Professional Documents
Culture Documents
Embankment Dam-(HE-621)
2021
Introduction
1
CONTENTS
3 Rock Fill Dams
01 River Basin
12
02 Surface Water
122 BCM
03 Ground Water
2.6 BCM
Cont…
Potential and Status of Water Resources Development in Ethiopia
Irrigation
Hydropower
Water Supply
Flood Control
Recreation
Others
1.2 Merits & Demerits of Dams
■ Embankment Dams
They are sensitive to overtopping and leakage, and erosion in the dam
A spillway can be placed at the crest, and if required over the entire length of the dam.
Chambers or galleries for drainage, tubing and ancillary works can readily be housed within the
dam body.
Homogeneous type
Zoned type
Diaphragm type
Cont….
■ Homogenous type
A purely homogeneous type of dam is composed entirely of a single
type of material.
The material must be sufficiently impervious to provide an adequate
water barrier.
Fully homogeneous section might be found convenient where the
slopes are required to be flat because of a weak foundation.
Piping at d/s slope
Cont….
Homogeneous dam with toe drain
Cont….
■ Homogeneous dam with horizontal blanket
Cont….
■ Homogeneous dam with chimney drain and horizontal
blanket
Cont….
■ Zoned type
A central impervious core is flanked by shells of materials
considerably more pervious
The shells enclose and protect the core.
The upstream shell affords stability against rapid drawdown and the
downstream shell acts as a drain that controls the line of seepage.
The central core constructed by clay, silt, silty clay or clayey silt.
Cont….
■ For the rock fill embankment dams, the following variants are common:
Note:
1-Consolidation grouting
2-Curtain grouting
3-Contact grouting
Cont….
Curtain Grouting
■ Is located in the dam foundation which is close to the upstream of the
water, forming a continuous anti-seepage curtain wall.
■ A grout curtain usually consists of a row of vertically drilled holes filled
with pressurized grout, a process commonly known as pressure grouting.
■ Because of the big work quantity and the time conflict with dam body
construction, curtain grouting is usually arranged in the dam foundation
grouting gallery to construct.
■ It can achieve dam body lift and bedrock grouting rise synchronously.
Besides, it also ensure that grouting construction has a certain concrete
weight.
■ Purposes: Reduce the seepage flow of dam foundation, decrease the
seepage pressure for the bottom of dam, guarantee the seepage stability of
foundation.
Cont….
Consolidation Grouting
■ Consolidation grouting is appropriate to be conducted when there is a
certain thickness of dam foundation concrete.
■ Purposes: Improve the bedrock integrity and strength, decrease the
bedrock permeability.
Cont….
H-the height of reservoir above the top of the grout curtain in a specific location
Cont….
Contact Grouting
■ Contact grouting should be arranged after dam concrete reached a stable
temperature.
■ It can prevent the shrinkage cracking of concrete.
■ Purposes: Strengthen the combination ability between dam concrete
and dam foundation or abutments. Improve the anti-sliding stability
property of the dam.
Cont….
Cement grouting construction
1. Drill Hole
■ Drillings of curtain grouting should adopt rotary drilling rig
and diamond drill bit or carbide drill bit.
■ Consolidation grouting should adopt various appropriate
drilling rigs and drill bits.
■ The quality of drill hole has a big impact on the quality of
grouting to ensure the hole depth, hole direction and hole
location comply with the design requirements.
Cont….
2. Drill Hole (crack) Washing
■ Wash out the rock powder remaining in the bottom of the hole
and the iron dust adhering to the hole wall.
■ Wash out the filling in rock stratum crack.
■ Generally it adopts the grouting pump to force water into the
circulation line of the hole to wash.
■ Rock stratum crack washing includes single-hole washing
and group-holes washing. When the rock is relatively
complete and the crack is fewer, it can use single hole
washing.
Cont….
Group-holes washing
(a)Before washing (b)after washing
1- crack 2-filling 3-drill hole
Cont….
■ Cement grouting is the most common rock foundation
grouting. It should pay attention to the varieties of cement,
the fineness of cement particles, types and dosage of
admixture.
■ The varieties of cement for cement grouting should be
determined according to grouting purpose and environment
water erosion. In general, it can adopt ordinary Portland
cement or Portland cement for dam that the grade is not lower
than C45.
■ The fineness of cement particles has great influence on the
grouting effect. The more fine cement particles is, the better it
can be poured into microscopic cracks, and the more
completed the hydration of the cement can be.
Cont….
■ Adding some admixtures in cement slurry can adjust or
improve the performance of the cement slurry, meet the
projects‟ specific requirements for the cement slurry, and
improve the effect of grouting.
Grouting ways
(a)pure pressure grouting (b) circular-type grouting
1- water 2-slurry mining tank 3-grout pump 4-pressure gage
5-grout pipe 6-grout plug 7-return pipe
Cont….
Leakage in Tendaho Dam
This leakage is through the right abutment after the raining season
in 2010.
The leakage wasn‟t through the dam body.
Leakage water from right abutment has a temperature of 40oC,
and from left abutment 33oC; while the reservoir water is 31oC.
Proposed grouting profile for Tendaho
Dam
1.5 Causes of Failures of Earth Dams
■ Earth dam failures are mainly caused by improper
design, lack of thorough investigations, and inadequate
care in construction and poor maintenance.
■ The Causes of failure of earth dam may be divided into
three categories as follows:
1. Hydraulic failures
2. Seepage failures
3. Structural failures
Hydraulic failure
Internal
erosion and
piping
through
dam body
and
foundation
Cont….
1
For dams >30m=> B 1.65( H 1.5) 3
■ The height of the dam is the most important factor to be considered for
fixing width of the dam.
3. U/s and D/s slopes
■ The U/s and D/s slopes of the dam depends upon following factors
Type of soil used
Foundation condition
Height of the dam
Cont…..
Sand or sand and gravel with RCC core wall 2.5:1 2:1
Cont…..
The dimensions fixed by Strange for earth dam are as follow.
Height of dam Min. F.B (m) Min. Top width (m) U/s Slope D/s Slope
Up to 4.5m 1.2 to 1.5 1.85 2:1 1.5:1
Drainage layer
Filter layer-constructed of
material that is finer than that
of the drainage.
Lining Layer-protects
the slope against Protective layer- constructed
external mechanical of sand or coarser earth
effects. material.
Cont…..
Slope protection mechanism
1. Rock fill Protection
2. Concrete and reinforced concrete slabs.
3. Asphalt lining.
1. Rock fill Protection
o Is simple
o Very effective and
o Safe because it cannot be damaged during deformation of the dam’s
body.
o This type of lining consists of a layer of rock fill placed over one or
more filter layers.
o Thickness of the filter should not be less than 15 cm.
o Rock fill linings are used for a height of waves up to 2.5 m.
o compressive strength of 50 MPa,
o and have a unit weight of γ>24kN/m
Cont…..
Mathematical computation
o In order to be stable during wave action
Individual pieces of rock should have a certain minimum weight
For slope inclinations m=1–3,
where:- B- is the length of slab along the normal of the contact of water and
dam slope
ks- is the coefficient of safety, equal to 1.25 to 1.5
■ Prefabricated slabs as slope protection
– at a thickness of 8–20 cm
– with dimensions of 1.5×1.5m up to 5×5 m,
■ During placement, the slabs can be connected, into larger units (10×10m
up to 20×20 m)
– by concreting of the joints,
– So that prefabricated monolithic slabs are obtained
■ Monolithic slabs have a wider application
Cont…..
3. Asphalt lining
■ Asphalt protective linings find more and more expanding application
■ Owing to their suitable deformation characteristics,
■ Complete mechanization of the construction process,
■ Absence of joints, etc.
■ They are used for waves up to 3.0m high.
■ Thickness of asphalt layers ranges from 5–10 cm.
Cont…..
D/s Slope Protection
■ The downstream slope is mainly protected by
– Construction of berm
– Means of grassing, where a layer of topsoil 20–30 cm thick is put into
position across the surface.
– Sometimes protection is achieved with a layer of gravel (10 cm)
■ If berms are constructed the width b should not be less than 1.5 m,
Earth Fill Dam Design and Analysis
Chapter Two
Factors For Dam Selection
Topography
■ A narrow V-Shaped valley with sound rock in abutments=>A concrete
arch dam.
■ A relatively narrow valley with rock walls=>A rock fill or concrete
gravity dam.
■ A wide valley with deep overburden=> An earth dam.
■ Topography may also influence the selection of appurtenant structures eg.
Natural saddles may provide a spillway location.
Geology and Foundation Conditions
■ Competent rock foundations with relatively high shear strength and
resistant to erosion can be used for all types of dam.
■ Gravel foundations, if well compacted, are suitable for earth or rock fill
dams with provisions for adequate seepage control.
■ Silt or fine sand foundations can be used for low concrete (RCC) and
earth fill dams but are not suitable for rock fill dams.
Cont…
■ Non dispersive clay foundations may be used for earth dams but require flat
embankment slopes.
Materials available
■ If suitable soils for an earth fill dam can be found in nearby, an earth dam
may prove to be more economical.
■ The availability of suitable rock may favor a rock fill dam.
■ The availability of suitable sand and gravel for concrete at a reasonable cost
locally or onsite is favorable to use for a concrete (RCC) dam.
Spillway
■ The size, type and restrictions on location of spillway are often controlling
factors in the choice of the dam type.
■ When a large spillway is to be constructed, it may be desirable to combine
the spillway and dam into one structure, indicating a concrete overflow dam.
■ In some cases where required excavation from the spillway channel can be
utilized in the dam embankment, an earth or rock fill dam may be
advantageous.
Cont…
Climate
■ The construction difficulty during wet weather should be taken into
consideration.
Cont…
Economic
■ The final selection of the type of dam should be made only after carefully
analysis and comparison of possible alternatives, and after through
economic analyses that include costs of all appurtenant structures, power
and control structures, and foundation treatment.
Environmental
■ The need to consider protection of the environment affects the type of
dam, its dimensions, and location of the spillway and appurtenant
structures.
Cont…
Geotechnical Investigations
■ Two types of questions in dam projects
1. Engineering questions, which relate essentially to the design, construction and
operation of any structure of the type proposed, and
2. Geological questions, which arise from understanding of the site geological
environment and its likely influence on the design, construction and operation of
the project.
■ Most dam failures occurred due to failure to fully understand and define the right
geotechnical questions.
■ Checklist of Geotechnical questions for dam projects:
1. Source of Materials
■ Source of materials for the following purposes:
Earth fill, for the core or other zones;
Filters;
Rock fill;
Rip rap
Concrete aggregate;
Road pavements;
Cont…
■ For each material: Location of alternative sources, qualities/suitability,
quantities, methods for winning and processing, overburden and waste
materials and quantities, possible use of materials from required
excavations, e.g. spillway, outlet works and dam foundations.
2. Reservoir
Water tightness;
Effect on regional groundwater-levels or quality;
Stability of slopes inside and outside of reservoir rim;
Erodibility of soils-Possibility of turbidity problems;
Siltation rates and likely location of deposits.
3. Dam
Location- To suit topographic and geological situations;
Alternative sites, for comparison of costs and of geotechnical and other issues;
Type(s) of dam suited to site(s);
Depths to suitable foundations for concrete dam; earth fill; rock fill; core; filters;
plinth or grout cap;
Cont…
Nature of materials to be excavated, excavation methods, and possible uses of
materials;
Stability of excavations, support and dewatering requirements;
Permeability, compressibility and erodibility of foundations;
Foundations treatments required: grouting; drainage; slurry concrete; dental
treatment; filter blanket; other;
Embankment zones; methods of placement, and of control of quality, moisture
and compaction;
Stability of dam, and dam plus foundation in all situations;
Monitoring systems: types, siting.
4. Appurtenant Structures
Location and type;
Excavation methods, possible use for excavated materials;
Stability of excavations, need for temporary/permanent support;
Channel, need for lining/drainage;
Need for protection of the discharge area, or for excavation of a stilling basin.
Cont…
5. Seismicity of the Region
Design earthquake, annual exceedance probability versus ground motion;
Maximum credible earthquake.
■ Assuming that the flow is steady and incompressible, the quantity of water
entering the soil element is equal to the quantity of water leaving the soil
element:
∂Ψ/∂x = – vz
∂Ψ/∂z = vx
■ Therefore, the expression for flow rate per unit length, qT, can be obtained as:
𝑁𝑓
𝑞𝑇 = 𝐾. 𝐻. ( )
𝑁𝑑
The total flow rate, QT, is given by:
𝑄𝑇 = 𝑞 𝑇 . 𝐿
L-is the length perpendicular to the 2-D seepage plane.
Cont…
■ The nomenclature and formulas for drawing the line of seepage and exit
face and determining the quantity of seepage per unit length of
embankment, q.
Cont…
Phreatic line for dam without filter
■ From figure a a KF
Cont…
a
The various values of a a have been given by Cassagrande , as
shown below
α a
a a
30o 0.36
60o 0.32
90o 0.26
120o 0.18
135o 0.14
150o 0.10
180o 0.0
Cont…
Analytical Solution
For α< 300
■ Schaffernak and Van Iterson have derived an equation for determining the
value of “a” in terms of h, b and α.
■ The equation is derived on the assumption that the hydraulic gradient is
equal to the slope of the phreatic line.
dy
i tan
dx
dy
qK y
dx
y JJ ' a sin
dy
qK y K ( a sin )(tan )
dx
a (sin )(tan )dx ydy
Cont…
■ Integrating both sides between limits
x a (cos ) to xb
y a(sin ) to yh
b h
asin tan dx ydy
a cos a sin
h 2 a 2 sin 2
a sin tan (b a cos )
2
b b2 h2
a 2
cos cos sin
2
Cont…
When α lies between 30o & 60o
■ Cassagrande has suggested the use of sinα in place of tanα
h 2 a 2 sin 2
a sin ( S a)
2
2
h2
a 2aS
2
0
sin
2
or
h2
aS S 2
sin 2
S b2 h2
h2
a b h b h
2 2 2 2
sin 2
1
a b 2 h 2 b 2 h 2 2 1
sin
a b 2 h 2 b 2 h 2 cot 2
Cont…
Pavlovsky’s solution
Pavlovsky analyzed the embankment by dividing it into three zones.
o Pavlovsky assumed horizontal flow in each zone and wrote the basic equation
q = kiA for each zone.
o The equations for each zone are:
o Zone-I
qI K I
hw h1 ln hd (i)
cot d
h h1
Cont…
Zone-II
K h12 ao ho
2
qII (ii)
2b 2 hd ao ho cot
Zone-III
For ho>0
Kao ao ho (iii)
qIII 1 ln
cot ao
For ho=0
Kao
qIII
cot (iv)
2
b b
ao hd hd h1
2
(vi)
cot cot
0.002 ft *18.3 ft
0.0122 ft 3 / min per ft length of the dam
Kao min
q
cot 3
b b2 h2
a 2 73 ft
cos cos sin
2
q K (a sin )(tan )
0.002 * 73* (sin18o 26' ) * (tan18o 26' )
0.015 ft 3 / min per ft length of the dam
Cont…
o Graphical method
o This method was suggested by Cassagrande.
o CD will be equal to CA
o For parabola AP=QH (distance of point from focus is equal to distance from
directrix)
o But, AP x 2 y 2 QH
o If focal distance AH is taken as yo then
o QH = QA+AH = x+yo
x 2 y 2 x yo
x 2 y 2 x 2 2 xyo yo2
y 2 yo2
x
2 yo
Or y 2 2 xyo yo2
This is the equation of base parabola.
Cont…
The value of yo can be determined either graphically or analytically by
considering co-ordinates of point C as follows
yo x2 y 2 x
yo b2 h2 b
Cont…
■ Pore pressure: The hydrostatic head or pore water pressure at any point
can be expressed as
hw w
■ Seepage force:
– The seepage force per unit volume of the soil is
Fs i w
– Through foundation
Fs i w (1 n)( 1) w
– Through the body of dam
h
ie w w
l
■ Where: ie is the exit gradient and l is the average dimension of the last field
in the flow net
Measures to control seepage through the dam
■ To reducing seepage a core of impervious material (silty clay or clayey silt) generally
provided.
■ The type of core is selected depending on availability of materials, topography of the site,
foundation conditions, etc.
■ There are two types of core according to inclination of the axis of the core.
1. Vertical core, and
-Provides high pressure at the contact plane b/n the core &
foundation & It is more effective in reducing seepage.
2. Inclined core
Relief wells
Drainage of Earth Dams
■ Drainages are carried out in the body and foundation of earth fill dams to fulfill
– Acceptance and drainage of seepage water
– Reduction of the zone in which the seepage flow acts,
– Decline in the seepage line and, thus, elimination of the danger of freezing of
the earth material;
– Acceleration of the process of consolidation of clayey materials and reduction
of pore pressure
■ As a rule, drainages consist of an intake part and an offlet part.
■ The intake part usually consists of layers of
– sand,
– gravel, or
– a stone gritting material, set out according to the filter rules.
Combined drainages
o Represent a combination of the previously described drainage
constructions, which increases their efficiency.
Cont…
Combined drainages
o Represent a combination of the previously described drainage
constructions, which increases their efficiency.
Design of filters
o Filters are usually identified in terms of their particle size distribution
o Basic purpose of filters and drains
o To intercept water flowing through cracks or openings in a base soil
and block the movement of eroding soil particles into the filter.
o To intercept water flowing through the pores of the base soil,
allowing passage of the water while preventing movement of base
soil particles.
o Basically filter material consist of sand, gravel, or a sand and gravel
mixture placed in embankments, foundations, and backfill of hydraulic
structures.
o Basic filter design method employs the following important steps.
Step 1
o Plot the gradation curve (grain-size distribution) of the base soil material.
Step 2
o Proceed to step 4 if the base soil contains no gravel (material larger than
No. 4 sieve)
Cont…
Step 3
o Prepare adjusted gradation curves for base soils that have particles larger
than the No. 4 (4.75 mm) sieve.
o Obtain a correction factor by dividing 100 by the percent passing the
No. 4 (4.75 mm) sieve.
o Multiply the percentage passing each sieve size of the base soil
smaller than No. 4 (4.75 mm) sieve by the correction factor
determined above.
o Use the adjusted curve to determine the percentage passing the No.
200 (0.075 mm) sieve.
Cont…
Step 4
o Place the base soil in a category determined by the percent passing the No.
200 (0.075 mm) sieve.
Cont…
Step 5
o To satisfy filtration requirements, determine the maximum allowable D15
size for the filter in accordance with the following table.
Cont…
Step 6
o Determine the minimum allowable D15 in accordance with the following
table.
Cont…
Step 7
o The width of the allowable filter design band must be kept relatively
narrow to prevent the use of possibly gap-graded filters.
o First, calculate the ratio of the maximum D15 to the minimum D15
sizes determined in steps 5 and 6 If this ratio is greater than 5, adjust
the values
o Label the maximum D15 size as Control point 1 and the minimum
D15 size as Control point 2.
Step 8
o Both sides of the design filter band will have a coefficient of uniformity,
defined as:
D
CU 60 6
D10
Cont…
Step 9
o Determine the minimum D5 and maximum D100 sizes of the filter
according to the following table
o Label as Control points 5 and 6, respectively.
Cont…
Step 10
o To prevent segregation during construction Determine maximum D90 and
the minimum D10 from calculation and table
Step 11
o Connect all the control points
Cont…
Example
o Given: The most important function of the filter being designed is to act as
a filter.
2. Stability of Earth Dams
Stability of Slopes
o The side slopes of an earth dam should be safe against shear failure.
o The Swedish circle method is one of the various methods of stability
analysis of slopes.
o In this method, the potential failure surface is assumed to be cylindrical
(i.e. circular in cross section).
Re sistingMoment Re sistingForce
FS
ActuatingMoment ActuatingForce
N W cos ………………………………………………………...(1)
T W sin ………………………………………………………...(2)
o Resolving all the forces in the normal (or radial) direction,
N U B R cos ……………………………………………..………(3)
o Resolving all the forces in the tangential direction,
T C R sin …………………………………………...……..(4)
o Substituting the value of R from equation (3) into equation (4),
N UB
T C sin
Cos
o Forces are computed for all the slices above the assumed slip surface and the
corresponding actuating and resisting moments can be computed.
N U tan cL ……………………………………..(6)
FS
T
o For a purely cohesive soil (Φ= 0), the point A itself represents the center of
the most critical circle.
o The Swedish circle method is used for checking the stability of the earth dam
for the following critical conditions.
1. Stability of d/s slope during steady seepage condition
2. Stability of u/s slope during sudden drawdown condition
3. Stability of both slopes during construction.
Cont…
Stability of earth dam against headwater pressure (or overall stability)
o The overall sliding stability of the earth dam is determined considering it
as a solid body.
o The factor of safety against sliding is defined as the ratio of the force
resisting sliding of the dam to the force tending to cause sliding
PH
w h2
2
o Thus, the factor of safety is given by
W tan
FS
o wh2 not be less than 2.
2
Cont…
Stability of earth dam against horizontal shear (i.e. stability of d/s portion of the
earth dam)
Hd
SH2
2
tan 45
2 o
2
w h12
2
where:- γ1is the submerged unit weight of the soil below the phreatic line and γ2is
the moist unit weight of the soil above the phreatic line.
Cont…
o The resisting force against sliding is developed due to internal friction
and cohesion of the soil mass in the downstream portion of the dam, and
is given by
Rd Wd tan cbd
where:- Wd- Is the total effective weight of the d/s portion of the dam above
the base,
c -Is the unit cohesion and
bd -Is the width of the base of the d/s portion.
o The average factor of safety Fs against shear is given by
Wd tan cbd
FS
sH 2
2
2
tan 45 o
2
w h12
2 should be at least 2
Cont…
Factor of safety against maximum shear (d/s slope)
o According to the theory of elasticity, the maximum shear (ηmax) is twice the
average shear (ηa). Thus
Hd
max 2 a 2
bd
Or
max
S H 2 tan 2 45o 2 w h12
bd
■ The horizontal force acting on the upstream portion of the dam is given
by
H
SH2
u tan 45
2
2
o
w h12
2 2
■ If bu is the width of the base of the u/s portion of the dam, the average
shear stress at the base is given by
a
Hu 1 S H 2
bu
bu 2
tan 45
2 o
2
2
w h12
Cont…
■ The maximum shear stress is taken as twice the average shear stress.
Thus
max 2 a
■ A resisting force develops against the horizontal shear force, which is
given by
Ru Wu' tan cbu
where:- W´u-is the total effective weight of the u/s portion of the dam
above the base.
F
Smax
bu s' h tan c
'
where:- γm-is the mean unit weight of the soil mass of the dam and
foundation, which is weighted in proportion of the thickness of each.
D h1 h2 F h2
m
h1
Cont…
■ Ф1is the equivalent angle of internal friction of purely cohesionless soil,
given by
m h1 tan 1 m h1 tan c
m h1 tan c
tan 1
m h1
where:- Φ and c are, respectively, the angle of internal friction and cohesion
of the foundation soil.
■ The average shear stress is given by
m h12 h22 tan 2 45o 1 2
a
S
bu bu
where:- γ´m-is the mean submerged unit weight of soil mass of the dam and
the foundation, given by
D' h1 h2 F' h2
'
m
h1
2
1 S1 S2
FS should at least be 1.50
a
Cont…
■ The factor of safety against maximum shear is also necessary.
■ The shear strength at point D where the maximum shear stress occurs is
given by
Smax c m h tan
'
Where:- γ´m-is the mean effective unit weight of the soil mass along a
vertical line passing through point D, and is given by
D' h h2 F' h2
'
m
h
■ The factor of safety against maximum shear is given by
Smax
FS' should be greater than unity
max
Solution:
o The soil column above the slip surface is divided into7 slices. The slices
have been taken such that the base of each slice is in one type of material.
The entire soil mass has been assumed to be saturated. Actually, a small
portion above the phreatic line under steady seepage conditions will not
be saturated. The computations for the stability analysis are shown in the
table below. The weight of each slice is computed from its area and the
corresponding unit weight. The values of Φ and c are taken
corresponding to the material through which the base of that slice passes.
The value of the angle θ, which the vertical lines make with the normal,
are measured and written in Col. (7).
Cont…
2. For the dam shown in the figure below (height 100 ft), the maximum
headwater is at an elevation of 90ft above the base. The position of the
seepage line results in 65% of the cross section being saturated and
submerged. Determine the safety against headwater pressure (overall
stability)
Cont…
Solution:
■ From the given data, the average unit weight may be computed as:
65% of material submerged = 0.65 x 74.5 = 48.5 lb
35% of material moist = 0.35 x 122 = 42.6 lb
Average unit effective weight of cross-section = 91.1 lb/cu.ft
o The area of the cross-section=
o The effective weight of a section of the dam 1 ft wide will be
o Assuming that tan Φ of the material of which the dam is composed is 0.3 and
neglecting cohesion, the shear resistance is 1002.1 tons x 0.3 = 300.6 tons.
o The headwater pressure will be perpendicular to the upstream slope, but
horizontal component of this pressure will be
o Thus, the overall factor of safety against horizontal shear due to headwater
pressure
o ≥ 2.0 (Satisfactory)
Cont…
3. Refer to the following figure of a dam cross section of homogeneous
material consisting of a medium silt placed in 6-inch rolled layers.
Slopes are u/s and d/s, 3:1 and 2.5:1, respectively. The dam is founded on
a firm and relatively impervious foundation. Determine the safety against
downstream horizontal shear.
Cont…
o Solution:
o Assumptions:
Void ratio, material in dam, e = 0.43
or per cent voids (or porosity) = e/(1+e) = 0.30
Specific gravity = 2.65 Hence, dry unit weight = 62.5 x 2.65 x(1 – 0.30)
= 116 lb/cu. ft
Water contained in pores when saturated = 0.30 x 62.5 = 18.8 lb/cu.ft
Saturated unit weight = 116+18.8=134.8 lb/cu.ft
Submerged unit weight = 134.8 – 62.5 = 72.3 lb/cu.ft
Moist unit weight will be assumed as 120 lb/cu.ft
Angle of internal friction, Φ= 26°, unit cohesion, c = 0
Mean (weighted average) unit weight: Up to elevation 60 the material is
below seepage line and will have submerged unit weight of 72.3 lb/cu.ft
and above and beyond the seepage line unit weight will be taken as
moist or 120 lb/cu.ft
Cont…
o which is the total horizontal shear per foot of width tending to move the
downstream section of the dam downstream.
Next, determine the resisting forces downstream.
=2*(187.5/350)=1.07ton/sq.ft.
■ At the point of maximum shear the unit shear resistance will be
S=72.3*60*0.488+0=2120=1.060tons/sq.ft.
■ Factor of safety at the point of maximum shear=1.06/1.07=0.99 (Not
satisfactory)
Cont…
5. Refer to the following figure and find the Approximate shear stress in the
foundation and Approximate factor of safety against foundation shear.
Data:
Height of dam = 100 ft
h1= 160 ft, h2= 60 ft, b = 400 ft, γ= 120 lb/cu. ft, Φ= 17°, c = 400 lb/sq. ft = 0.20 tons/sq ft
Equivalent angle of internal friction, Φ1, is determined from
from which, Φ1= 18°.
Cont…
■ Equivalent liquid unit weight (Rankine‟s formula)
The maximum unit shear will be 1.4xSa= 1.4x0.875 = 1.23 tons/sq. ft.
Approximate factor of safety against foundation shear
■ Unit shear strength of foundation below toe = c + γ1h2tan Φ, where γ1is the effective
unit weight of the material.
■ Assuming that ground water level is at ground surface in this case, the submerged
unit weight
= 120 – 62.5 = 57.5 lb/cu. ft.
■ Unit shear strength below toe = 400 +(57.5x60xtan 17°) = 1455 lb = 0.73 tons/sq. ft.
Cont…
■ At point in foundation under upper shoulder of slope
■ Shear strength at this point = 400 + (96.5 x 160 x tan 17°) = 5140 lb = 2.57
tons /sq. ft
■ Average unit shear strength = (0.73 + 2.57)/2 = 1.65 tons/sq. ft
■ Overall average factor of safety against foundation shear = 1.65/0.875 = 1.9
(Satisfactory)
Factor of safety against shear in the foundation at the point of maximum shear:
■ The mean effective unit weight, γ1, will be (57.5 + 120)/2 = 88.8 lb/cu.ft.
– This is because at this point there is 60 ft below and 60 ft of material above the
ground water level.
■ Unit shear strength at the point of maximum shear = c + γ1h tan Φ= 400 +
(88.8x120x0.306) =3670 lb = 1.84 ton.
■ Factor of safety against shear at point of maximum shear = 1.84/1.23 = 1.5
which is satisfactory.
Rock Fill Dam Dams
Chapter Three
Rock Fill Dams
■ Dam that contains more than 50% of compacted or dumped previous fill.
■ Stability mainly developed by the fraction and interaction of the particles.
Rock fill dam sections
o Dam with inclined impervious zone
Cont…
o Dam with central core
Cont…
o Dam with upstream membrane
Cont…
Foundation Design
■ Foundation requirements
More severe than earth fill dam but less serve than concrete gravity dam.
Hard erosion resistant bed rock is most suitable.
Rock fill dams are not suitable in soft foundation of sand, silt and clay.
Foundation with river gravel + rock fragments is acceptable.
■ Foundation treatment must be sufficient to satisfy the following criteria:
Minimize leakage.
Prevent internal erosion.
Prevent settlement.
Sufficient friction development between abutments and foundation to
ensure sliding stability.
Cont…
Membrane Design
■ Seepage membrane is required to stop the seepage through the dam
embankment.
Central core
U/s membrane
■ Materials for the membrane
Reinforced cement concrete
Steel
Timber
Stone/rubble or masonry
Asphalt concrete for u/s face membrane and
Earth/clay
Cont…
Internal Membrane
■ Shorter grout curtain length because of straighter alignment.
■ Protection from the effects of weathering and external damage.
■ If the core is centrally located, any future remedial grouting can be
accomplished from the crest; this is also true for cores that slope only slightly
upstream.
■ More easily adapted to less favorable foundation conditions, especially if the
core is centrally located.
■ Typically would not require specialized construction that may be needed for
upstream membrane.
Cont…
Earth core
a. Impervious Central Core
■ Enough quantity of earth fill available for core.
■ Used when u/s abutments are widely apart in comparison to dam axis length.
■ Or show highly weathered rock to great depth and require adequate
grouting/cutoff.
■ Design same as for earth fill dam, seepage and stability analysis required.
■ Core material to have enough plasticity to allow it to deform without cracking on
dam deflection.
■ Filter zones provided (one or multiple zone of 8-15ft thick)
■ Foundations and abutments opposite to core be treated to prevent piping.
■ Bottom width 0.5 h to 2.5 h.
■ U/s and d/s slopes symmetrical (0.3H:1V 1.5H:1V), or u/s flatter than d/s face.
■ Dam slopes as x+1H:1V (minimum 2:1). x-core slope
Cont…
Cont…
Fig. Concrete face sealing. Junction of the concrete face sealing and the plinth
(perimetric joint)
A. Face slab; B. Perimetric joint; C. Plinth; 1. Hypalon band; 2. Mastic filler;
3. Compressible wood filler; 4. PVC water stop; 5. Copper water stop; 6.
Neoprene cylinder; 7. Styrofoam filler; 8. Sand asphalt mixture; 9. Zone 2; 10.
Steel reinforcement; 11. Steel reinforcement to protect concrete against
crushing and to protect water stop: (ICOLD, 1989a)
Cont…
Membrane Cutoffs
■ To prevent seepage beneath the dam, foundations are usually grouted.
■ Provides leakage control in the upper few meters of the foundation.
■ Facilitate grouting operation (as grout cap).
■ A minimum width and depth of 3ft is recommended for cutoff walls in sound
rock.
Cont…
2. Asphaltic Concrete
■ Provides more flexibility and tolerates larger settlement.
■ U/s slope 1.7:1 or flatter for easy placement.
■ Good bedding layer to eliminate uplift pressures and piping if cracks.
■ Penetration coat cover leveling layer to bind and stabilize it.
■ Membrane thickness 20 to 25cm. Asphalt 8.5% by weight of dry aggregates.
■ Standard road paver used and asphalt placed in 3 layers.
■ Seal coat on the finished surface (for water proofing and increased durability.
Cont…
.
Cont…
3. Steel Face
■ Used on few dams.
■ Performance satisfactory.
■ Can be rapidly constructed.
■ Can tolerate greater embankment reverts.
■ Proper maintenance can be made facing as permanent.
■ D/s slopes 1.3 to 1.7.
■ Probability of corrosion- Disadvantage.
Cont…
■ Steeper slopes construction difficulties:
Plate anchored to embankment by steel anchor rods grouted in bedding
material.
Plate raised on scaffolding, grid, bedding material placed after or during
plate construction.
Plate thickness ¼ to 2/8 inch.
Jointed by bolts or continuous fillet weld.
Expansion joint provided are regular interval.
Coping walls can be used to retard over splash.
Cont…
Rock Material
■ Hard, durable and able to withstand disintegration due to weathering.
■ Free unstable materials.
■ Resist excessive breakage due to quarrying, loading, hauling and placing
operations.
■ Individual rocks of uniform size for good rock-to-rock contact.
■ Igneous, sedimentary and metamorphic rocks all used successively.
■ Each dam site a unique problem, thus general guidelines only.
■ Rock quality determined by lab tests and/or in-situ inspections of weathering
marks at the rock quarry site.
■ Test embankment to answer:
Use of marginal materials
Performance of materials during compaction operation.
Correct compaction equipment
Correct lift for each material
Cont…
Rock Sources
■ Excavation for foundations, structures, spillway, stilling basin, tunnels,
underground power house etc.
■ Quarry site near dam site.
■ Angular rock fragments can be obtained from the river bed.
Rock Size
■ Use rock specific gravity2.67 to 2.94 and weight not less than
160lb/cft=2560kg/m3.
U/s, d/s face slopes and zoning
■ Slopes depend on type and location of membrane. Slopes evolved from steep 0.5:1
to flat 1.3 to 1.7:1.
■ Steep slopes used to minimize rock volume and cost.
■ Steep slopes possible with u/s face membrane.
■ For fast design the steep slopes were stabilized by thick crane-placed dry rubble
masonry (and which provide as support zone for the bedding layer for u/s
membrane. No derrick/crane placed rock work required for present design.
Cont…
■ Central sloping core 2:1 to 4:1 both u/s and d/s.
■ U/s face membrane
Concrete u/s 1.3 to 1.7:1, d/s 1.3 to 1.4:1
Asphalt concrete face 1.6 to 1.7:1
Steel u/s 1.3 to 1.4:1
Crest Width
■ Should be determined by the type of membrane used and by its use after
construction.
■ The crest should, however, be wide enough to accommodate construction of
u/s membrane.
■ A minimum width of 15 to 20 feet is recommended.
Freeboard
■ Freeboard requirements depend on maximum wind velocity, fetch length,
reservoir operation conditions, spillway capacity and weather coping walls are
used.
Embankment Dam Construction, Performance &
Remedial Measures
Chapter Four
General Considerations
■ Embankment dams are the most widespread kind of water retaining
structures.
■ They can be defined as dams constructed of natural material obtained
from borrow pits located in the vicinity of the dam site.
■ Material obtained from excavation of foundations and appurtenant
structures is also very often used.
■ Owing to the complexity of problems that have to be solved during their
design, construction, and service, embankment dams fall within the most
complex engineering structures.
Cont…
Water Pressure Within the dam, foundation, and Piezometer, Observation well
abutments.
Rate of Leakage Flow Within the galleries, toe of the Weir, flume, flow meter or
dam and any other location of calibrated container.
interest.
Quality of Leakage Any location of interest. Turbidity meter.
Earthquake Response Dam crest, toe of dam and Peak acceleration recorder,
abutments. Strong motion accelerometer,
Micro-seismic Station.
Cont…
THANKS FOR YOUR ATTENTION
2021