SANTOS LAND DEVELOPMENT CORPORATION

Bajada Special Project


Manpower Requirement
JOMARI CHRIS BERON (Mechanical QC Engineer)
MONTH OF
MAY-JUNE DAILY WORK LOGSHEET OVERTIME
ACTIVITY / TASK PERFORMED
Date (dd/mm) Ivory FHR Housing Syntek DMO TOTAL (hrs) Ivory FHR Housing Syntek DMO TOTAL (hrs)

18-May 8 8 - Site Supervision for Elevator Works - Service Car Installation


19-May 8 8 - Site Supervision for Elevator Works - Service Car & Landing door Installation
20-May 8 8 - Site Supervision for EE room Painting, Wall Buffing & Floor Tapping works
21-May 8 8 - Site Supervision for Elevator works (Machine room equipment installation)
22-May 8 8 - Site Supervision for Elevator works - Hoistway Rope and Counterweight Inst.
23-May 8 8 - Site walkthrough in preparation for Elevator inspection
(Sunday) - -
25-May 8 8 - Supervision and walkthrough of MH 160 & 162
26-May 8 8 - Supervision for ongoing rectification ( tail piece extension installation)
27-May 8 8 - Site walkthrough for the priority Model house with PM ariel
28-May 8 8 - Prepartion of Elevation inspection form
29-May 8 8 - Site Inspection for Elevator installation works (Template, Rail & Bracket)
30-May 8 8 - Site Inspection for Elevator installation works (Hoistway & Entrance equipment)
(Sunday) - -
1-Jun 8 8 - Site walkthrough for EE room inspection/Meeting with Mechanical Contractor
2-Jun 8 8 - Preparation of Fire protection Scope of works
3-Jun 8 8 - Preparation of Fire protection Scope of works
4-Jun 8 8 - Preparation of Mechanical (Ventilation) Scope of Works
5-Jun 8 8 - Preparation of Mechanical (Ventilation) Scope of Works
112 - 24 - - 136 - - - - - -

TOTAL 82.35% 0.00% 17.65% 0.00% 0.00% 100.00% #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
PERCENTAGE

Submitted By: JOMARI CHRIS BERON Noted By ENGR. ARIEL CANTIL


Name & Signature PDPM HEAD