Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23
15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02
0 Children's Gourmet Cookbook 104 days Wed 01/02/23 Mon 26/06/23
2 1.1 Manuscript received 0 days Wed 01/02/23 Wed 01/02/23 1.2 Carole Poland
1.1 01/02
3 1.2 Content edit 25 days Wed 01/02/23 Tue 07/03/23 2 1.1 1.3 Carole Poland
Carole Poland
1.1 1.2 1.3
25 days
4 1.3 Handoff to Editorial 0 days Tue 07/03/23 Tue 07/03/23 3 1.2 2.1 Carole Poland
1.3 07/03
6 2.1 Organize manuscript for copyedit 5 days Wed 08/03/23 Tue 14/03/23 4 1.3 2.2,3.1[SS] Robin Wood
Robin Wood
1.3 2.1 2.2,3.1[SS]
5 days
7 2.2 Copyedit 20 days Wed 15/03/23 Tue 11/04/23 6 2.1 2.3,3.3[SF] Copyeditors
Copyeditors
2.1 2.2 2.3,3.3[SF]
20 days
8 2.3 Copyedit incorp 5 days Wed 12/04/23 Tue 18/04/23 7 2.2 2.4 Robin Wood
Robin Wood
2.2 2.3 2.4
5 days
9 2.4 Handoff to Production 0 days Tue 18/04/23 Tue 18/04/23 8 2.3 4.1 Robin Wood
2.4 18/04
10 3 Design and Production 20 days Wed 08/03/23 Tue 04/04/23 5SS 2[SS] 4
11 3.1 Cover design 5 days Wed 08/03/23 Tue 14/03/23 6SS 2.1[SS] 3.2 William Flash
William Flash
2.1[SS] 3.1 3.2
5 days
12 3.2 Set pages 10 days Wed 15/03/23 Tue 28/03/23 11 3.1 3.3[SS] Robin Wood,Katie
Jordan
Robin Wood,Katie Jordan
3.1 3.2 3.3[SS]
10 days
13 3.3 Interior illustration design 15 days Wed 15/03/23 Tue 04/04/23 12SS,7SF
3.2[SS],2.2[SF] William Flash
William Flash
3.2[SS],2.2[SF] 3.3
15 days
15 4.1 Proofread and index 10 days Wed 19/04/23 Tue 02/05/23 9 2.4 4.2 John Evans,Katie
Jordan
John Evans,Katie Jordan
2.4 4.1 4.2
10 days
16 4.2 Incorporate 1st Pages review 5 days Wed 03/05/23 Tue 09/05/23 15 4.1 4.3 Carole Poland
Carole Poland
4.1 4.2 4.3
5 days
17 4.3 Send proofed pages to Production 0 days Tue 09/05/23 Tue 09/05/23 16 4.2 4.4 Robin Wood
4.3 09/05
18 4.4 Enter page corrections and index 5 days Wed 10/05/23 Tue 16/05/23 17 4.3 5.1 Katie Jordan,Robin
Wood
Katie Jordan,Robin Wood
4.3 4.4 5.1
5 days
20 5.1 Send to color house 1 day Wed 17/05/23 Wed 17/05/23 18 4.4 5.2 Carole Poland
Carole Poland
4.4 5.15.2
1 day
21 5.2 Generate proofs 5 days Thu 18/05/23 Wed 24/05/23 20 5.1 5.3[FS+3 Color Setting Services
days]
Color Setting Services
5.1 5.2 5.3[FS+3 days]
5 days
22 5.3 Print and ship 20 days Tue 30/05/23 Mon 26/06/23 21FS+35.2[FS+3 Printing Service
days days]
Printing Service
5.2[FS+3 days] 5.3
20 days
Project: Children's Gourmet Co Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Mon 08/06/20 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress