RAY/THRISSUR-KUTTIPPURAM/MEASUREMENT SHEET
Work Order: REPL / APPC / 0160 / KSTP / 226 Progres Period: 01.12.21 ~ 31.12.21
Dated: December 02, 2021
Bill No:01 Date of Measurement: 31 December 2021

Chainage
Total Up to Quantity Amount
WO Line Total Quantity Amount For
Side Item Description Unit Nos Length Width Height Quantity date Rate Previously Previously
Item Amount For This Bill This Bill
From To Quantity Paid Paid

DRAIN

7.021 PCC m3 24.680 950 23,446.0 0 - 24.680 23,446.0

4364.00 4420.00 LHS PCC for Drain 1 56.00 1.70 0.100 9.520
4182.00 4230.00 LHS PCC for Drain 1 48.000 1.7 0.100 8.160
5700.00 5700.00 RHS In front of Shobha City 1 5.000 5.000
7710.00 7725.00 LHS For Culvert Diversion 1 2.000 2.000

7.02A RCC Structural Concrete for Drain m3 52.750 2,500 1,31,875.0 0 - 52.750 1,31,875.0

4364.00 4420.00 LHS Drain Raft 1 56.000 1.500 0.125 10.500


4364.00 4420.00 LHS Drain Side Wall 2 56.000 0.125 1.155 16.170
4382.00 4420.00 LHS Cover Slab 3 12.050 1.500 0.110 5.965
4182.00 4230.00 LHS Drain Raft 1 48.000 1.5 0.150 10.800
4203.00 4230.00 LHS Drain Side Wall 1st Lift 2 27.000 0.15 1.150 9.315

7.023 Reinforcement Bars Epoxy Coated Ton 5.447 10,000 54,470.0 0 - 5.447 54,470.0

4364.00 4420.00 LHS As per BBS 1 1.827 - - 1.827


4182.00 4230.00 LHS As per BBS 1 3.225 - - 3.225
4364.00 4420.00 LHS Slab 3 nos 1 0.395 - - 0.395

TOTAL 2,09,791 - 2,09,791