You are on page 1of 18

Estimates

Mobilization and Demobilization

COMPUTATION OF EQUIPMENT OUTPUT PER DAY

Equipment
Requirement
Type of No of Unit Activity Type of No. of Unit Activity
Equipment Equipment
Duration Duration
(Days) (Days)
Backhoe
Pay loader
Dump Truck
Crawler Crane,
36 40T
Crawler
Crane,46-50T

DESCRIPTION QTY. UNIT DAYS UNIT COST AMOUNT


DIRECT COST
A. Equipment Rental:
(To include fuels
and Lubricant)
a. backhoe
b. Pay loader
c. Dump truck
d. Crawler Crane, 36-
40T
e. Crawler Crane 46-
40T
f. Road grader
g. Road roller
h. Transit mixer
i. Water truck
j. Cargo Truck (5T)

B. Labor
a. Backhoe
Operator
b. Payloader
Operator
c. Dump Truck
Driver
d. Crane Operator
e. Road Grader
Operator
f. Road Roller
Operator
g. Transit Mixer
Operator
h. Water Truck
Driver
i. Cargo Truck
(5T) Operator

a. Backhoe
Helper
b. Payloader
Helper
c. Dump Truck
Helper
d. Crane Helper
e. Crane Helper
f. Road Grader
Helper
g. Road Roller
Helper
h. Transit Mixer
Help
i. Water Truck
Helper
j. Cargo Truck
(5T) Helper

C. Materials:
D. DIRECT COST
(A+B+C)

SURPLUS COMMON EXCAVATION

UNIT: cu.m.

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/ Duration


Manpower Day
cu.m. days
Backhoe
Dump Truck

Note: Don’t use DT if materials to be excavated will be utilized as backfill.

DESCRIPTION QTY. UNIT DAYS UNIT COST AMOUNT


A. Equipment
Rental: (To
Include fuel and
Lubricants)
a. Backhoe
b. Dump Truck
c. Pay Loader
Equipment
Total
B. Labor:
a. Foreman
b. Backhoe
Operator
c. Dump Truck
Driver
d. Pay Loader
Operator

a. Helper (Backhoe)
b. Helper (Dump
Truck)
c. Helper (Pay
Loader)
Unskilled
Sub-Total
Labor Total
C. Materials:

D. Direct Cost
(A+B+C)

STRUCTURE EXCAVATION

DESCRIPTION:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/ Duration


Manpower Day
Cu.m
Backhoe
Dump Truck
Water Pump

Note: Don’t use DT if materials to be excavated will be utilized as backfill.

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Backhoe
b. Dump
Truck
c. Water Pump

B. Labor
a. Foreman
b. Backhoe
Operator
c. Dump Truck
Driver

a. Helper
(Backhoe)
b. Helper
(Dump
Truck)
c. Laborer

C. Materials:

D. Direct Cost
(A+B+C)

SHORING AND COFERDAMMING

UNIT: cu.m.

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Backhoe
Dump Truck
Pay Loader
Laborer (for
Sandbags)

Note: Don’t use DT if materials to be excavated will be utilized as backfill.

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Backhoe
b. Dump
Truck
c. Water Pump

B. Labor
a. Foreman
b. Backhoe
Operator
c. Dump Truck
Driver

a. Helper
(Backhoe)
b. Helper
(Dump
Truck)
c. Laborer
C. Materials:

D. Direct Cost
(A+B+C)
EMBANKMENT COMMON BORROW

UNIT: cu.m.

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. days
Bulldozer
Backhoe
Road Grader
Road Roller

Note: Don’t use DT if materials to be excavated will be utilized as backfill.

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Backhoe
b. Road Grader
c. Road Roller
d. Bulldozer

B. Labor
a. Foreman
b. Backhoe
Operator
c. Road Grader
Operator
d. Road Roller
Operator
e. Bulldozer
Operator

a. Helper
(Backhoe)
b. Helper
(Dump
Truck)
c. Helper (Road
Roller)
d. Helper
(Bullzdozer)

C. Materials:
D. Direct Cost
(A+B+C)
AGGREGATE SUB-BASE COURSE

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Road Grader
Road Roller
Water Truck

Note: Don’t use DT if materials to be excavated will be utilized as backfill.

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Road Grader
b. Road Roller
c. Water Truck

B. Labor:
a. Foreman
b. Foreman
c. Road Grader
Operator
d. Road Roller
Operator

a. Helper (Road
Grader)
b. Helper (Road
Roller)

C. Materials:
Embankment
Materials

D. Direct Cost
(A+B+C)

AGGREGATE BASE COURSE

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Road Grader
Road Roller
Water Truck

Note: Don’t use DT if materials to be excavated will be utilized as backfill.

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Road Grader
b. Road Roller
c. Water Truck

B. Labor:
a. Foreman
b. Road Grader
Operator
c. Road Roller
Operator
d. Water Truck
Driver

a. Helper (Road
Grader)
b. Helper (Road
Roller)

C. Materials:
Embankment
Materials

D. Direct Cost
(A+B+C)

REINFORCED CONCRETE RAILINGS

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
FOR CONCRETE
Foreman
Skilled Laborer
Unskilled Laborer
FOR FORMS
Foreman
Skilled Laborer
Unskilled Laborer
FOR RSB
Foreman
Skilled Laborer
Unskilled Laborer
Bar Cutter
Bar Bender
1-Bagger Mixer
Concrete Vibrator
Water Truck
Foreman
Skilled Laborer
Unskilled Laborer
TOTAL

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Bar Cutter
b. Bar Bender
c. 1- Bagger
Mixer
d. Concrete
Vibrator
e. Water Truck

B. Labor:
a. Foreman
b. Skilled
Laborer
c. Unskilled
Laborer

C. Materials:
a. Portland
Cement, 40
kgs.
b. Washed
Sand
c. Gravel
d. Reinforcing
Steel Bar,
Grade 40
e. Tie Wire, #16
f. Marine
Plywood, ½”
x 4” x 8’
g. Lumber
h. CWN
(Assorted)

D. Direct Cost
(A+B+C)

METAL DRAIN

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Foreman
Skilled Laborer

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
Minor Tools (10%
of Labor)

B. Labor:
a. Foreman
b. Skilled Laborer

C. Materials:
150 mmØ G.I.
Pipe
(S-40)
10mmx10mmx6m
square bar

D. Direct Cost
(A+B+C)

REINFORCING STEEL, GRADE 40

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Bar Cutter
Bar Bender
Service Truck
Foreman
Skilled Laborer
Unskilled Laborer

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Bar Cutter
b. Bar Bender
c. Service Truck

B. Labor:
a. Foreman
b. Skilled Laborer

a. Unskilled Laborer

C. Materials:
Reinforcing Steel
Bar, Grade 60
10mmx10mmx6m
square bar
Tie Wire #16

D. Direct Cost
(A+B+C)

STRUCTURAL CONCRETE, CLASS A, FC’ = 28 MPA

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Foreman
Skilled Laborer
Unskilled Laborer
Concreting
Foreman
Skilled Laborer
Unskilled Laborer
Concrete Vibrator
Minor Tools (10%
of Labor)
TOTAL:

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Concrete
Vibrator
b. Minor Tools
(10% of
Labor)

B. Labor:
a. Foreman
b. Skilled
Laborer

a. Unskille
Laborer

C. Materials:
a. Pre-mixed
Concrete, 21
MPa
b. Marine
Plywood,
4’x8’x1/2”
c. Form
Lumber,
Coco
d. Assorted
Common
Wire Nails
e. Tie Wire, #16

D. Direct Cost
(A+B+C)

PRESTRESSED CONCRETE GIRDER (TYPE IV-B)

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Fabrication of
Forms
Skilled Laborer
Unskilled Laborer
Fabrication and
Setting of Rebars
(both Grade 40 &
60)
Foreman
Skilled Laborer
Unskilled Laborer
Concreting
Foreman
Skilled Laborer
Unskilled Laborer
Placing of Tendons
Foreman
Skilled Laborer
Unskilled Laborer
Stressing
Foreman
Skilled Laborer
Unskilled Laborer
Erection/Launching

Crawler Crane, 50T


Foreman
Unskilled Laborer
TOTAL:

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
Minor Tools (10%
of Labor)
h. Crawler Crane,
50T
j. Minor Tools (10%
of Labor)

B. Labor:
a. Foreman
b. Skilled Laborer

a. Unskilled Laborer

C. Materials:
a. 0%

D. Direct Cost
(A+B+C)
ELASTOMETRIC BEARING PADS, DURO 60

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

For Fabrication, Placing, Dismantling of Forms and Concreting

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Foreman
Skilled Laborer

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants

B. Labor:
a. Foreman
b. Skilled Laborer

C. Materials:
a. 0%

D. Direct Cost
(A+B+C)

STONE MASONRY

UNIT: cu.m

QUANTITY:

COMPUTATION OF OUTPUT PER DAY:

For Fabrication, Placing, Dismantling of Forms and Concreting

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Foreman
1-Bagger
Concrete Mixer
Skilled Laborer
Unskilled Laborer

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. 1 Bagger
Concrete
Mixer
Minor Tools
(10% of
Labor)

B. Labor:
a. Foreman
b. Skilled
Laborer

a. Unskilled
Laborer

C. Materials:
a. Boulders
(Rock Class
“A”)
b. Portland
Cement, 40
kgs.
c. Washed
Sand
d. Weep Holes

D. Direct Cost
(A+B+C)

TEMPORARY FACILITY

UNIT: LUMSPUM

QUANTITY: 1

Rental of 48.00 sq.m. area with bedroom & toilet & bath

Equipment/ No. of Unit Quantities Output/Day Duration


Manpower
cu.m. Days
Foreman
Skilled Laborer

DESCRIPTION QTY UNIT DAYS UNIT COST AMOUNT


.
DIRECT COST
A. Equipment
Rental: (To
Include
Fuel and
Lubricants
a. Rental of
Temporary
Facilities

B. Labor

C. Materials:

D. Direct Cost
(A+B+C)

SAFETY AND HEALTH

UNIT: LUMPSUM

QUANTITY: 1

DESCRIPTION QTY UNIT MONTHS UNIT COST AMOUNT


.

A. Equipment
Rental: (To
Include
Fuel and
Lubricants

B. Labor:

C. Materials:
a. Safety Shoes
b. Gloves
c. Safety Helmet
d. Medicines
e. Medical Supplies
& Equipment

D. Direct Cost
(A+B+C)
ESTIMATE OF MATERIALS

Materials Factor for Concrete

Class Concrete Strength Cement (Bag) Sand (m3) Gravel (m3)


(Psi)

“AA”
“A”

“B”
“C”

Weight of Steel Bars

SIZE MASS LENGTH


(mm) (kg/m)

PRICE OF MATERIALS

Material Unit Price


Cement Bags
Sand m3
Gravel m3
10 mmØ 6m/pcs
12 mmØ 6m/pcs
16 mmØ 6m/pcs
20 mmØ 6m/pcs
36 mmØ 6m/pcs
tie bar Kgs.
Plywood Pcs.
Lumber 23x10 Pcs.

Nail Box
Prestressed Concrete AASHTO Pcs
Girder Type IVA (30M)

Source:
PERT-CPM

Steps in Complying the PERT-CPM:

1. Draw your PERT-CPM based on the desired an appropriate methodology of construction.


2. Determine the no. of days for each item of work based on the activity duration in DUPA.
Note that the activity duration in the DUPA is just your point of reference. It is the discretion of
the engineer to determine the no. of days for/per each item of work based on the magnitude
and complexity of the work.
3. Determine the critical path of the PERT-CPM.
4. Compute the required total number of days in the critical path.
5. Determine the unworkable days by multiplying the duration to the desired/allowed percentage.
Note that the percentage to use will be dependent on the rainfall intensity based on previous
(PAGASA) data and experiences of the engineer in the field construction. (20% and above
allowance can be used as long as just.
6. Add the assumed/computed unworkable days to the total no. of days in the critical path
including the Sundays and holidays in a year to get the total. no. of calendar days.
Note! Inclusion of holidays and Sundays is stated under IRRA 9184

LIST OF ACTIVITIES DURATION


Shoring and Cofferdamming
Crane Way
Surplus Common Excavation
Structure Excavation
Embankment Common Borrow
Aggregate Base Course
Reinforcing Steel, Grade 60
Aggregate Sub-base Course
Reinforcing Steel, Grade 60
Structural Concrete, Class A, Fc’=27.8 MPa
Prestressed Concrete Girder
Elastomeric Bearing Pads, Duro 60
Metal Drain
Stone Masonry
Steel Railings
Mattress

You might also like