Basic Rules
1. Scaffolds must be erected or dismantled in accordance with WCB Regulations and by qualified workers only.
2. Scaffold components must be inspected prior to being assembled. Defective parts must not
be used.
3. Once a scaffold has been erected, the supervisor must inspect it prior to allowing workers to use it.
1. The purpose of screw jacks is to level the scaffold 1. Frames shall be erected in accordance with the
system, so that: manufacturer’s recommendations and WCB regulations.
a. the frame is plumb
b. the work platform is level Cross Braces
© Scaffold Depot - All Rights Reserved. SD Scaffold Erection Procedure and Guidelines | Page - 2
SCAFFOLDS FROM THE BOTTOM UP
Guardrail Systems: Work Platforms (Decks and Plank Type):
The purpose of the guardrail system is to prevent The work platform provides a worker with a surface from
workers from falling from scaffold work platforms. which to work. The work platform must comply with the
• Guardrails must be used if the platform height is following minimum requirements:
10 feet or more.
• must consist of lumber or manufactured planks
• The guardrail system consists of:
a. guardrail posts, which are engineered placed side by side to provide a work surface with
specifically for guardrail systems; a minimum nominal width of 50cm (20 inches).
b. top rails located 42 inches above the work • as far as possible completely cover the area
platform; between front and rear vertical supports of the
c. mid rails located at midpoint between the rear guardrail, and in no case leave more than one
work platform and top rail; opening in a work platform greater than 10 inches.
d. toe-boards There are two types of work platforms:
© Scaffold Depot - All Rights Reserved. SD Scaffold Erection Procedure and Guidelines | Page - 3
SETTING UP & DISMANTLING SCAFFOLDS
Pre-set inspection Components Required
© Scaffold Depot - All Rights Reserved. SD Scaffold Erection Procedure and Guidelines | Page - 4
STEP BY STEP SCAFFOLD ASSEMBLY
Note: Every component must be inspected prior to installation, by an experienced employee.
© Scaffold Depot - All Rights Reserved. SD Scaffold Erection Procedure and Guidelines | Page - 5
SAFE PRACTICES
DO DON’T
• inspect every component piece. Tag defective parts • do not mix-match components, as it may affect the
and replace them immediately. structural integrity of the scaffold
• ensure that components are uniform. This means, • do not use defective parts, even if slightly damaged
components are of the same type and from the same
manufacturer • do not leave scaffolds unattended, particularly around
schools/ parks
• inspect scaffolds frequently and after every break,
particularly locking devices • do not wire in place of locking devices
• ensure that each wheel is locked (has brakes on) • do not over extend screw jacks
before climbing the scaffold • never climb or stand on cross braces or guardrails, as
• use a ladder to climb the scaffold. Keep a 3 point you may fall over or bend them
contact while climbing • never use makeshift (bricks, boxes, scrap lumber, etc.)
• complete the work platform before working on the or ladders on a work platform. If you need to reach a
next level higher elevation install another scaffold level
• use a rope to hoist tools, materials or equipment onto • never exceed 3 times the smallest base of a scaffold
the work platform • never reset or hang materials or equipment from the
• keep the work platform clean and free of obstacles and guardrails
slipping or tripping hazards at all times • never ride on a scaffold. Get down, help relocating to
• remove or firmly secure materials and equipment the desired location and climb up again
before moving scaffolds • when cleaning the work platform, never throw leftover
• when dismantling, remove jammed or rusted material or scraps to the ground. Use a bucket and hoist
components carefully. Tugging or pulling of stuck parts down
may tip the scaffold over or damage the components • never jump onto decks or planks
• when moving a scaffold always push toward the
bottom
© Scaffold Depot - All Rights Reserved. SD Scaffold Erection Procedure and Guidelines | Page - 6
SCAFFOLD INSPECTION CHECK LIST
1. Inspect the scaffold on which you are to work to make certain they are safe and that they remain safe.
2. Any damage to scaffolds, false work or other supporting structures must be reported promptly to the foreman.
3. Scaffolds planks are to be carefully selected, and made secure to prevent slipping by using cleats, and wiring in
open windy conditions. Planks must extend no less than 6” and no more than 12” beyond the center of the sup-
port.
4. As far as safety is concerned there is no such thing as a “temporary scaffold”. Build all scaffolds with the safety in
mind, as the “temporary scaffold” many times is used for longer than originally anticipated.
5. Never overload a scaffold. All scaffolds should be designed and built to take the maximum material load that may
be placed on them as well as the weight of the workmen.
6. Safe access and egress to all scaffolds must be accomplished via properly secured ladders or stairway systems.
7. Guardrail, intermediate rail and toe boards must be installed on all scaffolds and/ or working platforms over 10ft
high as per O.H.&S regulations 13.21 (1)
8, All scaffolds must be adequately supported in both directions by a system of diagonal cross braces.
9. Scaffold towers must be secured at vertical intervals not more than 15 feet and horizontally at not more than 21
feet.
10. Scaffold platforms must be a minimum 19” wide, but where more than 8” from the ground or floor the platform
must be full width of the scaffold.
11. All components of a rolling scaffold must be properly secured or locked together.
12. All scaffold wheels must have proper braking devices locked when scaffold is not being moved.
13. No rolling tower scaffold shall be higher than three times its least lateral dimension including outrigger when
used.
14. Rolling towers are not to be moved with workers on top
15. Use adjusting screwjacks instead of blocking to adjust to uneven grade conditions.
16. Plumb and level all scaffolds as the erection proceeds. Do not force braces to fit.
© 2011 Scaffold Depot - All Rights Reserved. SD Erection Procedure and Guidelines | Page - 7
SCAFFOLD INSPECTION CHECK LIST Yes No
7. Tower tied to rigid support horizontally every 20’ and vertically every 15’
8. Free standing tower scaffold steadied with guy wire every 30’ in height
9. Platform planking pleated on underside at each end with wood or angle iron
13 . Safety cage needed around vertical ladder if it is more than 30’ in height
14. Perimeter handrail 36” to 44” high with a mid rail all around work platforms.
15. Separate roped off or hand line in place at all platforms to raise and lower tools or materials.
16. Warning devices/ signs provided if erected over walkways or roadways (flashing lights, reflec-
tive tape streamers, or area is roped off )
17. Minimum clearance from overhead power lines maintained as per occupational health and
safety regulations.
18. Rolling scaffold wheel brakes locked and outriggers extended to maintain maximum height
of 3 times the smallest base dimensions.