Professional Documents
Culture Documents
CHAPTER ONE
INTRODUCTION
1.1. General
Ethiopia is rich in water resource potential. Among these hydropower is prominent one.
The over all potential is estimated to be in the order of 15,000 - 30,000 MW. However,
only 1-2% of it has been utilized up to now. Study reveals that about 90% of the energy
consumed in the country is derived from biomass fuels. The use of biomass as the
source of energy has resulted in massive deforestation and subsequent soil erosion. In
addition to these diesel engines generate about 10% the electric energy consumed in the
entire country thus it has significant impact on the foreign exchange of the country.
The existing situation indicates that the supply and demand of power is not balanced.
Not only is the demand being unbalanced with the supply but also the rate of demand
much greater than that of the supply.
Due to power supply shortage and other reasons out lined above, currently the
government of Ethiopia whishes to maximize the use of hydro resources for power
generation.
To that end, the objective in this particular project deals with the assessment of
available alternative water resource potential in the Gilgel Gibe river, down stream of
Gilgel Gibe I and to verify weather the potential projects appear technically,
economically and environmentally feasible or not.
Gilgel Gibe River is one of the major tributaries of Great Gibe river, which originates in
mountainous area south – west of Jimma and flows towards the north until it joins Great
Gibe River.
The river regulated by the upstream dam (which is currently in operation) hear after
called Gilgel Gibe I could be utilized further downstream with out constructing
substantial structure. Billie diversion weir which is located approximately at
07055’00”N, 37023’22’’E, some 19km downstream of the upper dam (Gilgel Gibe І)
and it is intended to divert the river water through a 6.1 km power tunnel that will
transfer the water to the power house located on the left of the river at approximate
geographic location 07 058’39”N and 37024’30”E. This site has a total catchments area
of about 4400km2 and mean annual inflow of 1667Mm3.
1.2.2. Geology and Topography
Ethiopia is located in the northern corner of Africa plate, on the southwestern margin of
the Red sea, close to the present location of the triple junction between the Red sea, the
Gulf of Aden and the Ethiopian rift.
The Precambrian (basement) rocks up on which all the younger formation is deposited
contain the oldest rock in the country having age’s grater than 600 million years. The
Gilgel Gibe project area is located in the southwest plateau very near to the main
Ethiopian Rift (MER), and the geology of the project area comprised rocks, which
range in ages from Precambrian to Quaternary dominantly Plioene age volcanic.
The most likely occurred rock types in the project area are mainly lower basalt,
rhyolites, ignimites and upper basalt etc. The lower basalt is the oldest rock in the site,
which is described as dark grayish to black, very strong, with two joint sets vertical and
dipping west or southern west. The acidic flow represents the top part of the areas
geology and mostly affected by instability problems. The flood basalt, which is one
form of the lower basalt, is the oldest, thickest and most widespread rock type of the
project area. And also, a series of most acidic volcanic rocks overlie the flood basalts.
The master plan report as well as field observation have revealed that this rock is the
hardest and the most resistant to weathering than other volcanic rock.
Generally, the river channel at the proposed diversion weir site is concentrated by very
big blocks, boulders and cobbles trace sand and gravel deposits, which are alluvial as
well as colluvial origin. From close inspection of the site, the bedrock, which is very
sound one, are estimated to be round at a shallow depth below the river channel.
The topography of the area can be grouped in to different geomorphic units based on
morphology. Major geomorphic geneses in the area are concave hill, higher chain of
undulating hills, plateau, long very steep slope and valley bottom. In general, many
rounds to conical hills that rise above the surrounding region and having a very steep
slope characterize the project area.
As a result, it is necessary to extend the data at a station Assendabo using runoff- rain
correlation. Since rainfall records of longer duration than the run off data available at
station Assendabo, the regression equation can be used to generate synthetic runoff data
by using the available rainfall data.
CHAPTER TWO
HYDROLOGIC DATA ANALYSIS
2.1 General
The development of power from stream flow depends on the volume of flow and on the
differential head that could be available for power production. Hydrological date is
needed in the design of hydraulic structure to deduce from its analysis, significant figure
such as the minimum, mean and maximum discharge of the River at the proposed
location of the structure.
Hydrology finds its greatest application the design and operation of water resource
engineering projects such as irrigation, hydropower and flood control projects.
Hydrological studies involve the collection of relevant data and analysis of the data by
applying the principles and theory of hydrology to seek solution to practical problems.
Stream flow records are the major data required in planning and operation of
hydraulic structure.
Gilgel Gibe River is equipped with two gauging stations: one on the main river
near Ascendabo and the other on the river Bidru Awano, some 3km from
Sekouru. Besides a station on the Gilgel Gibe River near the town of Deneba for
which stream flow records has been obtained. This station was in operation only
during the period 1980 to 1994. However, it delivers useful information on the
correlation of flow with that measured at the upstream site near Assendabo.
The original given data for analysis consists of 28 year average monthly runoff with
some missing data and monthly precipitation (mm) at station Assendabo and 14 years
It is often necessary to estimate these missing records. The missing data can be
estimated by using the data of the neighboring station. There are different methods of
filling missing data such as arithmetic average method, normal ratio method or other
approximation methods. However, all the above methods require more than one near by
station and concurrent records. These problems force to adopt simple correlation
between runoff and rainfall value for the determination of this missing data.
For this particular project a better way is to fit a linear regression line between rainfall
and runoff. If the correlation coefficients is in the range 0.6 < r<1.0 indicates good
correlation (Ray k. Linsley.JR)
The equation for linear regression between runoff and rainfall is:
Y =aX+b
And the values of the coefficient and b are given by:
a=
b=
r=
Using the above procedure it is found that the regression coefficient between mean
annual runoff and rainfall at station Ascendabo is greater than 0.6. Hence the correlation
between runoff and rainfall is used to fill the missing data.
For a number of reasons mentioned above the published flow may not represent the data
actually required by the analysis. In this case, an adjustment of the record is possible by
the use of the double- mass curve method. A more effective procedure is to develop a
relation between precipitation (rainfall) and runoff and make a double mass curve of
observed stream flow verses runoff. (RAY.K.LINSLEY.TR)
As shown in the curve below, the record at Ascendaba does not show inconsistency thus
does not require any adjustment.
1000
Stream flow (Mm 3)
800
600
400
200
0
0 200 400 600 800 1000 1200
Runoff(Mm 3)
Thus the correlation between X and Y may be exploit to extend the length of the Y
records, by estimating a set of N-n flows for the period during which there was an X
records but no Y records. The obvious approach to this problem is to use regression to
estimate Y as the function of X. However, it is not particular values of Y i that is
important, but rather the full collection of estimates of Y, which means a set of Y values
those posses the correct statical properties of Y.
A better approach to this problem is a class of methods known as maintenance of
variance extension (MOVE). The simplest version MOVE 1, presents the variance and
mean of Y using the equation:
Yi =A+BXi
Where B =
A=
Sxx=
Syy =
For this particular project, the flow recorded at station Deneba has been observed only
15 years, but flow records at station Assendabo has been observed for 32 years. Thus
the method of MOVE-1 technique is employed to extend the 15 years recorded data at
station Deneba to 32 years of flow record using station Assendabo.
.
The following table shows the monthly coefficient for the extended data and the
extended data is given in the appendix.
Month JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Ymea
n 6.3 5.0 6.1 10.4 20.0 63.0 143.0 211.9 172.4 70.3 19.0 10.1
Xmea
n 6.9 5.9 11.0 15.8 21.1 47.0 77.5 106.8 81.7 52.5 22.7 8.4
901. 842. 5355. 11516. 7360. 10539. 18307. 55036. 49582. 41160. 14669. 1010.
Sxx 4 2 1 4 7 6 1 0 1 3 4 6
163. 5956. 22845. 62820. 72760. 63697. 30105.
Syy 4 53.7 235.6 1317.8 7 4 8 5 2 3 1442.2 388.2
B 0.3 0.2 0.2 0.3 0.7 1.1 1.4 0.9 0.9 0.7 0.2 0.5
A 4.0 3.9 4.3 6.3 5.2 9.3 31.7 116.8 100.6 35.5 13.5 6.1
In such cases, transferring of required information (runoff data) from gauged sites to
ungauged site becomes very essential. For our particular project there is no any
recorded data at the weir site, thus it is a must to generate the required run off data from
station Deneba which is assumed the representative for our weir site.
For Gilgel Gibe-II project, the flow at weir site is the inflow from an area of
considerable extent where there is no stream gauge records plus in flow from the
operation of Gilgel Gibe reservoir. The monthly mean precipitation from station Sekoru
some 2km far from Bilile diversion weir site and the runoff record from a near by
stream gauging station (Deneba) on unregulated stream that represented the sequential
variation of runoff from drainage area are taken for analysis.
For the estimation of annual runoff from annual precipitation, the coefficient of runoff
assumed to be 0.65 considering catchments characteristics such as hilly, steep, land use
management and annual rainfall greater than 110 mm (RAY. K. LINSLEY).
=K A
Where = average annual runoff volume per year from
ungauged drainage area
= averaging annual precipitation, m
A = area of the contributing drainage, m2
K = annual runoff coefficients
Once the sequential flows have been computed it is a simple procedure to add,
sequentially, the flow from the engaged tributary area to the regulated flow. The
sequential inflow from the ungauged catchments area can be calculated following a
step- by- step procedure as follows.
Each month flow fraction for representative gauge and the computed flow at the weir
site is given on the appendix .
There are two different methods for constructing flow duration curve; namely the total
year method and the calendar year method. In total year method, the entire available
record is used for drawing the flow duration curve. All the data are tabulated in
descending order starting from the wettest month on the entire period and ending with
the driest month of the period for which the flow record is available.
In calendar year method, each year average monthly flow values are arranged in
descending order. Then the average flow values corresponding to the wettest month, the
second wettest month and so on up to the driest month are found out by taking
arithmetic mean of all values of same rank. These average values are then used for
plotting flow duration curve.
Thus from the above mentioned advantages, the total year method gives more correct
results than the calendar year method. Therefore, the total year method is used to plot
the flow duration curve for this particular project.
It may be noted that all methods of determining plotting positions give practically the
same results in the middle of the distribution but produce different results near the tail
of distribution.
A comparative study among different empirical formulae revealed that, on the basis of
theoretical sampling from extreme values and normal distribution the Weibull formula (
m/n+1) provided the estimate that are consistent with the experience.
Where Pi = *100 %
Pi = plotting position
m = rank
n = length of records
Since total year method incorporates all the data in the record it gives more correct
results than the calendar year method. Therefore, the total year method is used to plot
the flow duration curve for this particular project. The coordinates of the flow duration
curve are given on appendix.
The ordinates of the flow duration curves at selected frequencies are given in table
below:
300
250
200
Flow (m3/s)
150
100
50
0
0 10 20 30 40 50 60 70 80 90 100
% of time exceedence
Frequency analysis is the hydrologic term used to describe the probability of occurrence
of a particular hydrologic event. Since stream flow data is historical (not experimental)
that is it can not be generated, frequency analysis is used to determine the occurrence of
flood. Water resource system must be planned for future events for which no exact time
of occurrence can be forecast.
It is important to realize that these extensions are only a valid as the data used. The
hundred year flood may occur next year or not for two hundred years or may be
exceeded several times in the next hundred years. Generally the accuracy of estimation
of hundred year flood depends on the length of the record the data is available and flood
flows.
Therefore, frequency analysis can be of great value in the interpretation and assessment
of events such as flood flows and the risks of their occurrence in specific time period.
suggested on the basis of their ability to fit the plotted data. Decisions for the selection
of probability distribution are made largely on empirical evidence.
L – MOMENT
L- moments are linear combinations of the ranked observations, and thus do not involve
squaring or cubing the observations as do the product moment estimators. As a result L-
moment estimators of the dimension less coefficients of variation and skew ness are
almost unbiased and have very nearly a normal distribution. In a wide range of
hydrologic applications, generally, L- moment provides simple and reasonable efficient
estimators of the characteristics of hydrologic data and distribution’s parameters.
Table 2.3 probability weighted moment and L- moment
probability weighted moment L moment
0
201.0 128.05 95.31 76.34 201.0 55.13 4.55 3.09
The figure below shows the relation between and and the location of our
sample on the weir site.
1.4000
1.2000
1.0000
0.8000
0.6000
0.4000
0.2000
0.0000
0 0.2 0.4 0.6 0.8 1 1.2
XT= +
K= - 0.14173
= 181.2
=80.8
= 0.1
= 0.06
Selecting higher return period means the corresponding flood magnitude will be high.
Such a very high flood may never occur during the life time of the structure. On the
other hand, if a very low discharge corresponding to lower return period is chosen for
the design and if it is exceeded it will result in the failure of the structure causing more
damage than would have been caused in the absence of the structure.
Subramanian (1989) and Novak (1972) gave the general guideline for selecting the
return period as shown below.
S.no Structure Recommended design flood
1 Spillway for major & medium projects with T = 1000 years
storage more than 60mm3
2 Permanent barrage and minor dams with T = 100 years
The design flood may be one of the following types depending up on the importance of
the protection design.
1. Maximum probable flood (MPF)
2. Standard project flood (SPF)
3. A flood corresponding to a certain design frequency
Maximum probable flood (MPF)
MPF is the flood that may be expected from the most sever combination of
meteorological and hydrological conditions that is reasonable possible in the region.
The MPF is used in situation where the failure of the structure would result in loss of
life and catastrophic damage and as such complete security from potential flood sought.
The design flood is sometime taken as flood corresponding to certain desired frequency
of occurrence depending up on economic factors and other practical consideration.
XT =
XT = 181.2 +
XT = 706.4m3/s
Risk ( ) the probability of occurrence of an event (X≥XT) at least once over a period
of n years, where n is the useful life of the structure.
Reliability (Re) is the probability of non occurrence of the event (X≤XT) in n years.
= 1- (1- P)n
= 1- (1- )n
Re = 1-
Re = (1- )
Where R = risk
Re = reliability
P = probability of event (X≥XT) = 1/T
T = return period
n = life of the structure
Since the use full life of 50 years and a return period of 100 years are considered
= 1-
= 39.5%
Re = 1-
= 1-0.395
= 0.605
Re = 60.5%
Thus the possible risk of floods damage by flood magnitude exceeding the 100 year
frequency in the assumed 100 year life of the weir is about 39.5 % with a reliability
confidence of 60.5 % .This weir may fail if the flood magnitude greater than the design
flood occurs within the life timed of the weir.
CHAPTER THREE
DIVERSION WEIR
3.1 General
A diversion weir is a structure constructed across a river for the purpose of rising water
level in the river so that , it can be diverted into off taking tunnel. Diversion weir is
generally constructed on Perennials Rivers that have adequate flow throughout the year
and therefore there is no necessity of crating a storage reservoir.
A diversion weir must differentiate from a storage work or a dam. A dam constructed
on the river for the purpose of creating a large storage reservoir. The storage works are
required for the storage of water on a non- perennials river or on a river with inadequate
flow throughout the year. On the other hand, in diversion works, there is very little
storage (poundage) if any.
A diversion weir serves the following function.
It raises the water level on its upstream side.
affect the selection. Also it is better to have foundation with high bearing capacity,
resisting to erosion, and resistance to percolation.
For the selected weir site at the location approximately 07 055’00’’N and 37023’22’’E
some 19Km downstream of GG-I, we have narrow and straight reach, stable river
banks, the weir aligned at right angle so that it has minimum length and sufficient
discharge capacity and good foundation condition. Hence, the site selected for
construction of weir is feasible.
In this particular project the height of the diversion weirs fixed in such away that the
maximum water level ,including the surcharged head, should be less than the minimum
tail water level of the upstream power plant (Gilgel Gibe I power house ),i.e. less than
1431.1 m a.s.l. The surcharge (the water head above crest) is 3:0m. Therefore, the crest
level of the diversion weir fixed at elevation 1428m a.s.l. Hence, the height of the
diversion weir is 15m.
Length of the weir depends on the physical features of the given site.
A weir with long crest gives a small discharge per unit length and hence the
required energy dissipation per meter of the crest is smaller than what is needed
for a short crest length.
Constructing a weir longer than the river width causes formation of islands at
upstream side of the weir. As a result, the tunnels inlet can be cut off from the
river flow. The formation of the islands upstream of the weir reduces the
effective length of the crust.
From the flow master program the value of crest length for the corresponding elevation
of 1428m.a.m.s.l is about 56.16 m. However, the cross section of the river at the weir
axis shows the slope of the left abutment is unstable. This unstable section has to be
removed by excavation in order to maintain a stable slope, as a result the crest length
increased from 56.16 to 74m.
D = Vertical * slope
= 9.266 * 0.7 = 6.4862m.
For the bucket
Sin = E/R
E = R sin where =60 and R = H/4
E = 15/4 *sin 60 = 3.247m
Total bottom width of the weir is:
BTotal = B+C+D+E
BTotal = 0.846+5+6.4862 +3.247
BTotal =15.5792m ≈ 15.6m
3.4 Spillway
3.4.1 General
Spillway is a structure constructed on the weir to dispose of surplus waters from the
reservoir in to the down stream river reach. Spillways are providing for all hydraulic
structures as a safety measure against over topping and the consequent damages and
failure. A spillway acts as a safety valve for the structure, because as soon as the water
level in the reservoir rise above a predetermined level, excess water is discharge safely
into the down stream river reach, and thus the dam is prevent from failure.
II. It must be hydro dynamically and structurally safe and must not give
way under worst and variable loading conditions.
III. Its surface should be erosion resistant
IV. It must be located that the spillway discharge does not erode or
undermine the down stream toe of the dam.
V. It provided with some arrangements for effective disposal of the
energy of the falling water.
The shape of the crest of Ogee spillway generally made to conform closely to the
profile of the lower surface of nappe where the head over the highest point of nappe is
equal to the design head. At the design head, the water flowing over the crest of the
spillway always remains inconstant with the surface of the spillway as it glides over it.
For this shape, no negative pressure will develop on the spillway surface at the design
head.
However, when the head is greater than the design head the overflowing water tend to
break contact with the spillway surface and separation zone is formed. In this case a
negative or suction pressure occurs. On the other hand, if the head is less than the
design head, the water flowing over the crest of the spillway remains in contact with the
surface of spillway and positive hydrostatic pressure is exerted by the flowing water.
This is because the nappe tends to be depressed and crates a back water effect.
3.4.4 Cavitation
Cavitation is the formation and subsequent collapse of cavities in a region of liquid
where the pressure has reduced to that of vapor pressure of the liquid. When the cavities
collapse near a fluid way surface extremely high local pressure and stress in the
waterway surface result and cause pitting and erosion of the surface. It is an important
factor which must be considered in the design of high velocity outlet works where the
water way alignment and every surface of discontinuity are potential source of
producing cavitations and cavitations damage. In spillway designs, we certainly should
be very worry of cavitations problems at velocity exceeding 35 m/s, even if the spillway
surface is smooth and well constructed.
However, in this particular project the maximum velocity of water over spillway
surfaces is 18.4m/s, so there is no need of providing artificial aeration to reduce the
pressure causing cavitations problem.
DESIGN PROCEDURE
The discharge passing over the Ogee spillway is given by:
Q = C*Le*He 3/2
Where:Q = discharge
Le = effective length of the spillway crest.
C = coefficient of discharge
He = total head over the crest including the velocity head.
Coefficient of discharge may be taken as 2.2 and L ≈ Le = clear water way
Le= 6* 10
=60m then
Q = C. Le. He 3/2
706 = 2.2*60. He 3/2
He3/2 = 706/2.2*60 =4.457
He = 3.058 m say 3.0m
Correction Coefficients of Discharge
Correction due to height of weir
Since H/Hd > 1.33, the velocities of approach have a negligible effect up on ht
discharge, and as such, Hd becomes equal to He, i.e.
He /He ≈ 1.0
In such a case the coefficient of discharge,
C = Cd has been found to be 2.2
Correction due to upstream slope
Up stream slope correction factor is required when the up stream face is sloping at some
angle. However, for our case we provide up stem vertical face, hence no need to
upstream sloping correction.
Va =
Va = 0.5447m/s
Ha = va2/2g = 0.5442/2*981
Ha= 0.015m
For this particular project, an overflow ogee spillway having a vertical upstream face is
selected. Thus, the down stream crests profile given by the equation.
X 1.85 = 2* Hd0.85 *Y
Where, K = 2.0 and n = 1.85 (from the above table)
Before determining the various coordinates of the downstream profile, the point at
which the parabolic curvature ends should be determined. This curved profile of the
crest section is continued till it meets tangentially the straight sloping surface of the
downstream face of the over flow weir. The slope of the downstream face of the over
flow weir usually varies in the range of 0.6:1 to 0.8:1
Y= , Where Hd = 3.0m
Y= =
X = 5.00 m.
The parabolic curvature is ended at x= 5.00m from the apex of the crest. The
coordinate from
x = 0 to x = 5.00 are solved as follows.
2.50 1.0705
3.00 1.5000
3.50 1.9950
4.00 2.5540
4.50 3.1759
5.00 3.859
At the end of straight sloping surface, a curved circular surface, called bucket provided.
This circular curved is drawn with a radius equal to H/4 = 15/4 = 3.75m at an angle of
600 from the vertical.
In general, the kinetic energy of this super critical flow can dissipate in two ways.
i. Converting supercritical flow into sub critical flow by hydraulic jump.
ii. Directing the flow of water in to air and then make falls away from the toe of
the structure. The energy dissipated by the aeration of jet and impact of
water on the riverbed. However, some scour will take place, but it is too far
away from the weir to endanger it.
Hydraulic jump
Hydraulic jump is a sudden and turbulent rise of water, which occurs where changes
from supper critical flow state to the sub critical flow state and it is very effective means
of energy dissipation.
Case –I
It represents a case in which the tail water (y3) is equal to the sequent depth (y2). In this
case the jump occurs at the toe of spill way at all discharges. For scouring protection
purposes, a simple concrete apron is generally sufficient to provide in the region of
hydraulic jump. In practices this conditions might not be fulfilled since a little
difference. Between the actual and assumed values of the hydraulic properties of
structure and the river and assumed values of the hydraulic properties of structure and
the river will cause the jump to move from its calculated position. Consequently some
factor of safety should be considered to control the position of the jump.
Case- II
In this case the tail water depth (Y3) is lower than depth (Y2) for all discharges. Such a
condition occurs when the tail water is carried away quickly due to a rapid or a fall
some where on the down stream of the spillway. In this case, the jump will be located at
a point in the down stream of the toe of the spillway. This problem can be solved by:
I. Provision of a sloping apron below the river bed.
II. Construction of a low secondary weir
III. Provision of ski jump bucket.
Case- III
In this case the tail water depth (Y3) is grater than sequent depth (Y2) for all discharges.
Theirs condition usually occurs when the river cross section on the down stream of the
spillway is narrow and therefore the tail water back up.
The hydraulic jump in this case is located up stream of the toe on the spillway face and
it might be drowned /submerged.
This problem can be solved by:
I. By constructing a sloping apron above the river bed.
II. By providing a roller bucket type of energy dissipater.
Determination of sequent depth (Y2)
For Q =706 m3/s
Le = 60.00m
H = 15.0m
Hd = 3.0m
q = Q/L = 706/60 = 11.767 m3/s/m
Y2 = - +
Y2 = -0.637 +
Y2 = 6.34m
To determine the tail water depth, the rating curve at the location of the weir needs to be
known. The curve is usually constructed from the river stage and discharge
measurement records. But this data is not available at the location of the weir; therefore
a theoretical rating curve should be constructed. The following steps can be taken to
draw a tail water rating curve for the design purpose.
From the tail water rating curve give for Q = 706 m 3/s the corresponding value of tail
water depth Y3 is equal to 6.3m. Hence y2≈ y3 therefore, case I is to be considered for
the selection of energy dissipater i.e. provision of apron.
Design Procedure
1. Determine the pre and post hydraulic jump of water depth.
Apron Thickness
Apron of concrete blocks are placed immediately down stream of the weir. Its thickness
may be designed by using Bligh’s creep theory for pervious foundation and by
considering dynamic condition. Also the thickness of apron is recommended by various
investigators, Spring recommended a thickness of about 0.9m, Gales recommended a
thickness varying from 1.35m to1.2m for discharge from 7000 to 70000m 3/s (R.S.
Varshney), and for concrete block apron 3ft to 4ft (0.91 to 1.219m) depth are
recommended (Hand book of applied hydraulics).For this particular project average of
1.0m thick down stream apron is provided.
3.7 Cutoff
Concrete cutoff may be used under aprons or under the over flow sections. They
constructed by the trenching with a machine. A concrete cutoff is probably the best type
of wall for preventing under seepage. For this particular project since there is good
foundation and no problem of seepage, small reinforced cut off (groove) with 1m depth
and 0.5 m width is provided for the structural stability (sliding resistance) of the weir.
V2=q/Y2=11.76/6.347=1.85m/s
Vm=18.4+1.85 =10.12m/s
2
Dm=0.637+6.347 =3.492
2
Freeboard=0.61+.04*Vm*dm1/3
=0.61+.04*10.12*3.492 1/3
=1.22m
=0.637+10.12 2/2*9.81+1.22
Hd = 3.0 m
H2 = H+Hd Where, H = height of the weir
Ha =va2/2g, Va = 0.467 m/s
Ha = 0.4672/2*9.81 = 0.0111m
The total force PH acts at a height of Z above the bed given by:
Z = 1/3 [H2-H1] [H2+2Hd+3Ha / [H2+H1] +2
Z = 1/3 [18-3] [18+2*3/18+3]
Z = 5.7143 m
Up Lift Pressure
Water enters in to the body of the weir through the pores, cracks and fissures within the
body of the weir, at interface between the weir and within the foundation. Because the
water is under pressure it creates up lift pressure on the body of the weir .The pressure
acts in all directions but the pressure acting up ward is important for the design of weir,
as it reduce the effective weight of the weir. The magnitude of the up lift pressure
depends up on the character of foundation used in construction, grout curtains, the drain
and the method used in construction. A force due to up lift pressure requires the
determination of the area on which it acts and intensity of up lift pressure at various
points.
I. Area Factor
The up lift pressure generally does not occur on the entire horizontal area because, in
some portions there are no pores in which water can enter. The function of the total area
on which the up lift pressure acts is the area factor. A latest investigation shows that the
area factor for concrete and impervious foundation is unity.
U=
Where,
B = the base width of the weir =15.6m
H = the depth of water on the u/s side =15m
H’= the depth of water on the D/s side = 0.637m
U=
= 9.81 ( ) * (1*15.6)
= 1196.5119KN
And it acts through the centroid of the trapezoid 1-2-3-5
For convenience, the up lift pressure diagram is divided in at a rectangle 1-2-3-4 and
triangle 1-4-5. Thus the up lift becomes;
U = U1+U2 =
e=
X=
Where,
M = sum of all moments about the toe
VF = sum of all vertical force
X = distance of resultant of the force
B = width of the weir base
M = 11104.31kN-m
VT =3182.4 KN – 1196.5119KN = 1985.888KN.
X= = 5.59m
e=
= 2.6m
The factor of safety against over turning (F.S) is defined as the ratio of the sum of the
stabilizing moment (resisting moment) to that of the over turning moment about the toe.
Usually a safety factor of a bout 1.5 to 2 is applied.
F.s =
F.s =
Before starting the construction of the weir the rock surface is suitably dressed. It
consists of removing the entire loose rock and overburden up to the some bed rock
should be carried out can equally so as not damage the bed rock.
The choice of the method depends up on the practicality of the method for a particular
job. The method of grouting in large measure depends up on the treatment to be given
to the foundation material. This in turn will depend on the geological features. For
diversion weirs a grouting of small depth i.e. consolidation grouting is recommend.
Prior to the commencement of grouting of wholes, all the holes washed with alternate
use of water and air to remove all loose materials and drill cutting etc. The holes are
then tested with water under pressure to check the water tightness of the rock or to
locate seams or other openings in the rock, which are to be plugged.
The consistency of the grout required depends up on the water tightness of the rock. The
ratio of cement to water in the grout is suitably adjusted. Usually the ratio varies
between 1: 3 to 1:8. The holes are generally grouted using a low pressure of 300 to 400
KN/m2 (3 to 4 kg t / cm2).
The required depth of the deepest holes depends upon the nature of the rock in the
foundation. The accurate assessment of depth can be made by water testing of holes
drilled up at various depths to determine the extents of leakage.
U.S.B.R. has suggested the following criteria.
d = 0.33 h + C
Where: d = depth of the hole in m
h = height of the weir in m
C = constant varies from 7.5 to 25
Therefore, for this particular project the required average depth of hole for grouting is:
d = 0.33*15 + 10
d = 15m
CHAPTER FOUR
DIVERSION DURING CONSTRUCTION
4.1 General
Construction of a weir in a river channel requires that the site should be dry during
construction. So diversion of stream flow around or through the weir site during
construction period is essential.
Diversion Requirements
The selection of the most appropriate scheme for handling the flow of the stream during
construction is important to the secure economy in the cost of the weir. The required
area for weir should satisfy the following criteria.
Usually, it is not economically feasible to plan on diverting the largest flood that has
occurred or may be expected to occur at the site, and consequently some lesser
requirement must be decided up on. This, therefore, brings up the question as to how
much risk is involved in the diversion scheme under consideration.
For Gilgel Gibe II project, the diversion flood is designed for 15% acceptable risk and
the construction period for the weir is 4 years. Thus the return period for this risk is
computed as ;
R =1-(1-P)n =1-(1-1/T)n
0.15 =1-(1-1/T)4
T = 25 years
Therefore, the diversion work is designed for the return period of 25 year and
acceptable risk of 15%.
During filling the compactor will increase the water tightness of the materials. However
to provide better water tightness the upstream face has to be provided with clay. To
prevent erosion the down stream slope is provided with larger materials. The design
considerations of which closely follow those for permanent small dams of the same
type.
Thus the diversion tunnel should be capable of carrying a discharge selected by the
frequency analysis for a reasonable risk in view of the hazard involved. The 25 year
return period flood is calculated as follows.
Q25 =
Where , = 80.8
=181.2
K= - 0.14173
Q25 = 520.82m3/s
But for diverting the design flow through a tunnel requires 10.6m diameter. The height
of the coffer dam required to divert the water through this diameter tunnel not much less
than the actual structure. Hence the best way to divert the water is using concrete
culvert through the bottom of the diversion weir. Two 3.5 height by 4.5 wide
rectangular 120m long concrete culverts are used to pass the 25 year return period flood
which is 580.2m3/s.
In calculation the flow within the culvers, energy conservation is assumed between the
section immediately upstream of the culvert intake and the culvert out let section.
The energy conservation equation can be written as follows:
For our particular project, the manning coefficient of 0.0125 for the concrete, ke = 0.5
and kv = 1.1 is assumed. For the assumed maximum flood, v =8.4 m/s
During the plant operation or after the completion of dam construction, one of the
culvert which is equipped with sliding gate performs the function of under sluice in
order to flush the sediment, where as the other will be close with concrete stop log at the
end of construction.
CHAPTER FIVE
CONVEYANCE STRUCTURE
5.1 Intake Structure
5.1.1General
An intake is a structure constructed at the entrance of a power canal or tunnel or pipe
through which the flow is diverted from the source such as a river or reservoir. It is an
In order to attain the required discharge capacity the intake must be placed sufficiently
below reservoir operating level and high enough to prevent entry of sediment.
For circular tunnel the bell mouth shape can be achieved by an equation given by
Douma.
The bell mouth has an elliptical shape with an equation;
According to Mosony’s formula, velocity which eliminates eddies and vortex is taken
for this particular project
V=0.075
=1428m-1420m
=8m
V=0.075*
=0.94m/s
III. Bar Thickness
Thickness of bar should be between 0.65 cm and 2.5 cm. A bar thickness of 1.2 cm is
used for this particular project.
According to J.B. Gardon, for the condition of no vortex at inlets the necessary
submergence depth will be given by;
Ys> 0.725*V*
The minimum required depth of the intake for no formation of vortex is 3m, but for this
particular project the intake is fixed at a depth of 5 cm considering some factor of
safety.
=0.94m/s
Therefore, he =
=0.00144m
hr =2.4* * *sin 70
=0.0037m
Gate Loss
hL = , Where Kg = 0.2
= 0.08
pass pipe conduit. The entrapped air is therefore driven out through out the
air vent.
According to G.S. Sarkarias formula the diameter of the air vent pipe is given by;
d = 0.00578 D1.365
where, d = diameter of air vent pipe ,m
D = diameter of head race tunnel, m
Therefore,
d= 0.00578*61.365
d= 0.0667m
Hence, 67.0 mm air vent pipe is provided.
Generally there are two options to transport the water from its source (reservoir) to the
powerhouse. Theses are;
to provide a pressure shaft (penstock)
to provide a long low pressure head race tunnel, surge tank and a short pressure
shaft (penstock).
Usually the second option is adopted when the distance between the intake and the
powerhouse is long.
For Gilgel Gibe- project, which has a distance of 6.1 km between the intake and the
power house, the second option is found to be the best choice.
The minimum slope for a pressure tunnel is limited on the base of dewatering
requirement. The usual practice is to keep the slope of the power tunnel gentle; usually
a slope of 0.005 is adopted until the surge tanked and then steeper for the pressure shaft.
Flow Velocity
The allowable velocity through tunnel depends up on weather lined or unlined. For
concrete line tunnels 4 to 5 m/sec is often employed.
Optimum Cross-Section
The optimum cross section (diameter) of a tunnel or s shaft is one for which the sum of
tunnel construction cost and the economical loss due to the head loss is minimum.
For quick and initial estimate of diameter of pressure tunnel, the imperial formula
suggested by Fahibusch can be used as:
For concrete lined tunnel
D = 0.62 Q 0.48
Where D – diameter of tunnel
Q – Design discharge
D = 0.62*(82.16)0.48
= 5.45m (say, D=6m)
A= m2
V= m/s (Ok!)
Table 5.1 Cost optimization for pressure tunnel
Diameter,
(m) Tunnel cost M birr Lost cost in M birr Total cost in M birr
8.96 58.19 59.09
8.64 55.83 1.10 56.93
8.35 53.68 1.33 55.01
8.08 51.70 1.57 53.27
7.84 49.89 1.85 51.74
7.62 48.29 2.16 50.45
7.41 46.70 2.49 49.18
7.23 45.38 2.85 48.23
7.05 44.06 3.25 47.31
6.89 42.90 3.68 46.58
50.00
40.00
TOTAL COST
30.00
20.00
10.00
0.00
3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00
TUNNEL DIAMETER
The optimum diameter of the power tunnel is selected to both minimize the sum of
capital construction costs and lose of energy due to head losses and also to keep the
velocity in a permissible range.
Hence for Gilgel Gibe project, an optimum diameter of 6.0m is selected for pressure
tunnel from the above cost optimization
The minimum concrete thickness, to provide rigidity against the water pressure can be
determined according to U.S.B.R recommendation, which is given by;
t(mm) =
Then,
t=
= 16.25 mm
Allowing 1.5mm extra thickness for correction;
t= 16.25 + 1.5 = 17.75 mm, say t = 18mm
Therefore, 6.0m internal diameter head race tunnel and 18mm thick concrete lining is
provided.
As min ≥
As min ≥
Vo =
LT = 5500m
AT = 2
hf = f = 7.1m
hfp = f
Total loss,
hT = hf + hfp + loss in the trash rake + loss in entry
= 7.1 + 1.785 + 0.0033 + 0.00144
= 8.89m
Hnet = 108 – 8.89
=99.11m
Therefore,
As min =
= 95.38 m2
But, Asurge =
144.25 = , D = 13.5m
Therefore, for this particular project a surge tank with a diameter of 13.5m will be
provided.
In actual installation, frictional effect is not negligible. Jaeger has recommended the
following formula for computing up surge and down surge in the case where the friction
is taken into account.
Po =
Zmax = Vo
Zmax = 2.91
Zmax = 30.63m
Po = =
Zup = Zmax
= 30.63*
= 25.71m
Zdown = Zmax
= 30.63(-1 + 2*0.232)
= -16.42m
Therefore, the height of surge tank will be:
H = Zup + Zdown + height of live storage + 3m(for protection of air entry)
H = 25.73 +16.42 + 5 + 3
H = 50.0 m
5.4 Penstock
A penstock is high pressure pipe line between surge tank or reservoir and a turbine. In
designing of a penstock, water hammer effect must be considered
.
Factors that must be considered for the choice of material for pressure tunnel are head,
topography, and discharge. Various materials used are steel, RC, asbestos cement, PVC,
etc. But the following factors have to also be considered when deciding materials to use
for. These are required pressure, design life etc. Steel penstock become the most
common type of installation in hydropower development due to simplicity in
fabrication, strength and has long life etc. Hence considering the above criteria’s a steel
penstock is selected for this particular project.
Number of penstocks
The number of penstocks used in any particular installation can be single or multiple.
The design should strive for maximum economic solution. If the number of penstocks
increases the total weight of steel and the erection cost also increase.
The present trend is to use a single penstock. Based on this, a single penstock which has
two manifolds at the end of the penstock and valves at the beginning of each manifold
to control the flow are designed.
The allowable velocity for a pressure shaft which is steel lined, is in the range 5m/sec to
8m/sec.According to USBR empirical formula for economical diameter of a penstock:
V = 0.125
V < 0.125*
< 5.5 m/s
V= =
= -------------(*)
Where
Q= design discharge
D = diameter of penstock (m)
L = length of penstock
hf =
V= =0.554
V= ------------ (**)
Solving the above equation by trial and error procedure the required diameter become:
D=4.5m
Checking for the allowable velocity:
A= m2
V= = 82/15.9
sudden pressure rise known as water hammer, due to the moment of flowing water
being destroyed.
Ideally there will be, a series of pressure waves traveling back and forth over the length
of the pipe. The celerity of these pressure waves can be calculated by the formula:
C=
Where,
C =celerity of wave in m/sec
Eb = bulk modules of water = 2.1*109pa
B = modulus of elasticity of steel =2.1*1011pa
= mass density of water = 1000 kg/m3
D = internal diameter of penstock = 4.5m
t = thickness of steel linear in m
C=
C=
Pc=
Pc = *
t=
The total internal pressure (PT) in the penstock as a function of depth (h) below the
intake level is given by:
= h + (1428 -1420) +
The above formula related to the design of penstock thickness when the whole water
pressure is taken by penstock liner and no load is shared by the rock or concrete. But in
actual case the design of pressure conduits in under ground power house is influenced
by the available rock cover and the characteristics of the rock.
When steel liners are installed in pressure conduit it requires proportioning of internal
pressure between steel and surrounding rock.
The formula given by F.W Patterson, R.L clinch and I.W Mc Lag’s is used to
proportion the pressure taken by out side steel liner and surrounding rock to adopt an
economical steel liner thickness as show below. (R.S Varshemy).
Where:
E = young’s modulus for steel in t/m2
Ec = young’s modulus for concrete in t/m2
Er = young’s modulus for rock in t/m2
b= radius to inside of steel liner in m
c = radius of out side surrounding concrete in m
d = radius to end of radial fissures in rock in m
R = radius to point considered in m
t = thickness of steel liner
e= gap between steel liner and surrounding material in m
1/m = poison’s ration for rock
P = pressure in conduit in t/m2
= proportion of pressure taken by out side steel liner and by the rock.
The values of the above variables for this project are taken as:
t = 30mm 0.03m (assumed)
e = 3 mm 0.003m (assumed)
b = 2.25m
c = 2.25 +0.5 +0.03 = 2.8 (assuming thickness of concert =0.5m)
E = 21*106t/m2
Ec= 1.4 * 106 t/m2
Er = 0.75*106t/m2
Substituting the values in the above equation, the total internal pressure:
Ps =
Ps =
=482.08m
So, PT = h+8+482.08
= (h+ 490.08) t/m2
Then the proportioning of internal pressure between steel and rock will be;
Numerator
Denominator=
Therefore, the values of at various depths from the top of intake level are given
below:
P= *(h + 482.08)
r = radius of penstock =2.25m
q = max. Permissible stress = 10,000 t/m2
V= velocity in tunnel
D= diameter of tunnel
L= length of tunnel
ht =
=7.1m
hlp =
=1.78m
hf = Q2 =
= constant
Where:
Q = discharge through the penstock
Q2 = discharge through the main fold
D1 = diameter of pens
D2 = diameter of manifolds
Since there are two units of turbine for this particular project the magnitude of flow
which passes safely through each manifold will be half of the designed discharge.
i.e. Q2=
D2=
=
=3.4m
Therefore, adopt a diameter of 3.4 for both of the manifolds which feed for each of the
two turbines.
Shape: Tunnels are either circular or non circular in shape. Circular tunnels are
structurally more stable. They are more stable when the internal water pressure is high.
Non-circular tunnels usually have flat floor, near vertical or gently flaring walls and
arching roof. The most popular of the various sections adopted is the so called horse
shape. Horse shoe shapes are very convenient from the construction point of view.
Alignment: The alignment should be following the location of the power house on one
hand and suitable reach f a natural river on the other hand, keeping in view the length as
short as possible, the alignment away from dangerous fault planes.
Slope: gentle longitudinal slope (=0.005) should be provided in the case of tail race
tunnel to make it allow pressure tunnel.
Lining: Lining is a protective layer of concrete, RCC or steel on linear surface of the
tunnel. Tunnel in good round rock can be left unlined. Most of the time low pressure
tunnels are left unlined.
V=
R=
R=
V=
Where:
Q = design discharge = 82m3/sec
V=
D=5.7m
V=82/26.94
V=3.0m/s
Thus the velocity is within the range of allowable velocity for trimmed tunnel.
Therefore adopt a tail race tunnel of:
D = 5.7m
A = 23.94 m2
L = 300m
CHAPTER SIX
PRELIMINARY POWER ASSESSMENT AND POWER
HOUSE LAYOUT
6.1 General
Hydropower is extracted from the natural potential of usable water resources. The
transformation of the pressure and kinetic energy of water in to more easily usable form
of electrical energy is takes place in the power house. The plant of hydropower includes
different structures such as dams, intakes, conveyance structure, penstock, power house,
surge tank, draft tube and tail race.
Based on these criteria, the powerhouse is located at a position 1320m above mean sea
level so that a total gross head of 108 m is developed including the tailrace outlet.
6.3 Overburden
For pressure tunnels, it is obvious that the overburden of the rock on the roof of the
tunnel serves to balance the effect of upward force due to internal pressure. The
minimum desirable height of the overburden ‘hr’ for any given internal water pressure
head ‘h’ is given by the following condition.
Where γw and γr are the unit weight of water and rock respectively
nγwh = γrhr
Therefore, the tunnel alignment should be selected along a location where a minimum
over burden of 20m available. For our project there is ample overburden pressure
through out the tunnel, therefore, overburden pressure problem is not a major concern.
Because of many reasons Gilgel Gibe II hydropower project has an underground power
house than surface powerhouse. Some of the reasons are costs, risks operation and
maintenance and the availability of good sound rock at the desired location and depth.
Due to these good topographic and geologic conditions underground power house is the
best choice for this particular project
For our project downstream station arrangement is the best because most of the head is
gained by a long water way releasing water. The down stream station arrangement has a
long and nearly horizontal pressure tunnel together with pressure shaft and a short tail
race tunnel.
The layout contains the following sections, nearly horizontal pressure tunnel, inclined
pressure shaft, under ground power house, tailrace tunnel and access tunnel.
The pressure tunnel is 5500m long inclined at approximately 0.5% slope. It is classified
as low pressure tunnel and line with concrete over its whole length. A surge is provided
at the end of the pressure tunnel. Inclined pressure shaft (penstock) has a length of
510m and has a slope of 19.9%. It is steel lined over its whole length. The tail race
tunnel has a length of 300m and it is inclined at approximately 0.5 % has a horse shoe
shape and trimmed rock surface. It will be supported by short crating and bolting. The
lay out of the hydropower plant is given on appendix.
Let ‘p’ be the potential power for a stream having head ‘H’ and a discharge ‘Q’. The
theoretical potential power can be expressed as
P = ηoγQH
Load Factor
It is the ratio of average load to the peak load and is expressed as a daily, weakly,
monthly or yearly value. The load factor can be taken within the range of 0.4 to 0.6 for
developing countries. Generally the load factor gives an idea of utilization of plant
capacity.
Installed Capacity
Installed capacity or plant capacity refers to the maximum power that a power plant can
produce at its full capacity using the maximum available head and maximum discharge
condition.
Qmax = Qaverage
Load factor
=82.07m3/s
P = 0.85*9.81*82*99
P = 67.69 MW
Pfirm = 0.85*9.81*34.47*99
Pfirm = 28.46 MW
CHAPTER SEVEN
HYDRAULIC TURBINES AND ELECTOMECHANICAL
EQUIPMENT
7.1 General
Hydraulic turbines are a machine, which use the energy of water and converts it into
mechanical energy. The mechanical energy so produced is used to drive the electric
generator.
economical. Since higher specific speed is generally more liable to cavitations, it is not
possible to increase the speed indefinitely. So, suitable range of specific speed should
be selected. In addition specific speed is an important parameter for the design of the
turbine as it includes all the three parameters. i.e. speed, power and head of the turbine.
Cavitations Characteristics
Cavitations affect the installation of a reaction turbine. It is better to install the turbines
as much above the tail water level as possible. This saves the cost of excavation for the
draft tube. Care should be taken to ensure that cavitations not to occur.
Overall Cost
It includes initial cost and running cost. As much as possible we have to adapt minimum
overall cost turbine unit. Therefore, based on the available head h= 99m, Francis turbine
It includes initial cost and running cost. As much as possible we have to adapt is
considered in this particular project. The turbine size and number of unit have to be
chosen so as to given optimum working condition as well as economy. If to big a size of
a single unit is adapted the failure may result in considerable slashing of load. On the
other hand, too small a turbine size may mean more number of units and thus is
uneconomical.
After knowing total installed capacity, the number of unit is decided. If the capacity of
the turbine is fixed, it will have to run at low efficiency during low demand period. If
load is constant, only one unit provided. However if the load goes down to 50% of the
installation capacity, two units would be better. An additional unit is provided for extra
capacity during surplus flow.
For this particular project, the installation capacity is not much high that means about
67.69MW, so it is enough to select two units.
Generally, Francis turbines have high efficiency at medium specific speed. The table
below shows the value of the specific speed ranges and the efficiencies of the three
main types of turbine.
Ns = = =164.83
c. Moody formula
Ns = +83.6
= +83.6 =145.945
Ns = = = 167.983
e. Guthrie brown
Ns= 141
f. USBR formula (for Francis turbine)
Ns = = =154.776
=0.9*H
Hc = 0.9*99 =89.1
Ns = =167.684
Taking the average of the above values the specific speed will become
Ns =158.995 =159
η=90%
Q= 82m3/s (design discharge)
γ =Specific weight of water
P = η*γ*Q*H
=0.9*0.81*103*82*99
= 71673.822kw
P1=P/2=35836.911KW
N=
N= Where, f=50Hz
NP= no of poles
NP=
Therefore,
N= =250<=262 OK!
Ns=
Nr = Kn *N*
Where,
Kn = (o.1475 Ns +14.5) in % age
= (o.1475*152+145)
= 167.42 in % age
= Kn =1.6742
= Nr = 1.6742*250
= 437.16 r.p.m
ii. F.de Siervo and F.de. Leva (1997) formula
Nr = 1.52N (1*0.001N3)
= 1.52 * 250 (1+0.001*152) = 437.76
a. Kruegers formula
¢=0.0197*Ns2/3 +0.09
=0.0197*1522/3 +0.09
=0.651
b. Nag.and K.Madhvan’s formula
¢=0.036*Ns7/12
=0.036*1527/12
=0.675
c. D.ZanoBett’s formula
¢=0.68+
=0.68 +
=0.741
Taking the average of the three, the value of ¢ is 0.689
The determination of discharge diameter using E.Mosonyi’s formula is as follows:
D=84.6*¢*
D3= D (0.5+ )
- According to F.de Siervo and F.de.Leva. Water velocity at spiral case inlet
section can be calculated as
V= 844 *NS-0.44
= 844 (152)-0.44=92.54 m/s
A = D3 (1.2 - )
F = D3 (1 + ) =2.08 (1 + ) = 3.80m
type draft tube, because of the following advantages it offers over the straight
type.
- Minimizes the required depth of excavation.
- Directs the flow in the direction of the tail water flow
- Allows the provision of rate at the outlet of the tube which can facilitate the de-
watering of the turbine for repairing.
V1 =8.74 *
S = D3 = 2.04 * = 10.80m
T = D3 (1.5+0.00019NS) = 2.0 (1.5 +0.00019*152) =3.12m
U= D3 (0.51 -0.0007 NS) =2.0 (O.51 -0.0007*152)=0.82m
7.5 Cavitation
Cavitation is the formation in subsequent collapse of vapor pockets in a region of liquid
where the pressure has been reduced to that of vapor pressure of the liquid. When the
pressure in any part of flow passage reaches the vapor pressure of the flowing liquid it
starts vaporizing and small bobbles of vapor form in large number.
The effects of cavitations are:-
- Surface of the vanes subjected to intense pressure during the collapse becomes
scored, pitted and even torn.
- Cause noise and vibration.
- Cavitations in a turbine can be avoided by the following measures
- A careful stream lined design of the flow passages of the runner as well as that
of draft tube.
- The average sub-atmospheric pressure at runner outlet is kept reasonably above
the vapor pressure limit.
- Some metals are more resistance to cavitations damage than others.
- By a periodic inspection of the turbine and by regular spot welding the eroded
portions.
Since reaction turbine is running under pressure, they are exposed for cavitations than
impulse turbine. So the above measures should be carefully used. In order to have
cavitations free operation of a turbine;
Pmin>P V => σc<σ
The expression used to determine the maximum elevation (Z max) of the turbine above
the tail water surface for vacation to be avoided.
σc= 0.625 *
Mechanical Equipments
- Shafts, bearings, coupling etc. for the generator
- The oil circuits and pumps
- Compressors and air ducts
- Breaking equipments
Besides the above auxiliary equipments, lighting, water supply and drainage facilities
are also required for the power house.
7.7.2 Generator
The generator should have vertical configuration, protection against run away speed are
to be provided. This machine should be capable of supplying heavy line charging
current since the hydroelectric power plant is located at a considerable distance from the
load end.
The different parameter of the generator is designed as follows:
Weight of Generator
Using USBR formula
Wg= g - 85 tones
= =
= 89592.2775KVA
Wg=26* -85
= 407.2 tones
≈ 408 tones
D’g=
D’g= =5.28m
Df =Dg* + 1.55
= 7.5* + 1.55
= 9.71m
The generator pit diameter in meter
DP = Df+2
= 9.71+2
= 11.71m
Total height of the generator in meter
Hg= k’S * +2.3 Where: k’s = is constant varies from 5.5 to 12.75
Take, k= 8
Hg = 8 * +2.3
=4.8m
≈ 5m
Hence the generator has;
Height =5m
Weight = 404 tones
Diameter = 7.5m
Pit diameter =11.71m
Gap-diameter =5.28m
Frame diameter =9.71m
The existing transmission voltages in Ethiopia inter connected system (ICS) are 230 KV
and 132KV. Based on this experience, we suggest a step up transformer of 230 KV,
which is located in separate cavern or hall in the powerhouse.
A transmission system delivers huge power from the power station to the load center. In
our case the overhead line to take the advantage of air insulation, which decreases the
cost for insulation, should transmit it. Since the insinuated cables are exposed to
lighting and fall of trees, the load close to the lines has to be cleared of trees and carried
out periodically.
CHAPTER EIGHT
POWER HOUSE DIMENSIONING
8.1 General
The power house is a building constructed for housing and protection of various
hydraulic and electrical equipment required for the generation of power. The power
house provides the following main equipment and facilities:
I. Water conveyance structure penstock, draft tube etc.
II. Energy conversion equipments turbines, generator etc.
III. Electrical energy control equipments switch board, control equipments
etc.
IV. Other facilities.
As the name implies in the surface power station the units and all other equipments and
power house is situated over the ground surface, usually surface power house is
accompanied with power canal following the terrain, forbay and surface penstock which
has no space limitation and maintenance of power house is easy.
On the other hand, under ground power house is accompanied by head race tunnel,
surge shaft, embedded penstock and tail race tunnel. Under ground power house is safer
during war attacks and in areas with frequent seismic activates, land slides, and flood
etc. If there is a gorge, a valley, and good geology around the site an under ground
power house is found to be the economical choice.
For this particular project, due to good geologic and topographic condition, under
ground powerhouse is selected. The layout of the powerhouse is shown on the
appendix.
1. Unit spacing
i. N- Ven Kata raws (1960) formula (for Francis turbine)
Unit spacing = (3.8 to 5) D
= 4.4 D
= 4.4 * 2.04 = 8.976 ≈ 9m
=(5.5- )*2.04
= 9.6696 ≈10
Adapt unit spacing =10m
2. Length
The length of the machine hall depends on the number of units and the size of the
machine. The preliminary dimensions between center to center of two unit is
L = 5D +2.5 m
L = 5* 2.04 +2.5
= 12.7
Hence the total length:
LT = 2 unit + 1 unit for erection bay + 1unit for control room.
= 4 units
= 4 * 12.7 = 50.8m
3. Width
The width of the machine hall is determined by the size and clearance spacing between
the wall needed as a gantry way.
I. According to U.S.B.R, the width of the power house can be calculated as;
W =F+C+2+1.85D
F= D (1+ )
C = D (1.32+ )
4. Height
The height of the machine hall is fixed by the head room requirement. The hall must
have a height which will enable the crane to lift the rotor of the generator or the runner
clear of the floor with out any obstruction.
The capacity of generator can be calculated using the power factor for the generator. A
power factor of 0.85 is selected for the installed capacity of 67 MW and plant factor of
0.4.
Generator capacity =
For this much capacity and net head of 99m the total height from generator floor to
crane rail is obtained to be after two step linear interpolation is 15.72m
space for crane hook can be taken as 2m
height of the generator = 5m
hence, total H = 15.72 + 2m = 17.72m ≈ 18m
To conclude, a power house of the following dimension is provided for Gilgel Gibe II
hydropower project.
Length X Width X Height
(50.8 m X 12.7 m X 18 m)
CHAPTER NINE
ENVIRONMENTAL IMPACT ASSESSMENT
9.1 General
Hydropower projects that are intended to produce electric energy, may cause
irreversible environmental changes over a wide geographic area and thus have a
potential for significant impacts. The area of influence of the project extends from the
upper limits of the catchments to far down stream. Therefore hydro project such as
Gilgel gibe II are designed to enhance economic development and bring a better
standard of life to people due consideration should be given to their adverse
environmental and social effects. This can be done through environmental impact
assessment which is a management tool for officials and manager who take decision
about important development project.
The EIA not only predicts potential problems but also identifies measures to minimize
the problems and out lines ways to improve the project suitability for its proposed
environment.
Generally EIA can be described in short as an instrument used to identify, predict and
assess the environmental consequences of a proposed major development project.
Moreover EIA is used to plan appropriate measures to reduce adverse effects.
The amount of water in the river will highly reduce during most time of the year due to
diverting of the river water to a 6.1 km power tunnel for generating but the river flow
has a minimum flow of 1.3m3/sec from the tributaries, so that it will not affect human
and domestic animal water requirements but aquatic fauna particularly fish and large
animals like hippocampus and crocodile may be affected.
dictated by power demand cycles. All these changes well definitely deterioration and
physical changes can also result in chemical impact to the river system, like inclination
of trees and other vegetation may lead to increase in nitrate and phosphate imputes that
would initiate eutrophication (depletion of oxygen).
9.2.5 Sedimentation
Sedimentation studies carried out for upper Gilgel Gibe reservoir indicates that most
of the suspended sediment is represented by very fine particles of silt and clay and
considering the amount of sediment deposited in the upper reservoir, the estimated
annual sediment yield at Billie weir is in order of 0.25 million tones.
Natural hazards
Since the project area is close to the rift valley which has the most active seismic
centers, energy developed by earth quake originating should be considered.
In most of the impact areas a fairly dense wood land or wooden grassland will be
affected permanently.
The area to be taken for strong water, which will be cleared before reservoir filling will
be an important loss of wild life habitat. Animals moved to the adjacent areas could
become more vulnerable to poaching by the local people or immigrant people during
the construction period.
During construction period there will be job opportunities attracting labor force from
out side the area. This new influx will change the existing population. The main effects
will be increased exposure of workers and their families to locally endemic diseases and
sexually transmitted diseases.
CHAPTER TEN
ECONOMIC ANALYSIS
10.1 General
Economic analysis in a hydropower project deals primarily with the development and
application of benefit – cost analysis, which is the most frequently, used procedure for
project economic evaluation. The objective of economic analysis is to provide an
economic basis for deciding weather on not to implement a project.
5 Infrastructure and
Access
to the weir Km 150.000 2
0.27
to the powerhouse Km 150.000 4
0.6
camp facility
4.0
tunnel m3 42
6.33
Sub total= 11.2
6 Hydro Mechanical
Equipment
-intake gates, trash rack, 2.85
trash rack cleaning, gate
opening equipment
The equivalent annual cost calculated from the total cost of the projects will be
A = CRF *C
Where,
A = annual equivalent project costs
C = total project cost
CRF = capital recovery facto
Where, i = annual interest rate
= 10%
N= project life, 50 Years
CRF =
=0.1
NPV =
=19.34M$UDS
NPV =
IRR = 12 % > 10 %
Therefore, from the above the project is economically feasible.