R&M
1.2.5 Lighting
Complete illumination system as required for complete internal and
external lighting of associated system, extended room of existing building
and buildings under bidder scope. The scope includes supply and
installation of Lighting transformers, lighting fixtures, conduits, wires,
switchboards, distribution boards etc. Existing lighting fixtures / DBs
/conduits / wires etc. shall not be use.
1.2.6 DC system
Employer shall provide 220 V DC power at one point in each unit. Cables
of suitable rating for further distribution shall be in the contractor’s scope.
In addition 20% spare feeders (minimum one spare feeder) for each type
and rating of the out going feeders shall be provided on each MCC.
1.3.3 Motors
Motors along with couplings and coupling guards for all rotating auxiliaries
covered under this package. All motors shall be with cable glands & lugs.
1.3.4 Cables
a) HT & LT Power cables, control & instrumentation cables and any
special cables for the completeness of the system required for
connection between equipment/devices in contractor’s scope and
between owner’s and bidder’s equipment.
b) Control & instrumentation cables required for connection between
equipment/devices in contractor’s scope and between owner’s and
bidder’s
equipment.
1.3.5 Cabling, earthing and lightning protection
a) Cabling viz., cable laying along with cable accessories, cable trays
with supporting structure, terminations & jointing kits, trenches,
overhead trestle, duct banks etc as required for the cables to be
supplied by the contractor
b) Grounding and lightning protection for the plant and equipment under
bidder’s scope with its interconnection to the nearest owner’s earth
grid at two points.
1.3.6 Illumination system
Complete illumination system as required for complete
internal and external lighting of associated plant and
buildings under bidder scope.
1.3.7 Control system
PLC based control system for the entire ash handling system of stage-I
under this package as per tender drawing titled 'PLC configuration diagram
i. One (1) no. Main control desk for stage-I along with mimic of entire
ash handling system on OWS, push buttons, control & selector
switches, lamps and meters.
ii. Processor panel for control room for housing the hot redundant
processors, complete with I/O racks and necessary hardware as
per system requirement.
iii. For control, monitoring & interlocks between the Employer’s
existing ash handling system & the bidder’s ash handling system,
equipment facility of two ways communication from the bidder’s
PLC system to existing PLC system shall be provided. Bidder’s
scope shall include the complete hardware & software as required
for successful operation of the complete dry ash handling system
of stage-I.