Punch List Items Balance work as on 27.04.

2020
Total Qty as Previous Today Done Upto date Total Balance
Sr. Items Unit Side pe Punch list Done Qty Qty Done Qty Qty.

1 CC Drain including outlet Km LHS & RHS 3.042 0.229 0.000 0.229 2.813
2 Road side Kuchcha drain as per CA Metre BHS 58861 12768 9397 22165 36695
Km LHS 1.121 0.556 0.000 0.556 0.565
3 (a) Service Road
Km RHS 1.821 0.466 0.000 0.466 1.355
Km LHS 0.222 0 0.000 0.000 0.222
3(b) Service Road Hindrance
Km RHS 0.807 0 0.000 0.000 0.807
Km LHS 1.369 0.504 0.180 0.684 0.555
4 (a) Slip Roads
Km RHS 0.419 0.230 0.000 0.230 0.189
Km LHS 0.160 0.000 0.000 0.000 0.160
4(b) Slip Road Hindrance
Km RHS 0.090 0.000 0.000 0.000 0.090
5 Bus shelter Each LHS & RHS 12 4 0.000 4.000 8
6 Bus Bays Each LHS & RHS 16 14.000 1.000 15.000 1
Km LHS 2.077 1.245 0.000 1.245 0.392
7 Kerb /SR/Slip Road/PQC outer
Km RHS 1.382 0.000 0.000 0.000 0.542
Km LHS 14.475 5.055 0.000 5.055 9.420
8 REwall/SR/kerb/ seperator paint
Km RHS 14.475 5.197 0.000 5.197 9.278
9 Median Plantation Km Median 16.995 0.650 6.002 6.652 9.298
a) Minor Junctions Each 8 3 0.000 3.000 5
10
b) Grade Separated Intersection Each 4 0 1.000 1.000 3
11 MBCB in curves having Radii ≤ 450 m Km BHS 1.46 0.424 0.646 1.070 0
12 MBCB Built-up Km Median 4.226 3.019 0.000 3.019 0.435
Km LHS 9.608 7.736 0.000 7.736 1.872
13 Median Kerb Painting
Km RHS 10.410 8.755 0.000 8.755 1.715
Antiglare (2-Lane) Km Median 4.935 4.035 0.220 4.255 0.000
14
Antiglare (4-Lane) Metre Median 5.256 0 0.435 0.435 4.821
15 Sign Board Each BHS 139 0 0.000 0.000 139

Crash barrier painting, Painting on parapet wall, Painting on Hand railing, Protection
16 Structure Work Each works for culverts, Structure numbering, Waterway cleaning, Finishing of Structures,
wearing coat in footpath etc.

17 PCC over median where median width is 1.5


mtr (built up section) Km BHS 11.63 0 0.000 0.000 11.63

Km LHS 14.475 0 0.000 0.000 14.475


18 PCC over Seperator
Km RHS 14.475 0 0.000 0.000 14.475
km LHS 0.45 0 0.000 0.000 0.450
19 Slope Protection Work in high embankment
km RHS 0.8 0 0.000 0.000 0.800
20 Delineator Nr. 1555 0 0.000 0.000 1555
21 Service and silp road pavement marking km BHS 23.09 9.325 0.000 9.325 13.765
22 Street Lighting Rs. ###
23 Slope Dressing Km BHS 60.755 60.755 0.000 60.755 0
24 CC Drain inlet grating Each ###
25 Seprator chute drain Km BHS 4.515 0 0.000 0.000 4.515
26 Toll
work
Plaza & ATMS Project facilities balance
Each 2 1 0.000 1.000 1

27 Pedestrain Guard Rails footpath & School,


Colleges, Hospitals etc Stretch LHS 6 4 0.000 4.000 2

28 Drainage provision in superelevation area Metre Median

29 Access road to new Bypass from Existing Road. Each 3 0 0.000 0.000 3
30 Foothpath Stretch BHS 8 0 0.000 0.000 8
31 Painting Lines, Dashes, Arrows etc on Roads in
Two Coats on New Work Sq.m 3900 861.4 0.00 861.40 3039

32 Ramp-1
Lalsot
Lalsot to Jaipur & Ramp-2 Agra to
###
33 Cleaning of utility Duct Nos 66 0 0.000 0.000 66

Concessionaire's Authorized Representative IE' Authorized Representative


Total Qty as Previous Today Done Upto date Total Balance
Sr. Items Unit Side pe Punch list Done Qty Qty Done Qty Qty.

34 90m Direct Taper of Minor Junctions in 4-lane


sections Nos 14 0 0.000 0.000 14
35 Rest area 1 & 2 Each ###