You are on page 1of 3

a.

Payback

To determine the payback, construct the cumulative cash flows for each projects:

Project X Project Y
Year Cash Flows Cumulative CF Cash Flows Cumulative CF
0 ($10,000) ($10,000) ($10,000) ($10,000)
1 6500 (3500) 3500 (6500)
2 3000 (500) 3500 (3000)
3 3000 2500 3500 500
4 1000 3500 3500 4000

$ 500
Paybackx = 2+ = 2.17 years.
$ 3000
$ 3000
Paybackx = 2+ = 2.87 years.
$ 3 5 00
Net Present value (NPV):

$ 6500 $ 3000 $ 3000 $ 1000


NPVX = -$10000 + 1 + 2 + 3 + 4
(1.12) (1.12) (1.12) (1.12)
= $10,000 + $5,803.57+ $2,391.58 + $2,135.34 + $635.52

= $966.02

$ 3 500 $ 3 5 00 $ 3 5 00 $ 3500
NPV Y = - $10000 + 1 + 2 + 3 + 4
(1.12) ( 1.12) ( 1.12) (1.12)

= - $10,000 + $3,125.00 + $2,790.18 + $2,491.23 + $2,224.31


= $630.72

Alternatively, 'using a financial calculator, input the cash flows into the cash flow register,

Enter I = 12, and then press the NPV key to obtain NPV X= $966.01 and NPVY = $630.72,

Internal rate of return (IRR): To solve for each project's IRR, find the discount rates: that equate
each NPV to zero:

IRRX = 18.0%

IRRY = 15.0%.

Modified internal rate of return (MIRR):


TV
PV of cash outflows = n
(1+ MIRR)

Cost =
∑ CIFt (1+r )n−t
t=1

(1+ MIRR)n

$10000 = $ 6500 ¿ ¿

$ 17,255.23
$10,000 = 4
(1+ MIRRx )
$ 17,255.23
(1+ MIRRx )4 =
$ 10,000
1
MRRX = (1.725523)4 – 1.0

= 0.1481
= 14.81%

$10000 = $ 3 500¿ ¿

$ 16 , 727.65
$10,000 =
(1+ MIRR y )4

$ 16,727.65
(1+ MIRR y )4 =
$ 10,000
1
MRRX = ( $ 16,727.65) 4 – 1.0

= 0.1373
= 13.73%
Discounted Payback Period (PBDisc):
To determine the discounted payback, construct the cumulative discounted
cash flows for each project:
Project X Project Y
Year PV CF @ 12% Cumulative CF PV CF @ 12% Cumulative CF
0 ($10,000.00) ($10,000.00) ($10,000.00) ($10,000.00)
1 5,803.57 (4196.43) 3125.00 (6,875.00)
2 2,391.58 (1,804.85) 2790.18 (4,084.82)
3 2,135.34 330.49 2,491.23 (1,593.59)
4 635.52 966.01 2,224.31 630.72

$ 1,804.85
PBDiscX = 2+ = 2.85 years
$ 2,13 5.34
$ 1,593.59
PB DiscY = 3+ = 3.72 years
$ 2,224.31

b. The following table summarizes the project Rangkings by each method:

Project that Ranks higher


Traditional Payback X
NPV X
IRR X
MIRR X
PBDisc X

Note that all methods rank Project X over Project Y. In addition, both
projects are acceptable under the NPV, IRR, MIRR, and PBDisc criteria.
Thus, both projects should be accepted if they are independent.

You might also like