REVISED WORKING SCHEDULE OF CONSTRUCTION OF


BUNKER
Name of the Job: Construction of Bunker
Location: Babarmahal, Kathmandu
7]Ssf k§fsf] ;+VofM– DUDBC/Works/NCB-01-074/75
Contractor: SIVAKO/PUSPANJALI J.V.

Month Jestha Ashad Shrawn


Item
No.
Construction Phases and Work Iten Year 2077 2077 2077
Weeks 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
1 Site Clearance &Preparation
2 Footings Excavation
3 Soling and PCC
4 Foundations: RCC
5 Reinforcement Works (Sill and Lintel)
6 Form Work (Sill and Lintel)
7 RCC casting Works (Sill and Lintel)
8 Masonry Walls: Bricks
9 Roofing Works
10 External Windows
11 External Doors
12 Roughly Electrical Works
13 Plastering Works: External & Internal
14 Cornice, Veneer and Exterior rims
15 Screeding and Punning Works
16 Tile and Marble works
17 Painting Works
18 Iron works
19 Deep Boring works
20 Earthing Works
21 Finish Mechanical
22 Finish Electrical
23 Handover

NOTE:
Continuous Activity
Deadlines
Intermittent Activity
Completed Activity