G BOILER WEEK 1 DWI MARDI UTOMO
SCOPE
1. BRIEFING PAGI OPERATION
2. TRACING JALUR SECONDARY AIR
3. TRACING JALUR PRIMARY AIR
4. TRACING JALUR SEAL AIR
5. TRACING JALUR SCANNING COOLING BLOWER
1. CHECKSHEET COAL FEEDER
2. CHECK LUBE OIL BEARING AIR HEATER
3. CHECKSHEET AIR HEATER TEMPERATURE OUTLATE
4. CHECKSHEET LUBE OIL GEARBOX PULVERIZER
5. CHECKSHEET IK SOOTBLOWER 810 A: GLAND PACKING BOCOR
1. BRIEFING PAGI OPERATION
2. TRACING JALUR FUEL SYSTEM
3. TACING JALUR BURNER
4. TRACING JALUR FUEL OIL
5. TRACING JALUR PULVERIZER
1. BRIEFING PAGI OPERATION
2. MANAGEMENT OPERATION
3. TRACING JALUR WATER AND STEAM
4. TRACING JALUR STEAM DRUM

1. BRIEFING PAGI OPERATION


2. TRACING JALUR WATER AND STEAM
3. TRACING JALUR INLET ECONOMIZER
4. TRACING JALUR OURLET SUPERHEATER
5. TRACING JALUR INLET DAN OUTLATE REHEATER