This document is a timesheet for Jomari Chris Beron, a mechanical QC engineer at Santos Land Development Corporation, for May and June. It shows Beron spent most of his time, 112 hours or 82.35% of his total hours, supervising elevator installation works like service car installation, landing door installation, and machine room equipment installation. He also spent 24 hours or 17.65% of his time supervising rectification works and walkthroughs of model houses. The timesheet provides details of Beron's daily activities and tasks performed during this period which involved inspection, supervision, preparation of scopes of works, and meetings with contractors regarding ongoing construction projects.
This document is a timesheet for Jomari Chris Beron, a mechanical QC engineer at Santos Land Development Corporation, for May and June. It shows Beron spent most of his time, 112 hours or 82.35% of his total hours, supervising elevator installation works like service car installation, landing door installation, and machine room equipment installation. He also spent 24 hours or 17.65% of his time supervising rectification works and walkthroughs of model houses. The timesheet provides details of Beron's daily activities and tasks performed during this period which involved inspection, supervision, preparation of scopes of works, and meetings with contractors regarding ongoing construction projects.
This document is a timesheet for Jomari Chris Beron, a mechanical QC engineer at Santos Land Development Corporation, for May and June. It shows Beron spent most of his time, 112 hours or 82.35% of his total hours, supervising elevator installation works like service car installation, landing door installation, and machine room equipment installation. He also spent 24 hours or 17.65% of his time supervising rectification works and walkthroughs of model houses. The timesheet provides details of Beron's daily activities and tasks performed during this period which involved inspection, supervision, preparation of scopes of works, and meetings with contractors regarding ongoing construction projects.
Manpower Requirement JOMARI CHRIS BERON (Mechanical QC Engineer) MONTH OF MAY-JUNE DAILY WORK LOGSHEET OVERTIME ACTIVITY / TASK PERFORMED Date (dd/mm) Ivory FHR Housing Syntek DMO TOTAL (hrs) Ivory FHR Housing Syntek DMO TOTAL (hrs)
18-May 8 8 - Site Supervision for Elevator Works - Service Car Installation
19-May 8 8 - Site Supervision for Elevator Works - Service Car & Landing door Installation 20-May 8 8 - Site Supervision for EE room Painting, Wall Buffing & Floor Tapping works 21-May 8 8 - Site Supervision for Elevator works (Machine room equipment installation) 22-May 8 8 - Site Supervision for Elevator works - Hoistway Rope and Counterweight Inst. 23-May 8 8 - Site walkthrough in preparation for Elevator inspection (Sunday) - - 25-May 8 8 - Supervision and walkthrough of MH 160 & 162 26-May 8 8 - Supervision for ongoing rectification ( tail piece extension installation) 27-May 8 8 - Site walkthrough for the priority Model house with PM ariel 28-May 8 8 - Prepartion of Elevation inspection form 29-May 8 8 - Site Inspection for Elevator installation works (Template, Rail & Bracket) 30-May 8 8 - Site Inspection for Elevator installation works (Hoistway & Entrance equipment) (Sunday) - - 1-Jun 8 8 - Site walkthrough for EE room inspection/Meeting with Mechanical Contractor 2-Jun 8 8 - Preparation of Fire protection Scope of works 3-Jun 8 8 - Preparation of Fire protection Scope of works 4-Jun 8 8 - Preparation of Mechanical (Ventilation) Scope of Works 5-Jun 8 8 - Preparation of Mechanical (Ventilation) Scope of Works 112 - 24 - - 136 - - - - - -