NAVI MUMBAI METRO LINE 1

Mast Calculation - Panchanand Depot


Mast: TTC 5.5m
1.Specifications:
Cables & Wires
nominal tension with
section diam weight
Description material tension wind
2
mm mm kg kg(35' ) kg(35' )
Earth cable Steel 93.3 12.5 0.437 500 738
Catenary wire Cu Cd 65 10.5 0.597 1200 1200
Contact wire Hard Copper 150 14.5 1.34 1200 1200
Anticreep cable Cu Cd 65 10.5 0.597 1000 594

2 TTC 5.5m
Width of moment of moment of Section of Section of
Weight Depth of sec. Area of sec.
sec. 2
Inertia X-X Inertia Y-Y modulus X-X modulus Y-Y
(kg/m) (mm) (cm ) 4 4 3 3
(mm) (cm ) (cm ) (cm ) (cm )
104 300 225 66.5 4787.5 814 471 106.6

3 Schematic drawing : 5.5

0.152

Heights are with


respect to
Foundation level
- + - +
Hmw 0.00
3.0 2.0 Hcw 5.95
6.95(Hopc)

H'mw 0.00
9.60(Hm)

5.5(Hcw)

5.5(Hcw)

H'cw 5.95
Hm 9.60
HOPC 6.95
0.300 Stagger 1 -0.20
Stagger 2 -0.20
0.45
0.55

4.9
1.50

1/3
Ref.Line: Centre Line of Track(Considered as Tangent) + ve - ve

1.Radial Tension
Deviation from left side Deviation from right side
Radial Tension = X Tension of the
Left Span Right Span conductor

Left Span = 27.00 Avg Span (IR) = 27.00


Right Span = 27.00

Track Left Centre Right

OHE (HWT)
0.200 -0.200 0.000
0.200 -0.200 0.000
0.400 0.200
((0.4/ 27) + (0.2 /27)) X 1200 = 27 kg

OHE (XO-4)
-0.150 -0.200 0.000
-0.150 -0.200 0.000
0.050 0.200
((0.05/ 27) + (0.2 /27)) X 1200 = 11 kg

OPC (SL8) -3.000 -3.000 -3.000

-0.300 -0.300 -0.150

-3.300 -3.300 -3.150

0.000 0.150
((0/27) + (0.15/27)) X 738 = 4 kg

2.Wind Load (Perpendicular to Track)


OHE (HWT) = 0.67X150X(14.5)/1000 X27.00= 39 kg
OHE (XO-4) = 0.67X150X(14.5)/1000 X27.00= 39 kg Conductor = 0.67
OPC = 0.67X150X(12.5)/1000 X27.00= 35 kg Mast(Safety Factor) = 1.5
Upright = 1.5 X 150 X 0.225 X 8.1= 410 kg Wind Pressure = 150
2
Drop Arm = 1.5 X 150 X 0.152 X 3.0= 103 kg kg/m

3.Lever Arm
OHE (HWT) 3.0+(.300/2)+0.200 = 3.350 m
OHE (XO-4) 3.0+(4.9-2.1)+(.300/2) 5.950 m

4.Vertical Load
OHE (HWT) 1.34 X 27 = 36 kg
OHE (XO-4) 1.34 X 27 = 36 kg
Bracket (2 Nos.) = 120 kg
Upright (9.6-1.5)X104 = 842 kg
OPC (0.437) X 27 = 12 kg
Boom = 265 kg
Weight of Drop Arm = 130 kg
Total vertical load
on Drop Arm (1.34)X27+130+120+60 346 kg
(wt. of OHE+wt. of DA + wt. of BKT+Man wt.)
Weight of TTK = 88 kg

5. Wind load parallel to track


Upright 1.5 X 150 X 0.300 X 8.1 = 547 kg
Bracket( for each) = 40 kg
Boom = 80 kg
Drop Arm = 100 kg

2/3
Design of OHE Mast
Displacement of Bracket OHE (SL8) OHE (SL7)
Type of Mast TTC 5.5m d=L T 0.291 TTC 8m 27.00 21.80 Implantation 3.00
Wind Perpendicular to track Wind parallel to track
Lever arm X - axis Y - axis Type of load Lever arm X - axis Y - axis Y - axis
Type of Load (m) Load (Kg) BM (Kg-m) BM (Kg-m) (m) Load (Kg) BM (Kg-m) BM (Kg-m) Load (Kg) BM (Kg-m)
Permanent (Horiz. point load) Lp d*BM / i Temporary Wind load Lw d*BM / i load Lw
OHE (SL8) 5.95 27 161 16 OHE (SL8) 5.95 39 232 23
OHE (SL7) 5.95 11 65 6 OHE (SL7) 5.95 39 232 23
OPC 6.95 4 28 OPC 6.95 35 243
Total 42 254 22 Upright 4.05 410 1661 547 2215
H1 M1 M3 Bracket 6.45 80 516
Drop Arm 1.5 103 155 100 150
Vertical load Boom 8.0 80 640
X-axis Y-axis
Lever arm Load BM BM (Kg-m)
(m) (kg) (kgm) d*BM / i
OHE+B/2+Man
+kit 3.350 176 590 57 Total 626 M5= 2522 M7= 46 H3= 807 M6= 3521
Total vertical X-axis
load on Drop
Arm 5.950 346 2059 H2 M1= 254 M3= 22 M3= 22
1/2*Bracket 30 M2= 4107 M4= 57 M1= 254 M4= 57
Boom 5.50 265 1458 M2= 4107
Upright 842
Weight of TTK 88 Wind Perpendicular to track Wind parallel to track
OPC 12 x-axis y-axis x-axis y-axis
Total 1759 4107 57 Total BM at top of Foundation 6883 125 4361 3600
V1 M2 M4
Proposed Foundation : P7