Protocol for a DFO80 Installation Supplier Name: Middle East Development Company Ltd Customer PO# TINS-PO-045-2018 Customer: Al Mabani General Contractors Co. Date: 1st Mar, 2020 Project Location: Welding Annexe (TINS Studies Project Dammam) Equipment Brand Name: Nederman (Sweden / EU)
S.No. Items to Check Inspection Remarks
1 Nederman DFO 80 Filter Installation 2 Filter cleaning equipment 3 Installation of compressed air and electricity 4 The function of the safety switch installation 5 The rotation direction of the motor by test start of unit. 6 Fan Inverter Installation 7 Fan NCF 80/20 380V 7,5kW 60Hz Installation 8 Fume Extractor L=3m Original Arm 9 Wall bracket for extraction arm installation 10 G.I round duct installation.