Professional Documents
Culture Documents
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/29
Sign
First
19.03.2022 R0 Date
submission 20.08.2022 20.08.2022 20.08.2022 20.08.2022
Record of Revisions
Revision
Date Details of Revision Page Affected
No.
20.08.2022 R0 First Issue -
TATA PROJECTS LIMITED
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/29
1.0 PURPOSE:
The purpose of this work procedure is for “use for scissor lift for cleaning of Diaphragm
wall, maintenance of camera, LED and any other activities where scissor lift to be used”.
2.0 SCOPE:
The scope covers the work method for simple lifting procedure for work in scissor lift.
Strictly followed as per the manufacturer's Health and Safety recommendations for handling
and use of the materials. Ensure all involved personnel shall be aware of the same.
TATA PROJECTS LIMITED
TPL/UI/IKEA
URBAN INFRASTRUCTURE GMP/F&RM/MS/29
5.0 PROCDURE:
A) Preparation
Prior to start the work related to scissor lift make sure the following points
Donts list
9.0 ABBREVIATION:
F&RM Fleet & Resource Management
TBT Tool Box Talk
HIRA Hazard Identification & Risk Assessment