Activity List – July 2018

Name: Michael Hailu Job Title: Project Engineer

N Activity Expected Collaborating Remark


o Completion Person
Date
 Searching manufacturers /suppliers for AAWASA’s Diesel In the first Nardos,eyerusale
generators. Two weeks m ,Jene & Francis
 Selecting of Better supplier/manufacturer according to the of the month
general and technical requirements of AAWASA bid
1
document.
 Double-Arrow from china was selected from the obtained
Diesel Generator manufacturers according to requirements
fulfillment.
Preparing of four types of documents for the Bid of Diesel generators In the last Nardos,eyerusale
according to requirement of Bid document as follows: two weeks of m ,Jene & Francis
 technical offer proposal, the month
2  Financial proposal
 Certification of compliance
 Installation cost
 General requirements etc.

Please describe any pending task and related reason in general.