A Approved No Comments
For CECO - Quality Reviewed with Document needs to be
B
comment resubmitted
For Allied Furnace For DCM Shriram
Approved / Reviewed
DATE
DATE
SIGN
Page 1 of 5
SHRI SAMARTH FABRICATION LLP
Hydro Test Procedure
Index
Section Contents
1 Scope
2 Reference standard
3 Responsibilities
4 Test Preparation
5 Test Medium
6 Test Temperature
7 Test Pressure
8 Procedure
9 Inspection
11 Inspection Report
Page 2 of 5
SHRI SAMARTH FABRICATION LLP
Hydro Test Procedure
1. Scope
2. Reference documents
Approved drawing.
Approved ITP
3. Responsibilities
In the absence of PE, the Production Manager (PM) and in absence of QCE, the Quality
Control Manager will carry out the above respective functions.
4. Test Preparation
The QCM shall review the ITP and accompanying documents for verification of
completeness of welding, and NDT prior to taking the Job for Hydro testing.
ii. External surface of equipment, including welded faces, shall be cleaned of any
oil,grease, or other contaminants.
5. Test Medium
Water shall be used as test medium.
6. Test Temperature
Ambient.
7. Test Pressure
Test pressure shall be maintained as per approved drawing.
Page 3 of 5
SHRI SAMARTH FABRICATION LLP
Hydro Test Procedure
8. Procedure
ii. Check the leakage at the weld joint. If there is leakage at the weld joint,
9. Inspection
Page 4 of 5
SHRI SAMARTH FABRICATION LLP
Hydro Test Procedure
Client : Equipment :
Temperature :
Medium : Air
Pressure Test Record
Duration : minutes
Make :
Range : kg/cm2
Calibration Report No.
& Date of calibration
Remarks if any :
Test Result :
Witnessed by TPI
Page 5 of 5