Cost and Budget Problem - UCR-A2
Cost and Budget Problem - UCR-A2
UCR Course
Assignment – 2
Please Draw the Project Network diagram based on the following information.
The project starts with the starting of the activities A and E together and ends with the
completion of L.
1. Find the critical path and project duration.
2. Construct an early/late start schedule chart
3. Find the cost of the project in each period for early/late start.
4. Prepare a budget estimate
Discuss the implication of early start and late start schedule on the project budget