whenever we needed it.
Our thanks also go to the Geography and the Meteorological departments, Makerere
University for providing us with the topographical map and precipitation data
respectively.
Above all we thank the Almighty GOD for the gift of life and wisdom. With him, anything
is possible.
v
ABSTRACT
This project attempts to design an efficient, economic easy-to-maintain drainage system
for the Western gate of the university under construction. Various natural and man-
made facilities were considered.
The method used to analyze the catchment drainage was the Rational method:
Where
Q – discharge
C – runoff coefficient of the catchment
i – rainfall intensity
A – catchment area
Development of IDFs, determination of intensities and return periods for 20 years were
achieved by analysis of rainfall data.
Catchment areas were calculated from a detailed contour map of the area.
A land survey was also done to establish the existing levels and slopes which were used
in the design of the channels.
The discharge Q, for each drainage feature was computed and used to calculate the
dimensions of the channels using Manning’s equation. Four channel sizes were
developed to cater for different discharges. Culvert diameter was also calculated and the
culverts were to be put at points where channels cross the road.
Sketch drawings to be used as guide in construction have also been produced.
vi
1.0 INTRODUCTION
1.1 Background:
Drainage is the process of interception and removal of water from over, and under the
vicinity of the road surface. Drainage can be surface (where water is conveyed on the
road surface and drainage channels), or subsurface (water flows underneath the
pavement structure).
Surface and subsurface drainage of roads critically affects their structural integrity, life
and safety to users, and is thus important during highway design and construction.
Road designs therefore have to provide efficient means for removal of this water; hence
the need for road drainage designs.
Drainage facilities are required to protect the road against damage from surface and sub
surface water. Traffic safety is also important as poor drainage can result in dangerous
conditions like hydroplaning. Poor drainage can also compromise the structural
integrity and life of a pavement. Drainage systems combine various natural and man
made facilities e.g. ditches, pipes, culverts, curbs to convey this water safely.
Various roads in Uganda have poor drainage facilities, with surface run off not being
catered for properly. Rainfall and surface run off onto and in the vicinity of the road
have to be removed quickly to ensure integrity of the road structure. The drainage
design must allow for storm water to be transported along or away from the road in the
cheapest, simplest and most efficient way without damaging the road or surrounding
structures.
The road under discussion is the new Western gate entrance to the University at the
Faculty of Technology. The road is under construction, and it was noticed that the
existing drainage does not cater for the design of the road; as such, water flows over the
road whenever there is a downpour. Hence there is a need for a comprehensive
drainage facility.
1
1.2 Problem Statement
As stated, the road is being redesigned to cater for an entrance to the University direct
from the Kikoni area of Makerere. Therefore a new drainage system has to be designed.
However, the existing road and drainage from the faculty down to Gatsby to Kikoni is
showing signs of failure, caused mainly by poor drainage.
Therefore, there is a need to improve on the current drainage design in some of the
areas leading to the existing road, and design of a new system leading to the new gate.
1.4 Objectives
1.4.1 Main objective:
Design of an efficient, easy-to-maintain drainage system from the new Western gate to
the Gatsby garage.
1.5 Scope:
This project was confined only to designing a drainage system for the road from the
junction to the faculty of Technology via Gatsby to the western gate.
2
1.6 Summary of Methodology
Reconnaissance study of the area to determine existing conditions. This involved
taking photos of the existing drainage features, the road and the current state of
the project.
Literature review using the internet, various textbooks and existing reports on
similar projects, drainage design manuals.
Obtaining rainfall data from the meteorological department, and analysis to
determine rainfall intensities. The data used was 10 year maximum daily rainfall,
1999-2008.
Surveying along the road to determine slope of road, position of drainage
channels.
Use of topographic maps from the geography department to obtain catchment
areas and slopes.
Design of the channels. Involved analysis of the rainfall data to obtain catchment
and sub catchment discharges. These were used to select suitable drainage
channel cross-sections and culvert sizes to be used in the drainage design.
3
2.0 LITERATURE REVIEW
2.1Introduction
Highway drainage is the process of interception and removal of water from over, under
and in the vicinity of the pavement.
Highway drainage is one of the most important factors in road design and construction.
If every other aspect of the highway design and construction is done well but drainage
is not, the road will quickly fail in use due to ingress of water into the pavement and its
base.
The damaging effects of water in the pavement can be controlled by keeping water out
of places where it can cause damage or by rapidly and safely removing it by drainage
methods.
Improper drainage of roads can lead to;
Loss of strength of pavement materials
Hydroplaning
Mud pumping in rigid pavement
Stripping of the bituminous surface in flexible pavements
4
The main source of surface water in most places is precipitation in form of rain. When
precipitation falls on an area, some of the water infiltrates in to the ground while a
considerable amount remains on top of the surface as surface run off.
Surface drainage must be provided to drain the precipitation away from the pavement
structure. This can be done through use of shoulders, ditches and culverts.
Surface drainage design includes the prediction of runoff and infiltration as well as open
channel analysis and culvert design for movement of surface water to the convenient
locations or naturally occurring paths. So, the surface drainage study can be
conveniently divided into two parts namely.
Hydrological study - which is concerned with the determination of water reaching the
inlet of the drainage ditch or culvert.
Hydraulic study – it is concerned with design of facilities needed to handle the water
arriving at the inlet.
5
2.5 Estimating the design flow:
1. Estimation of watershed area from a topographic map.
2. Obtain cover factor c from tables. It may be necessary to obtain the weighted
average in the drainage area, by weighting each c value with the proportion of
the drainage area it covers.
3. Hydraulic length, and slope G obtained from the site map. It may also be
necessary to determine the different and G values for different cover factors,
c.
4. Obtain the factor for each homogenous portion along the hydraulic length.
Most hydraulic designs are done by the use of Manning’s equation given by:
6
n – Manning’s constant
Area, wetted perimeter, hydraulic radius, and channel top width for standard channel
cross-sections can be calculated from geometric dimensions.
The minimum diameter of a pipe culvert under a road should be 600 mm or its
equivalent in corrugated metal pipe arches. Wherever culverts are laid on grade
producing self-scouring velocities and where maintenance is not likely to be a problem,
the minimum size may be decreased to 450mm diameter.
Similarly, the minimum size of precast concrete portal type culvert under a road should
be 750mm x 450mm. This may be reduced to 450mm x 300m wherever self-scouring
velocities through the culvert can be achieved, resulting in a maintenance free structure.
The 750 mm minimum recommendation applies for cross culverts where cross slopes
are not less than 3%. It also applies for side-drains or drives.
Note:
In the design of open channels, it is also important to calculate the critical depth in
order to determine if the flow in the channel will be subcritical or supercritical. If the
flow is subcritical, it is relatively easy to handle the flow through channel transitions
because the flows are tranquil and wave action is minimal. In subcritical flow, the depth
7
at any point is influenced by a downstream control, which may be either the critical
depth or the water surface elevation in a pond or larger downstream channel. In
supercritical flow, the depth of flow at any point is influenced by a control upstream,
usually critical depth.
d = V/g
2.9 Culverts
A transverse and totally enclosed drain under a road. They can either be prefabricated
or constructed in place.
8
They are constructed in many shapes: circular, box, elliptical, and from a variety of
materials depending on structural strength, cost, and durability. Most common are
concrete, corrugated steel and aluminium.
9
3.0 DATA COLLECTION AND ANALYSIS
3.1 Introduction
Some important terms and definitions used in obtaining the design flow
Return period, T
This is the average interval between occurrence of storms or floods of the same
Time of concentration,
The time required for a particle to flow from the hydraulically most distant point in the
water shed to the outlet or design point. Various factors affect the time of concentration;
slope of the path, length of flow, roughness of the flow path.
Peak design flow
This is the maximum flow rate of a flood wave passing a point along a stream. As the
wave passes the point, its flow increases to the maximum and recedes. It is a major
factor in culvert designs, and its magnitude is dependent on the selection of the return
period.
10
Table 3.1:Maximum daily rainfall.
The values of daily maximum rainfall against the duration (1 hour) were ranked from 1
to N, in descending order. Corresponding return periods were estimated using Weibull’s
plotting position formula:
The maximum rainfall depths were plotted against return periods on a semi-log paper
and a line of best fit plotted through the points.
11
Figure 3.1: Plot of
daily maximum
rainfall against
return period.
The correlation
coefficient
between the
maximum daily
rainfall and log
of return period was determined.
From the graph maximum rainfall depth at desired return periods were read off from
the graph. The maximum 24 hr intensity and coefficient were then computed for
, and
The desired sequence of duration (e.g. 10, 15, 30 minutes) was chosen for each set of
data, and used to calculate the rainfall intensity using the formula:
12
- The effective duration of storms in the area, was estimated at 1. This was
The Intensity Duration Frequency curves were then developed by plotting values of
intensity against duration for each return period.
13
Figure 3.2: IDF for the rainfall data.
Where
14
– coefficient of runoff for a particular surface, read from table 1
- correspondng area
b
1
2
d
Area
Wetted perimeter
Hydraulic radius
There were two unknowns in the above equations; a and b. one of the unknowns has to
be fixed in order to solve the equations; in this case, let a be fixed.
4) Velocity, V. calculated from Manning’s equation
Where
V – mean velocity
15
n – Manning coefficient of channel roughness
R – hydraulic radius
S – slope
5) Discharge Q is calculated from
values, iterations were carried out by varying the values of d until they were close as
possible. The corresponding depth d was taken as the corresponding design depth.
For drain 1
Q1 4 x126.25 x0.15 x0.85 64.39m 3 / hr
0.018m 3 / s
The discharge for this channel is 0.018 . This gives a small velocity that may be
safely carried by a kerb and gutter; hence design for a kerb and gutter.
Where: K c = 0.377
n = Manning's coefficient
16
Q = flow rate, m3/sec
The above equation neglects the resistance of the kerb face since this resistance is
negligible.
Data
Q=0.018 m3/s
K c = 0.377
S L = 0.121
0.377
0.018 x0.021.67 x 0.1210.5 T 2.67
0.012
T 2.67 1.132
T 1m
For drain 2,
Paved area A1 = 23482.78 m2
Vegetated area A2 = 3368.78 m2
Q2 0.85 x 23482.78 x0.15 0.15 x3348.78 x0.15
3069.85m 3 / hr 0.853m 3 / s
Qac=0.853 m3/s,
17
Manning’s n=0.013 (concrete base with sides of dressed stone in mortar)
DRAIN 2
a(m) d(m) Q(m3/s) A(m2) V(m/s) b(m) Comment
0.400 0.700 0.540 0.525 1.029 1.100 LOW
0.400 0.750 0.785 0.581 1.351 1.150 LOW
0.400 0.800 1.118 0.640 1.747 1.200 HIGH
0.400 0.287 0.856 0.156 5.481 0.687 OK
Table3.5: Iterations for drain 2.
For drain 3
Q=0.099m3/s and manning’s for ordinary lined concrete n=0.013
DRAIN 3
a(m) d(m) Q(m3/s) A(m2) V(m/s) b(m) Comment
0.100 0.150 0.151 0.034 4.487 0.300 HIGH
0.100 0.100 0.075 0.015 5.000 0.200 LOW
0.100 0.125 0.077 0.020 3.791 0.225 LOW
0.100 0.145 0.100 0.025 4.020 0.245 OK
Table 3.6: Iterations for drain 3.
v 4.020
dc
g 9.81
d c 0.41
Since dc >d flow in the channel is subcritical flow which is desirable. A depth of 0.15
will be used.
For drain 4
Q=0.174m3/s and using manning’s for ordinary lined concrete n=0.013
DRAIN 4
18
a(m) d(m) Q(m3/s) A(m2) V(m/s) b(m) Comment
0.300 0.125 0.094 0.045 2.084 0.425 LOW
0.300 0.160 0.142 0.061 2.331 0.460 LOW
0.300 0.190 0.189 0.075 2.514 0.490 HIGH
0.300 0.182 0.176 0.071 2.467 0.482 OK
Table 3.7: Iterations for drain 4.
v 2.467
dc
g 9.81
d c 0.251
19
d = 0.448 m
This is equivalent to using culverts of diameter =450mm which is available on the
market.
For the cross section drawings, see the appendix
20
4.0 CONCLUSION
The project required design of a suitable drainage system from the given data. Analysis
provided the following data.
Return period – 20 years
Time of concentration – 3.36 minutes
Design intensity – 150mm/hr
Discharges in :
o Drain 1 – 0.018
o Drain 2 – 0.853
o Drain 3 – 0.099
o Drain 4 – 0.174
The discharges above were used in the design of the drainage channels. The dimensions
produced are feasible and can be used for construction.
5.0 RECOMMENDATIONS
The following recommendations were made regarding the existing and proposed
drainage designs:
The data provided was insufficient; the maps were outdated and did not have some of
the new developments like the faculty extension, while the rainfall data lacked the
storm durations. The faculty should provide updated maps with all current features,
while the Meteorological department should be pressed to provide more
comprehensive rainfall data.
The slope cut on the upper section of the road junction is very steep and should not be
left bare as this will lead to erosion by run off. The slope should either be cut to reduce
the slope angle and grass planted on it or it can be stone lined so that the soil wall is
protected from erosion.
21
In order for the drainage channels to function efficiently and to enable them reach their
design life, routine maintenance works such as desilting should be done since the
designs were done without considering the expected sediment load.
Students should be given chance to participate in more feasible projects like this
particular one. This project has enabled us to apply concepts learnt in class for example
collecting and analyzing data, designing from first principles and making sound
engineering decisions in the field.
Sections of the drainage channel along Sir Apollo Kaggwa road are earth channel. This is
unsuitable for the volumes of water to be carried by the channel due to the ease with
which earth is eroded by high velocity water. We recommend that the earth channel
sections be lined with stone.
22
REFERENCES
Ministry of Works Design Manual
Highways Engineering Volume Two by C.A. O’flaherty
The Hand Book of Highway Engineering by T.F.FWA, CRC press 2006
Open Channel Hydraulics by V.T. Chow
23
APPENDICES
APPENDIX 1
A– D drain 3,
along route 1
B– C B drain 4,
along route 2
C– drain 4,
along route 3
D– proposed
culvert
A
ROUTE 1
24
2.81 0.78 95.239 CH 0+60
2.253 3.527 0.717 94.522 CH 0+50
3.585 1.332 93.190 CH 0+40
25
Route Vertical distance(m) Distance along route(m) Horizontal distance(m) Slope
Route 1 lower 4.747 40 39.94 0.119
Route 2 -3.067 42 41.89 0.073
Route 3 -1.077 50 49.99 0.022
Route 1 upper 5.81 60 59.72 0.097
26
Figure A2 – Section through road showing culvert
APPENDIX 4: NORMOGRAPH
27
Figure A4 – Normograph
28
29