Plot No. 158, I.D.A. , BOLLARAM, MEDAK DIST., HYDERABAD, ANDHRA PRADESH – 502 325, INDIA.
PURCHASE ORDER
2017-18 / P.O. No. 095.
Dated 05.02.2018.
To,
Mr. Pamu Babi,
M/s Bhavani Engineering Services,
Indrapalem,
KAKINADA.
Dear Sirs,
With discuss to you offered dated 04.02.18 and discussions we had with you for Fabrication and Erection
works site at Bay – 2, Panel Shed, Thermal Systems (Hyderabad) Pvt. Ltd., Bollaram. We are pleased to place
Purchase Order on you for Various Structural and Boiler Fabrication Works at our Site With the following
enumerated Terms & Conditions.
Page No. 2
Payment: Payment will be made against submissions of running bills in original after duly checked & singed by
Engineer as per actual measurements of work done.
Consumables: All Consumables required like Electrodes, gases for completion of above works is completely
under your scope.
All necessary tools and tackles required for the above works in your scope.
All Infrastructure materials like steel, pipes, Flanges, Bends, flats, Water and Power our Scope.
You have to make your own arrangements for accommodation, local conveyance and food for your staff and
workers.
Authorized Signatory
SERVICE WORK ORDER
Ref: T.S. / 2017-18 / S.W.O. No. 194.
Work Order Starting Date: 01.01.2018.
Work Order Ending Date: 31.12.2018.
To,
Mr. PAMU BABI,
M/s Bhavani Engineering Services,
Indrapalem,
KAKINADA.
Dear Sirs,
With discuss to you offered dated 29.12.2017 and discussions we had with you for Fabrication
and Erection works site at all Sheds, Boilers Making Shed, Thermal Systems (Hyderabad) Pvt. Ltd., Bollaram. We
are pleased to place Service Order on you for Annual maintenance various works Means Pipelines, Storage
Tanks, Structural and Boiler Fabrication Works at our Site With the following enumerated Terms & Conditions.
1. M.S. Storage Tanks Fabrication and Erection. 1,000 M.T. 15,000-00 Per Ton
(Approx)
2. M.S. Pipe line Fabrication and Fixing. 10,000 Mtr. 110-00 Inch Mtr.
(Approx)
3. Bends, flanges, Nipples, Reducers Fixing and
Welding. Each 110-00 Inch Mtr.
5. M.S. Structure Fabrication and Erection 500 M.T. 17,000-00 Per Ton
(Approx)
6. Dismantling and Shifting to Scrap Yard Double rate for above rates.
Cont…..
Page No. 2
Payment: Payment will be made against submissions of running bills in original after duly checked & singed by
Engineer as per actual measurements of work done.
Only Completion of the Fabrication considered 60% of the above rates.
Consumables: All Consumables required like Electrodes, gases for completion of above works is completely
under your scope.
All necessary tools and tackles required for the above works in your scope.
All Infrastructure materials like steel, pipes, Flanges, Bends, flats, Water and Power our Scope.
You have to make your own arrangements for accommodation, local conveyance and food for your staff and
workers.