Goverment of Nepal

National Reconstruciton Authority


Central Level Project Implementation Unit (CLPIU)
Babarmahal, kathmandu
Abstract of Cost

Project :- Conservation and reconstruction of World Heritage site Changunarayan Temple Complex (Sankhadaha reconstruction
project)
Location: Changunaryan, Bhaktapur
Rate with
S.N. Description Unit Quantity Amount Remarks
OH
A CIVIL WORK :-
1 Excavation for access road Cum 50.000 42.26 2,113.00

2 Excavation for Gabion Wall Cum 250 696.48 174,120.00

Supplying of Machine Made hexagonal mesh type 100mm


x 120 mm Gabion boxes / mattresses with diapharagms,
with binding wire 12 swg, mesh wire 10 swg and selvedged
wire 8 swg , including rolling, cutting and weaving ;
assembling Gabion boxes mattresses, palcing in position Ktm Road
3 Cum 334 5,521.52 1,844,187.68
including stretching, forming compartments; tying with Rate
bracing wires and tie wires; tying down the lid complete;
and providing and filling stone / boulder in gabion boxes /
mattresses etc. including dressing, beding, bonding and all
transporation as per specification.

Total 2,020,420.68
Overhead less @ 15% 263,257.52
Total 1,757,163.16
Contribution less @ 10% 175,716.32
Grand Total 1,581,446.84
Goverment of Nepal
National Reconstruciton Authority
Central Level Project Implementation Unit (CLPIU)
Babarmahal, kathmandu
Detailed Measurement Sheet

Project :- Conservation and reconstruction of World Heritage site Changunarayan Temple Complex (Sankhadaha reconstruction
project)
Location: Changunaryan, Bhaktapur
Measurement
S.N. Description No Quantity Remarks
Length Total L. Breadth Height
A CIVIL WORK :-
1.0 Excavation for access road 1.00 50.00 50.00 Cum
2 Excavation for Gabion Wall
Wall1 1 21.00 21.00 3.00 2.000 126.000
Wall 2 -
section 1 1 8.00 8.00 2.50 2.000 40.000
section 2 1 6.00 6.00 3.00 3.000 54.000
Wall3 1 7.00 7.00 3.00 1.000 21.000
Wall4 1 6.00 6.00 3.00 0.500 9.000
Total 250.000 Cum
Gabion Wall Work
3

Supplying of Machine Made hexagonal mesh type 100mm x


120 mm Gabion boxes / mattresses with diapharagms, with
binding wire 12 swg, mesh wire 10 swg and selvedged wire
8 swg , including rolling, cutting and weaving ; assembling
Gabion boxes mattresses, palcing in position including
stretching, forming compartments; tying with bracing wires
and tie wires; tying down the lid complete; and providing
and filling stone / boulder in gabion boxes / mattresses etc.
including dressing, beding, bonding and all transporation as
per specification.

Wall1
Step 1 1 21.00 21.00 3.00 1.000 63.000
Step 2 1 21.00 21.00 2.50 1.000 52.500
Wall2 -
Step 1 1 6.00 6.00 3.00 1.000 18.000
Step 2 1 14.00 14.00 2.50 1.000 35.000
Step 3 1 14.00 14.00 2.00 1.000 28.000
Step 4 1 14.00 14.00 1.50 1.000 21.000
Wall 3 -
Step 1 1 7.00 7.00 3.00 1.000 21.000
Step 2 1 7.00 7.00 2.00 1.000 14.000
Step 3 1 7.00 7.00 1.50 1.000 10.500
Wall 4 -
Step 1 1 6.00 6.00 3.00 1.000 18.000
Step 2 1 6.00 6.00 2.00 1.000 12.000
Measurement
S.N. Description No Quantity Remarks
Length Total L. Breadth Height
Step 3 1 6.00 6.00 1.00 1.000 6.000
Wall 5 -
Step 1 1 8.00 8.00 2.00 1.000 16.000
Step 2 1 8.00 8.00 2.00 1.000 16.000
extra 1 3.00 3.00 1.00 1.000 3.000
Total 334.000 Cum
Goverment of Nepal
National Reconstruciton Authority
Central Level Project Implementation Unit (CLPIU)
Babarmahal, kathmandu
Abstract of Cost

Project :- Conservation and reconstruction of World Heritage site Changunarayan Temple Complex (Step construction Project)
Location: Changunaryan, Bhaktapur

S.N. Description Unit Quantity Rate Amount Remarks

A CIVIL WORK :-

Earthwork in excavation for foundation in all


kinds of soil including timbering, dressing of
sides, ramming of bottom, stacking of excavated
1 Cum 23.35 696.48 16,265.45
material etc. all complete as per specification,
drawing and instruction of the Engineer.

Earth filling in 150 mm thick layer including the


supply of filling materials, watering, ramming
2 Cum 2.91 886.70 2,581.50
including 1.5m lift and 30 m lead all complete as
per drawing specification and instructions.

Earth filling in 150 mm thick layerexcluding the


supply of filling materials, watering, ramming Earth obtained
3 Cum 23.35 424.40 9,911.35
including 1.5m lift and 30 m lead all complete as from excavation
per drawing specification and instructions.

levels all complete as per specification and


instruction .
4 663,568.88
Sqm 66.75 9,940.66

Providing and laying plain cement concrete (1:2:4)


using ordinary portland cement(OPC), sand and
5 coarse aggregates including setting out, mixing, 57,084.08
compacting, curing and finishing etc. to approved
level, lines and dimension all complete as per
specification, drawing and instruction of the
Engineer. Cum 3.73 15,301.07

Sand Filling including setting out, compacting and


6 finishing etc. to approved level, lines and dimension 63,620.63
all complete as per specification, drawing and
instruction of the Engineer. Cum 17.01 3,740.19

Rubble masonry in cement sand mortar (1:4) , in


7 perfect line and level including cost of scaffolding, 647,557.10
packing the joints, raking the joints and curing the
work at least 7 days in all types and thickness of
wall as per specification, drawing and instruction of
Engineer, all complete.
Cum 46.03 14,069.64

8 Ashlar Stone Masonry wall above Stair in 1:4 81,289.67


without stone Cum 7.65 10,630.27
converted to sqm
9 Providing Machine made ashlar stone for wall 114,354.58 from material rate of
above stair Sqm 76.47 1,495.42 Bhaktapur
Rs. 1125 per
10 808,940.25 Running Feet from
5" thickness flag stones of 1' width for steps Rm 219.23 3,690.00 Quotation
11 3" thickness flag stones for landings Sqm 113.400 2,260.27 256,314.62
S.N. Description Unit Quantity Rate Amount Remarks

Total 2,721,488.12
Overhead less @ 15% 324,051.80
Total 2,397,436.33
Contribution less @ 10% 239,743.63
Grand Total 2,157,692.69
Goverment of Nepal
National Reconstruciton Authority
Central Level Project Implementation Unit (CLPIU)
Babarmahal, kathmandu
Detailed Measurement Sheet

Project :- Conservation and reconstruction of World Heritage site Changunarayan Temple Complex (Step construction Project)
Location: Changunaryan, Bhaktapur
Measurement

S.N. Description No Quantity Remarks


Length Total L. Breadth Height

CIVIL WORK :-
A

Earthwork in excavation for foundation in


all kinds of soil including timbering,
dressing of sides, ramming of bottom,
stacking of excavated material etc. all
complete as per specification, drawing and
instruction of the Engineer.

Side Wall below Stair segment 1 2 45.73 91.450 0.30 0.300 8.231
Side Wall below Stair segment 2 2 18.00 36.000 0.60 0.300 6.480
check Wall 14 2.74 38.415 0.30 0.750 8.643
Total 23.354 Cum
Earth filling in 150 mm thick layer,
watering, ramming including 1.5m lift and
30 m lead all complete as per drawing
specification and instructions.

landing and steps 1 1 3.38 3.375 2.74 0.225 2.084


landing and steps 2 1 3.08 3.075 2.74 0.300 2.531
landing and steps 3 1 3.08 3.075 2.74 0.338 2.848
landing and steps 4 1 3.03 3.025 2.74 0.150 1.245
landing and steps 5 1 2.95 2.950 2.74 0.300 2.428
landing and steps 6 1 2.83 2.825 2.74 0.375 2.907
landing and steps 7 1 3.33 3.325 2.74 0.425 3.877
landing and steps 8 1 3.30 3.300 2.74 0.375 3.396
landing and steps 9 1 3.73 3.725 2.74 0.150 1.533
landing and steps 10 1 3.28 3.275 2.74 0.150 1.348
landing and steps 11 1 3.23 3.225 2.74 0.075 0.664
landing and steps 12 1 3.25 3.250 2.74 0.075 0.669
landing and steps 13 1 1.78 1.775 2.74 0.075 0.365
landing and steps 14 1 1.80 1.800 2.74 0.075 0.370
Total 26.265 Cum
150 mm stone soling in voids in perfect
line and levels all complete as per
specification and instruction .
Landings
landing 1 1 3.375 3.375 2.70 0.15 1.367
landing 2 1 3.075 3.075 2.70 0.15 1.245
landing 3 1 3.075 3.075 2.70 0.15 1.245
landing 4 1 3.025 3.025 2.70 0.15 1.225
landing 5 1 2.95 2.950 2.70 0.15 1.195
landing 6 1 2.825 2.825 2.70 0.15 1.144
Measurement

S.N. Description No Quantity Remarks


Length Total L. Breadth Height

landing 7 1 3.325 3.325 2.70 0.15 1.347


landing 8 1 3.3 3.300 2.70 0.15 1.337
landing 9 1 3.725 3.725 2.70 0.15 1.509
landing 10 1 3.275 3.275 2.70 0.15 1.326
landing 11 1 3.225 3.225 2.70 0.15 1.306
landing 12 1 3.25 3.250 2.70 0.15 1.316
landing 13 1 1.775 1.775 2.70 0.15 0.719
landing 14 1 1.8 1.800 2.70 0.15 0.729
Check Wall
Check wall 14 2.74 38.36 0.3 11.508
Side wall below starirs 2 63.725 127.45 0.3 38.235
Total 66.753 Sqm
Providing and laying plain cement concrete `
(1:2:4) using ordinary portland cement(OPC),
sand and coarse aggregates including setting
out, mixing, compacting, curing and finishing
etc. to approved level, lines and dimension all
complete as per specification, drawing and
instruction of the Engineer.

Check wall 14 2.74 38.36 0.3 0.075 0.863


Side wall below starirs 2 63.725 127.45 0.3 0.075 2.868
Total 3.731 Cum
Sand Filling including setting out, compacting
and finishing etc. to approved level, lines and
dimension all complete as per specification,
drawing and instruction of the Engineer.

Landings
landing 1 1 3.375 3.375 2.70 0.15 1.367
landing 2 1 3.075 3.075 2.70 0.15 1.245
landing 3 1 3.075 3.075 2.70 0.15 1.245
landing 4 1 3.025 3.025 2.70 0.15 1.225
landing 5 1 2.95 2.950 2.70 0.15 1.195
landing 6 1 2.825 2.825 2.70 0.15 1.144
landing 7 1 3.325 3.325 2.70 0.15 1.347
landing 8 1 3.3 3.300 2.70 0.15 1.337
landing 9 1 3.725 3.725 2.70 0.15 1.509
landing 10 1 3.275 3.275 2.70 0.15 1.326
landing 11 1 3.225 3.225 2.70 0.15 1.306
landing 12 1 3.25 3.250 2.70 0.15 1.316
landing 13 1 1.775 1.775 2.70 0.15 0.719
landing 14 1 1.8 1.800 2.70 0.15 0.729
Total 17.010 Cum
Measurement

S.N. Description No Quantity Remarks


Length Total L. Breadth Height

Rubble masonry in cement sand mortar (1:4) ,


in perfect line and level including cost of
scaffolding, packing the joints, raking the joints
and curing the work at least 7 days in all types
and thickness of wall as per specification,
drawing and instruction of Engineer, all
complete.

Side Wall below Stair segment 1 2 45.73 91.450 0.30 0.760 20.851
Side Wall below Stair segment 2 2 18.00 36.000 0.60 0.760 16.416
check Wall 14 2.74 38.415 0.30 0.760 8.759
Total 46.025 Cum
Ashlar masonry in cement sand mortar (1:4) in
perfect line and level including cost of
scaffolding, packing the joints, raking the joints
and curing the work at least 7 days in all types
and thickness of wall as per specification,
drawing and instruction of Engineer, all
complete.

wall on stair 2 63.725 127.45 0.3 0.2 7.647 Cum


Providing Machine made ashlar stone of 3"
thickness for wall above stair

machine made ashlar stones for wall above stair of 4 63.725 254.9 0.3
76.470 Sqm
3" thickness
Solid Stone in steps
5" thickness flag stones of 1' width for steps 79 2.78 219.225 219.225
Total 219.225 Rm
3" thickness flag stones for landings
landing 1 1 3.375 3.375 2.70 9.113
landing 2 1 3.075 3.075 2.70 8.303
landing 3 1 3.075 3.075 2.70 8.303
landing 4 1 3.025 3.025 2.70 8.168
landing 5 1 2.95 2.950 2.70 7.965
landing 6 1 2.825 2.825 2.70 7.628
landing 7 1 3.325 3.325 2.70 8.978
landing 8 1 3.3 3.300 2.70 8.910
landing 9 1 3.725 3.725 2.70 10.058
landing 10 1 3.275 3.275 2.70 8.843
landing 11 1 3.225 3.225 2.70 8.708
landing 12 1 3.25 3.250 2.70 8.775
landing 13 1 1.775 1.775 2.70 4.793
landing 14 1 1.8 1.800 2.70 4.860
Total 113.400 Sqm
Natio
Cental Level P

बिलको क्रम संख्या: IPC-01


आयोजनाको नाम : Project :- Conservation and reconstruction of World Heritage site Changunarayan Temple Complex (Ste
उपभोक्ता समिति को नाम: sankhadaha

अघिल्लो भुक्तानी बिलको क्रम संख्या: N/A


अघिल्लो भुक्तानीको भौ.नं.: N/A

आईटम
कामको विवरण इकाई सम्झौता परिमाण

१ २ ३ ४

Earthwork in excavation for foundation in all kinds of soil including


timbering, dressing of sides, ramming of bottom, stacking of excavated
1 material etc. all complete as per specification, drawing and instruction Cum 112.28
of the Engineer.

Earth filling in 150 mm thick layer including the supply of filling


2 materials, watering, ramming including 1.5m lift and 30 m lead all Cum 12.74
complete as per drawing specification and instructions.
Earth filling in 150 mm thick layerexcluding the supply of filling
3 materials, watering, ramming including 1.5m lift and 30 m lead all Cum 112.28
complete as per drawing specification and instructions.
150 mm stone soling in voids in perfect line and levels all complete as
4 per specification and instruction . Sqm 371.33

Providing and laying plain cement concrete (1:2:4) using ordinary


portland cement(OPC), sand and coarse aggregates including setting
5 out, mixing, compacting, curing and finishing etc. to approved level, Cum 21.70
lines and dimension all complete as per specification, drawing and
instruction of the Engineer.

Sand Filling including setting out, compacting and finishing etc. to


6 approved level, lines and dimension all complete as per specification, Cum 82.01
drawing and instruction of the Engineer.
Rubble masonry in cement sand mortar (1:4) , in perfect line and level
including cost of scaffolding, packing the joints, raking the joints and
7 curing the work at least 7 days in all types and thickness of wall as per Cum 228.14
specification, drawing and instruction of Engineer, all complete.

8 Ashlar Stone Masonry wall above Stair in 1:4 without stone Cum 48.00
9 Providing 50mm lime surkhi layer on top of the side wall above the Cum 12.00
steps
Providing flush pointing on steps of stone paved surfaces with good
10 Sqm 1,104.35
finishing as per instruction of engineer.
11 Providing Machine made ashlar stone for wall above stair Sqm 480.00
12 5" thickness flag stones of 1' width for steps Rm 888.00
13 3" thickness flag stones for landings Sqm 546.75
Sub Total (A+B+C+D)=E
VAT amount @ 13%
Grand Total amount

ईन्जिनियर

यो बिल बमोजिम जम्मा रु


कट्टा गर्नुपर्ने रु:
ग. मेशीन औजारको बहाल: -

पेश गर्नेको सही:


दर्जा:
जम्मा रु:…………………………………………………..अक्षररुपी:………………………………………………………………………………
बाट प्राप्त भएको भनी सही गर्ने ठेके दारको सही:
Government of Nepal
National Reconstruction Authority
Cental Level Project Implementation Unit (Building)
Babarmahal, Kathmandu

ठेक्का सम्बन्धि बिल


n Temple Complex (Step construction Project)

अद्यावधिक काम भएको अघिल्लो बिलमा चढेको


परिमाण दर जम्मा मूल्य परिमाण जम्मा मूल्य
५ ६ ७ ८ ९

23.35 696.48 16,265.45 - -

2.91 886.70 2,581.50 - -

23.35 424.40 9,911.35 - -

66.75 9,940.66 663,568.88 - -

3.73 15,301.07 57,084.08 - -

17.01 3,740.19 63,620.63 - -


46.03 14,069.64 647,557.10 - -

7.65 10,630.27 81,289.67 - -


10,891.30 - - -

190.73 - - -
76.47 1,495.42 114,354.58 - -
219.23 3,690.00 808,940.25 - -
113.40 2,260.27 256,314.62 - -

- -
- -

ईन्जिनियर

अघिल्लो बिलबाट भुक्तानी भएको रु:


क. पेश्की रु: -
घ. आयकर रु:

जाँच गर्नेको सही:


दर्जा:
………………………………………………………………………………………………………………………………………………………………………….
कार्यारम्भ आदेश मिति:
काम सम्पन्न गर्नु पर्ने मिति:
काम सम्पन्न भएको मिति:
भुक्तानी भौचर नं.:
भुक्तानी मिति:
नापी किताब नं. को पृष्ठ नं.:

हाल भएको काम कै फियत


परिमाण जम्मा मूल्य
१० ११ १२

23.35 16,265.45

2.91 2,581.50

23.35 9,911.35

66.75 663,568.88

3.73 57,084.08

17.01 63,620.63
46.03 647,557.10

7.65 81,289.67
- -

- -
76.47 114,354.58
219.23 808,940.25
113.40 256,314.62
2,721,488.12
353,793.46
3,075,281.58

ठेके दारको सही

बाँकी दिनुपर्ने रु: -


ख. मालसामानको मोल रु: -
ङ. धरौटी रु:
खुद दिनुपर्ने रु: -

स्वीकृ त गर्नेको सही:


दर्जा:
को चे.नं.:………………………………………………………..