DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
1. Table of Contents
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 2 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
1. TABLE OF CONTENTS................................................................................................................. 3
3.0 REFERENCES................................................................................................................................ 4
4.1 Summary....................................................................................................4
4.2 Methodology................................................................................................4
4.3 Permit, Access, Approval and Site Preparation....................................................4
4.4 Loading & unloading of office containers, Installation of office containers.................5
4.5 WORK EXECUTION METHOD...........................................................................5
5.0 NATURE OF WORK....................................................................................................................... 6
8.1 PERSONNEL.................................................................................................................................. 7
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 3 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
4.1 Summary
This MS will be outlining the sequences and methods of works intended for loading of
containers and dismantling and remove the waste of Porto cabin from the compound.
4.2 Methodology
Step Description
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 4 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
c) Survey and measurement should be taken and marked, loading, dismantling of Porto cabins
and removal of dismantled items from the compound (waste).
d) Cable detection must be carried out to make sure no underground services.
e) Foreman & Equipment operator will check & plan the travel routes prior to demobilization.
Ensure travel routes & access to the jobsite is in good condition and free from obstruction.
f) Unauthorized person are not allowed in the work area.
g) Workers shall wear appropriate PPE for the task.
h) Supervisor/Foreman shall be present at all time during loading activity.
a) Forklift used for lifting container shall have valid competency certificate.
b) Site supervisor will conduct tool box and brief the safe loading operation,
c) Use the forklift truck only for the purpose for which it was designed.
d) Before starting the loading ‘lifting work, the assigned people must wear proper PPE and
adequate safety procedure must be implemented.
e) Barricade the marked location scheduled for loading and lifting operation with safety signage.
f) To Provide safe work during demobilization of office containers, there are consideration which
take according to weight of the container.
g) The site supervisor should prepare the site area to be clean and clear from obstruction.
h) Safety equipment must always present and ready for immediate use.
i) The weight of container is 5 Tonnes.
j)
k)
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 5 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
a) Site supervisor will conduct tool box and brief the safe working of operation
b) Dismantle the old/damage Porto cabin with proper tools.
c) The safe removal of all existing structures such as walls, fences, drainage, water pipes
and cables.
d) All the paper, wood, concrete waste shall be removed from site
e) Safety equipment must always present and ready for immediate use.
Cabin Waste Removal - Permit shall obtain and copy must be available at site when
the activities is being done.
Loading of waste material to pick-up must observed and mentioned.
Working During Summer Time – Working direct exposed to sunlight during summer
season shall not be permitted as directed by the Qatar Labor law.
Ensure to provide proper sun shades, drinking water at site.
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 6 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
1.1
9.1 PERSONNEL
Supervisor / Technicians
Ensure that all activities to be done in accordance with the approved MS,
Coordinate and ensure with various levels of people at site to have a safe Working place.
To ensure that the work is carried out with minimum impact to the environment
Supervisor shall monitor site installation, conduct tool box meeting and discuss to crew
member the hazard of the activities to be done.
To contact client associated personnel in case of an accident or injury.
To provide safety induction program to workers, prior access to site
Inspect all tools before use and on a daily basis
Comply with work instructions and permits.
Keeping the work area in an orderly condition.
Wear PPE provided to them and inspect it daily.
Supervisor also ensure that loading and dismantling cabin shall be as per MS,
Ensure that all dangerous activities are carried out under Permit to Work Procedure.
Forklift Operators
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 7 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
Signalmen
Ensure or verify that the load is properly secured in fork before he gives a clear
Signal to the forklift operator to lift the container.
Give correct and clear signals to guide the forklift operator in the maneuver of the load
safely to the trailer.
Workers
Accepting individual responsibility for their own safe behavior as well as
sharing responsibility with their fellow workers and line supervision to look out for their own
as well as their co-workers.
Work in a safe manner at all times.
Complying with HSE requirements which apply to an individual’s work activities.
Keeping the work area in an orderly condition.
Wear PPE provided to them and inspect it daily.
Comply with work instructions and permits.
Attend daily tool box/pre-task meetings
Inspect all tools before use and on a daily basis.
8.1
8.2.1 Equipment’s
10Tonne Forklift
Trailer
40Ft Container.
8.2.2 Tools
Page 8 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
Safety helmets.
Safety footwear.
High visibility vests.
Safety Glasses.
PTW QP
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 9 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING
OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
The printed version of this document is a non-controlled version. The current version is available in the software tool
for documentation management.
Page 10 of 14
11.0 RISK ASSESSMENT (RA)
0 No injury 0 Has not occurred in last two years RISK CLASSIFICATION RISK VALUE
Minor laceration, wound (first aid
2 2 Occurs very seldom LOW 0---6
case)
More severe injury medical
4 4 Occurs occasionally MEDIUM 6---16
attention
Serious injuries, broken bones,
8 8 Occurs often HIGH 16---32
amputation etc
10 Loss of life / fatality 10 Could / has happened CRITICAL 32---40
C POTENTIAL DAMAGE / LOSS D ENVIRONMENT ACTION REQUIRED
Supervision, training, certification, method/risk
Good
0 No damage, minimal costs (QAR) 0 No effect LOW assessments, safe work procedures training,
instruction.
toolbox talks.
Competent supervision, training certification, Change
2 Minor damage, small costs (QAR) 2 Minor effect MEDIUM method/risk assessments, safe work method,
Spillage, noise, procedures training, toolbox talks. mitigate
water, dust/ Competent supervision, training certification, Change
Med damage, stoppage (On site Serious effect
4 4 vapours/ faun and HIGH method/risk assessments, safe work method,
repair) medium cost (QAR) (Short term)
flora procedures training, toolbox talks. mitigate.
Very serious
Close competent supervision, training Intolerable,
8 More serious damage 8 effect (Long
certification, method/risk assessments, safe change
Term) CRITICAL
work procedures, PJO’s, work permits, method,
Severe damage, long term Catastrophic
10 10 training, and toolbox talks. transfer risk.
stoppage, high costs effect
The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
Whom / Additional
Hazards Identified A B C D R Controls Responsibility R
What Affected Controls
Access to Accident with *Workers 4 1 2 0 8 Proper Supervision Site Engineer 2
working spot moving vehicle *Staff Provide the safe access to the site. /Foreman
area. worker and *Assistant Before starting the work tool box should be
staff. conducted.
Proper PPE should be worn at the site.
Moving vehicle Adequate Fatality 2 2 4 0 16 Provide the safety barricades as per site Supervising & Site Engineer/ 4
equipment Access Egress. serious\Minor requirement. monitoring Supervisor
injuries Apply appropriate signage and pedestrian
control.
Keep Area clean & clear of obstacles.
Maintain good housekeeping (remove
debris, trip hazards, site tidiness.
Flag man should be available.
Accessing the Accident Workers 2 1 4 0 8 Provide safe and egress to work area Supervision & Site Engineer/ 4
trailer vehicle to With moving Trailer container loaded vehicle should be in frequent monitoring Supervisor
site location vehicle worker good condition.
and staff Flag man should be available.
Environment Vehicle driver valid license should be
applicable.
Authorized person should be operate the
trailer.
Mobile phone using while driving is
prohibited.
Comply with speed limit of 15km per hour
Working in site. Physical injury workers 1 2 4 0 8 Before starting the work tool box should be More awareness Surveyor 5
of the person conducted. should be given in Site Engineer/
Don’t park the vehicle in front of the form of trainings and Supervisor
The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.
Page 12 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
Usage of Minor injury of Workers / Staff 1 2 2 0 4 Use proper PPE safety helmet, & reflective Supervision Engineer/ 4
proper PPE the person. jacket. supervisor
and signage Do not enter unauthorized person signage
boards. board.
Advance warning sign should be provided.
Usage of Obstruction to Workers / 4 2 2 0 16 Clear access shall be marked and sign Adequate training Project 8
mobile crane. the walk way / property boards shall be kept prior. should be given Manger/
major injury by Damage Check the mobile crane condition. Engineer/
the person. Vehicle third party certificate. supervisor
Depends upon the container use the sling.
Vehicle condition should be checked infront
of the hook latch should be there. Then only
belt should be locked.
This condition should be checked at the
mobile crane.
Check the third party inspection for web
sling.
Tag line should be provided at the both end
of the container.
Ensure 3rd party training certificate for
crane operator and riggers.
Proper barricading and signs.
The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.
Page 13 of 14
DWA-00-HS-MS-GNF-0001-REV.00A DEWA PHASE III 800 MW PV SOLAR POWER PROJECT
METHOD STATEMENT: LOADING & UNLOADING OF OFFICE CONTAINERS, INSTALLATION OF
OFFICE CONTAINERS
Unloading the Manjor injury to Employees / 2 4 4 0 32 Before unloading the container underground More awareness Site Engineer/ 16
container the person, Property cable should not be there. should be given in Supervisor
/Installation of Damage Area should be cleared before unloading form of trainings and
Office the container. tool box talks
Containers. The maneuver will be leaded by the certified
Rigger.
Flag man should be available.
Tag line should be provided.
Area should be barricaded.
Unauthorised person no entry.
While loading the container keep the
support hallow block or wooden pieces to
load act on it.
The weight of container is maximum 5
Tonnes.
This RA has complied with 6.2.10.8. Critical
lifting operations, 6.2.9 Lifting Equipment
and Lifting Operations and 6.2.10. Selecting
the Right equipmeny in HSE Management
Plan (DWA-00-HS-PL-0001
The printed version of this document is a non-controlled version. The current version is available in the software tool for documentation management.
Page 14 of 14