RAY/THRISSUR-KUTTIPPURAM/MEASUREMENT SHEET
Work Order: REPL / APPC / 0160 / KSTP / 226 Progres Period: 01.12.21 ~ 31.12.21
Dated: December 02, 2021
Bill No:01 Date of Measurement: 31 December 2021
Chainage
Total Up to Quantity Amount
WO Line Total Quantity Amount For
Side Item Description Unit Nos Length Width Height Quantity date Rate Previously Previously
Item Amount For This Bill This Bill
From To Quantity Paid Paid
DRAIN
4364.00 4420.00 LHS PCC for Drain 1 56.00 1.70 0.100 9.520
4182.00 4230.00 LHS PCC for Drain 1 48.000 1.7 0.100 8.160
5700.00 5700.00 RHS In front of Shobha City 1 5.000 5.000
7710.00 7725.00 LHS For Culvert Diversion 1 2.000 2.000
7.02A RCC Structural Concrete for Drain m3 52.750 2,500 1,31,875.0 0 - 52.750 1,31,875.0
7.023 Reinforcement Bars Epoxy Coated Ton 5.447 10,000 54,470.0 0 - 5.447 54,470.0