FABRICATION CLAIM BRASHING

Custome / User / Plant : PT. BLP - EMCL = PLANING = OFFDAY


Project / Job Title : FABRICATION CLAIM BRASHING = IN PROGRESS
Job No. : 19 JMS 008 = FINISH on schedule
Date : 08 Februari 2019 = FINISHED TO LATE

MANPOWER - Duration - Maret 2019


No. DESCRIPTION OF WORK % Bobot
Person Days
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8
1 Inquiry Proposal DONE
2 Procurement 2 3 days
Plate Bar BLP
Paint BLP
Cupbrush & Stik weld & MataBor LNS-BJN 3

3 Fabrication Stage 4 Person 9 days


Marking LNS-Cerme 2 days 5,0
Cutting Plate Bar LNS-Cerme 3 days 6,0
Drill Bucket LNS-Cerme 9 days 8,0
Bending : LNS-Cerme 19 days
2" = 52 ea LNS-Cerme 6 days 12,0
3" = 6 ea LNS-Cerme 1 days 5,0
4" = 16 ea LNS-Cerme 1 days 6,0
10" = 22 ea LNS-Cerme 3 days 10,0
12" = 12 ea LNS-Cerme 2 days 8,0
14" = 2 ea LNS-Cerme 2 days 8,0
16" = 2 ea LNS-Cerme 3 days 8,0
20" = 2 ea LNS-Cerme 3 days 8,0
Welding LNS - BJN 25 days 10,0
Coating (cupbrush and Painting) LNS - BJN 28 days 6,0

Total 100,0

Rencana 0 0 0 0 0 0 0 0 0 0 0 0 0
Jumlah Komulatif #REF! #REF! #### #### #### #### #### #### #### ### ### #### ####

Realisasi
Jumlah Komulatif

Deviasi #REF! #REF! #### #### #### #### #### #### #### ### ### #### ####