al-ressalla hospital dafo for electrical and mechanical works 28-01-2020

Feb 02 Feb 09 Feb 16 Feb 23 Mar 01 Mar 08 Mar 15 Mar 22 Mar 29 Apr 05 Apr 12 Apr 19 Apr 26 May 03
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
04-May-20, RE Al-resalla

10-Mar-20, RE.1 roof works


pipe installation
pipe testing
pipe insullation
pipe clading
10-Mar-20, RE.2 internal works
pipe riser installation
pipe rizer testing
connecting with floors
riser pipe insulation
04-May-20, RE.3 comissioning wo
Chemical cleaning
3-way+flexiible conection to fancoil
electrical connection to the fancoil
thermostat fixed
trial operation
air balancing
3-way insullation

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: 2 Week Lookahead.

Remaining Work Milestone © Primavera Systems, Inc.