Professional Documents
Culture Documents
DOR: Tetratech
CONTRACTOR
TRANSMITTAL#
ACTION
CLASSIFICATION
MAILED TO
PARAGRAPH #
ACTIVITY#
MATERIAL NEEDED
DATE FWD CONTR
ACTION CODE
ACTION CODE
SPECIFICATION TO APPR
REVIEWER
REVIEWER
DESCRIPTION OF ITEM SUBMITTED DATE OF REMARKS
SUBMIT
SECTION AUTH DATE OF DATE RCD
ACTION BY
BY
BY
ACTION FRM APPR
AL YAMAMA
DATE RCD USACE AUTH
CQC MANAGER
FROM
CONTR
31 00 00-16 Detectable Warning Tape -Buried Utilitie 2.2.2 FIO A 9-Jun-2020 F 11-Jun-2020
SECTION 31 00 00
EARTHWORK
08/08
PART 1 GENERAL
1.1 REFERENCES
SECTION 31 00 00 Page 1
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.2 DEFINITIONS
SECTION 31 00 00 Page 2
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.2.6 Topsoil
1.2.8 Rock
SECTION 31 00 00 Page 3
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Materials that are too wet to properly support the utility pipe, conduit,
or appurtenant structure.
75 mm 100
37.5 mm 70-100
19 mm 50-85
4.75 mm 30-60
30 um 10-25
75 um 0-5
The liquid limit of such material must not exceed 35 percent when tested
in accordance with ASTM D4318. The plasticity index must not be greater
than 12 percent when tested in accordance with ASTM D4318.
SECTION 31 00 00 Page 4
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.2.12.2.2 Sand
Expansive soils are defined as soils that have a plasticity index equal to
or greater than 25 percent when tested in accordance with ASTM D4318.
As used herein, a structure where both the foundation and floor slab are
pile supported.
SECTION 31 00 00 Page 5
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.4 BLASTING
1.6 SUBMITTALS
Offsite Borrow
SECTION 31 00 00 Page 6
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Testing; G M
SD-07 Certificates
Testing
PART 2 PRODUCTS
Test offsite soils brought in for use as backfill for Total Petroleum
Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and
full Toxicity Characteristic Leaching Procedure (TCLP) including
ignitability, corrosivity and reactivity. Backfill shall contain a
maximum of 100 parts per million (ppm) of total petroleum hydrocarbons
(TPH) and a maximum of 10 ppm of the sum of Benzene, Toluene, Ethyl
Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH
concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX
concentrations by using EPA SW-846.3-3 Method 5030/8020. Perform TCLP in
accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing
for TPH, BTEX and TCLP from a composite sample of material from the borrow
site, with at least one test from each borrow site. Do not bring material
onsite until tests have been approved by the Contracting Officer.
Red Electric
SECTION 31 00 00 Page 7
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
2.3.2 Rock
2.3.3 Grout
SECTION 31 00 00 Page 8
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
PART 3 EXECUTION
SECTION 31 00 00 Page 9
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
3.2.3 Drainage
Provide for the collection and disposal of surface and subsurface water
encountered during construction. Completely drain construction site
during periods of construction to keep soil materials sufficiently dry.
Construct storm drainage features (ponds/basins) at the earliest stages of
site development, and throughout construction grade the construction area
to provide positive surface water runoff away from the construction
activity and or provide temporary ditches, swales, and other drainage
features and equipment as required to maintain dry soils. When unsuitable
working platforms for equipment operation and unsuitable soil support for
subsequent construction features develop, remove unsuitable material and
provide new soil material as specified herein. It is the responsibility
of the Contractor to assess the soil and ground water conditions presented
by the plans and specifications and to employ necessary measures to permit
construction to proceed.
3.2.4 Dewatering
SECTION 31 00 00 Page 10
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
SECTION 31 00 00 Page 11
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Ensure that footing subgrades have been inspected, approved and documented
by a licensed geotechnical engineer or by the Contracting Officer prior to
concrete placement. Excavate to bottom of pile cap prior to placing or
driving piles, unless authorized otherwise by the Contracting Officer.
3.5 SHORING
Submit a Shoring and Sheeting plan for approval 15 days prior to starting
work. Submit drawings and calculations, certified by a licensed
professional engineer, describing the methods for shoring and sheeting of
excavations. Finish shoring, including sheet piling, and install as
necessary to protect workmen, banks, adjacent paving, structures, and
utilities. Remove shoring, bracing, and sheeting as excavations are
backfilled, in a manner to prevent caving.
SECTION 31 00 00 Page 12
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Where indicated, divide work into grading areas within which satisfactory
excavated material will be placed in embankments, fills, and required
backfills. Do not haul satisfactory material excavated in one grading
area to another grading area except when approved by Contracting Officer.
Place and grade stockpiles of satisfactory, unsatisfactory and wasted
materials only in areas approved by the Contracting Officer. Keep
stockpiles in a neat and well drained condition, giving due consideration
to drainage at all times and stockpile requirements herein. Clear, grub,
and seal by rubber-tired equipment, the ground surface at stockpile
locations; separately stockpile excavated satisfactory and unsatisfactory
materials. Protect stockpiles of satisfactory materials from
contamination which may destroy the quality and fitness of the stockpiled
material. If the Contractor fails to protect the stockpiles, and any
material becomes unsatisfactory, remove and replace such material with
satisfactory material from approved sources at no expense to the government.
SECTION 31 00 00 Page 13
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
The contractor shall submit a plan and procedure for stockpiling unused
satisfactory material that will be used later for project construction.
The plan shall include procedures for maintaining the stockpile and
minimizing erosion and mitigating the impact of sedimentation around the
stockpile. Satisfactory material for stockpiling and use includes coarse
rock for construction of slopes or embankments adjacent to streams.
3.9.1 Stockpiling
First place backfill adjacent to any and all types of structures, and
compact, to prevent wedging action or eccentric loading upon or against
the structure. Prepare ground surface on which backfill is to be placed
and provide compaction requirements for backfill materials in conformance
with the applicable portions of paragraphs GROUND SURFACE PREPARATION.
Once fill has been compacted adjacent to structures, finish backfilling
and compaction further from structure by sheepsfoot rollers,
pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or
other approved equipment.
Replace unyielding material removed from the bottom of the trench with
select granular material or initial backfill material.
SECTION 31 00 00 Page 14
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Fill the remainder of the trench, except for special materials for roadways
and structures with satisfactory material. Select and place backfill
material and compact as follows:
After the manhole, catch basin, inlet, or similar structure has been
constructed and the concrete has been allowed to cure for 7 days unless
otherwise approved by CO, place backfill in such a manner that the
structure is not be damaged by the shock of falling earth. Deposit the
backfill material, compact it as specified for final backfill, and bring
up the backfill evenly on all sides of the structure to prevent eccentric
loading and excessive stress.
SECTION 31 00 00 Page 15
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Provide a minimum cover of 600 mm from the finished grade to direct burial
cable and conduit or duct line, unless otherwise indicated.
3.12.3.3 Grouting
SECTION 31 00 00 Page 16
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
3.13 EMBANKMENTS
SECTION 31 00 00 Page 17
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
3.14.2 Construction
3.14.3 Compaction
SECTION 31 00 00 Page 18
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
3.16 FINISHING
Place a capillary water barrier under concrete floor and area-way slabs
grade directly on the subgrade and compact with a minimum of two passes of
a hand-operated plate-type vibratory compactor.
Construct areas within 1.5 m outside of each building and structure line
true-to-grade, shape to drain away from structures, and maintain free of
trash and debris until final inspection has been completed and the work
has been accepted.
3.18 TESTING
SECTION 31 00 00 Page 19
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
b. Check the calibration curves furnished with the moisture gauges along
with density calibration checks as described in ASTM D6938; check the
calibration of both the density and moisture gauges at the beginning
of a job on each different type of material encountered or at
intervals as directed by the Contracting Officer whichever is more
frequent ASTM D2937, use the Drive Cylinder Method only for soft,
fine-grained, cohesive soils. When test results indicate, as
determined by the Contracting Officer, that compaction is not as
specified, remove the material, replace and recompact to meet
specification requirements.
One test per 300 cubic meters for structural fill and one test per 5,000
cubic meters in general fill areas for stockpiled or in-place source
material. General fill areas are those that are not under facilities or
structures. More frequent testing will be required if a change in
material is suspected during onsite visual inspection. Determine
gradation of fill and backfill material in accordance with ASTM C136,
ASTM D422, and ASTM D1140 as applicable.
Structural Fill
a. One test per 100 square meters, or fraction thereof, of each lift of
fill or backfill areas compacted by other than hand-operated machines.
b. One test per 100 square meters, or fraction thereof, of each lift of
fill or backfill areas compacted by hand-operated machines.
General Fill
a. One test per lift for each 4,000 square meters shall be performed
after soil improvements (Dynamic Compaction or Rapid Impact
Compaction).
Structural Fill
a. One check test per lift for each 2000 square meters, or fraction
thereof, of each lift of fill or backfill compacted by other than
hand-operated machines.
SECTION 31 00 00 Page 20
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
b. One check test per lift for each 2000 square meters, of fill or
backfill areas compacted by hand-operated machines.
c. One check test per lift for each 1200 linear meters, or fraction
thereof, of embankment or backfill for roads.
General Fill
a. One test per lift for each 80,000 square meters shall be performed
after soil improvements (Dynamic Compaction or Rapid Impact
Compaction).
After other required tests have been performed and the trench backfill
compacted to the finished grade surface, inspect the pipe to determine
whether significant displacement has occurred. Conduct this inspection in
the presence of the Contracting Officer. Inspect pipe sizes larger than
900 mm, while inspecting smaller diameter pipe by shining a light or laser
between manholes or manhole locations, or by the use of television cameras
passed through the pipe. If, in the judgment of the Contracting Officer,
the interior of the pipe shows poor alignment or any other defects that
would cause improper functioning of the system, replace or repair the
defects as directed at no additional cost to the Government.
-- End of Section --
SECTION 31 00 00 Page 21
100% Site and Facility Design Submittal
Specifications
SECTION 33 11 00
PART 1 GENERAL
1.1 REFERENCES
SECTION 33 11 00 Page 1
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
SECTION 33 11 00 Page 2
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
SECTION 33 11 00 Page 3
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.2 DEFINITIONS
Water mains include water piping having diameters 100 through 350 mm,
specific materials, methods of joining and any appurtenances deemed
necessary for a satisfactory system.
Water service lines include water piping from a water main to a building
service at a point approximately 1.5 m from building or the point
indicated on the drawings, specific materials, methods of joining and any
appurtenances deemed necessary for a satisfactory system.
1.3 SUBMITTALS
Connections; G M/R
Valves
Valve Boxes
SECTION 33 11 00 Page 4
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Fire Hydrants
Pipe Restraint
Tapping Sleeves
Bacteriological Samples; G M
Leakage Test; G M
Hydrostatic Test; G M
SD-07 Certificates
Lining
Valves
Fire Hydrants
Comply with NSF/ANSI 14 or NSF/ANSI 61 and NSF 372 for materials for
potable water systems; comply with lead content requirements for
"lead-free" plumbing as defined by the U.S. Safe Drinking Water Act
effective January 2014. Provide materials bearing the seal of the
National Sanitation Foundation (NSF) for potable water service.
Comply with NFPA 24 for materials, installation, and testing of fire main
piping and components.
Inspect materials delivered to site for damage. Unload and store with
minimum handling and in accordance with manufacturer's instructions.
Store materials on site in enclosures or under protective covering. Store
plastic piping, jointing materials and rubber gaskets under cover out of
direct sunlight. Do not store materials directly on the ground. Keep
inside of pipes, fittings, valves, fire hydrants, and other accessories
free of dirt and debris.
SECTION 33 11 00 Page 5
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.5.2 Handling
This section covers both the potable water and fire water distribution
systems from the water source to facilities served. For the potable water
system this includes piping and appurtenances from the municipal point of
connection to a point 1.5 m from the facility served including the fire
water tanks. For the fire water system this includes piping and
appurtenances connecting fire water tanks to the fire pump house and the
fire pump house to a point 1.5 m outside the facilities served. This
includes above grade piping at the fire water tanks and the above grade
piping running into the fire pump station and hydrants.
PART 2 PRODUCTS
2.1 MATERIALS
Pipe, except flanged pipe, AWWA C151/A21.51, Pressure Class 150 for
Potable Water lines and 200 for Fire Water Lines. Flanged pipe,
AWWA C115/A21.15. Fittings, AWWA C110/A21.10 or AWWA C153/A21.53;
fittings with push-on joint ends are to meet the same requirements as
fittings with mechanical-joint ends, except for the factory modified bell
design. Provide fittings with pressure ratings equivalent to that of the
pipe. Provide compatible pipe ends and fittings for the specified
joints. Provide cement-mortar lining, AWWA C104/A21.4, standard thickness
on pipe and fittings.
SECTION 33 11 00 Page 6
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Provide push-on joints or mechanical joints for pipe and fittings unless
otherwise indicated. Provide mechanical joints where indicated. Provide
flanged joints where indicated. Provide mechanically coupled type joints
using a sleeve-type mechanical coupling where indicated. Sleeve-type
mechanical couplings in lieu of push-on joints are acceptable, subject to
the limitations specified in the paragraph SLEEVE-TYPE MECHANICAL
COUPLINGS.
a. Push-On Joints: Shape of pipe ends and fitting ends, gaskets, and
lubricant for joint assembly as recommended in AWWA C111/A21.11.
Provide ASTM B88M, Type K copper tubing. Provide AWWA C800 fittings.
AWWA C800 includes ASME B1.20.3, ASME B1.20.1, ASME B16.18 solder-type
joint fittings.
2.1.2 Valves
b. AWWA C509 or AWWA C515: nonrising stem type with mechanical-joint ends
or resilient-seated gate valves 80 to 300 mm in size
SECTION 33 11 00 Page 7
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
flange for AWWA C500, AWWA C509, or AWWA C515 gate valves conforming to
the requirements of UL 262. Gate valves shall have ends compatible with
joining to the pipe used; push-on joint ends or mechanical-joint ends for
joining to ductile-iron pipe.
2.1.2.2 Gate Valves 75 mm Size and Larger in Valve Pit(s) and Aboveground
Locations
Construct the bodies of bronze, cast iron or cast steel with lead-free
bronze trim; the valve stem of stainless steel; the seat of lead-free
bronze; and the valve discs and diaphragms of synthetic rubber. Provide
flanged ends.
Provide a valve box for each gate valve on buried piping, except where
indicator post is shown. Construct adjustable valve boxes manufactured
from cast iron or precast concrete of a size compatible for the valve on
which it is used. Provide cast iron valve boxes with a minimum cover and
wall thickness of 5 mm and conforming to ASTM A48/A48M, Class 35B. Coat
the cast-iron box with a heavy coat of bituminous paint. Provide a round
head lid with the word "water" cast in the top. The minimum diameter of
the shaft of the box is 135 mm. Provide ASTM C1433 precast concrete valve
box. Provide precast concrete boxes installed in locations subjected to
vehicular traffic to withstand AASHTO H-20 loading. Manufacture precast
concrete boxes in accordance with Section 03 40 00.00 10 PLANT-PRECAST
CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION.
Provide fire hydrants where indicated. Paint fire hydrants with at least
one coat of primer and two coats of enamel paint. Paint barrel and bonnet
SECTION 33 11 00 Page 8
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
colors in accordance with UFC 3-600-01. Stencil fire hydrant number and
main size on the fire hydrant barrel using black stencil paint.
Provide the same hydrants as those provided for under paragraph Fire
Hydrants where flushing hydrants are indicated.
2.1.4 Disinfection
2.2 ACCESSORIES
SECTION 33 11 00 Page 9
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
SECTION 33 11 00 Page 10
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Ground key, round way, inverted key type; made of lead-free bronze,
ASTM B61or ASTM B62; and compatible with the working pressure of the
system. Provide compatible ends for connection to the service piping.
Cast an arrow into body of the curb or service stop indicating direction
of flow.
Provide a curb box for each curb or service stop manufactured from cast
iron, size capable of containing the stop where it is used. Provide a
round head. Cast the word "WATER" on the lid. Factory coat the box with
a heavy coat of bituminous paint.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Earthwork
SECTION 33 11 00 Page 11
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
3.2 INSTALLATION
3.2.1 Piping
Do not lay water lines in the same trench with gas lines, fuel lines,
electric wiring, or any other utility. Do not install copper tubing in
the same trench with ferrous piping materials. Where nonferrous metallic
pipe (i.e., copper tubing) crosses any ferrous piping, provide a minimum
vertical separation of 300 mm between pipes.
Remove fins and burrs from pipe and fittings. Before placing in position,
clean pipe, fittings, valves, and accessories, and maintain in a clean
condition. Provide proper facilities for lowering sections of pipe into
trenches. Under no circumstances is it permissible to drop or dump pipe,
fittings, valves, or other water line material into trenches. Cut pipe
cleanly, squarely, and accurately to the length established at the site
and work into place without springing or forcing. Replace a pipe or
fitting that does not allow sufficient space for installation of jointing
material. Blocking or wedging between bells and spigots is not
permitted. Lay bell-and-spigot pipe with the bell end pointing in the
direction of laying. Grade the pipeline in straight lines; avoid the
formation of dips and low points. Support pipe at the design elevation
and grade. Secure firm, uniform support. Wood support blocking is not
permitted. Lay pipe so that the full length of each section of pipe and
each fitting rests solidly on the pipe bedding; excavate recesses to
accommodate bells, joints, and couplings. Provide anchors and supports
for fastening work into place. Make provision for expansion and
contraction of pipelines. Keep trenches free of water until joints have
been assembled. At the end of each work day, close open ends of pipe
temporarily with wood blocks or bulkheads. Do not lay pipe when
conditions of trench or weather prevent installation. Provide a minimum of
760 mm depth of cover over top of pipe.
SECTION 33 11 00 Page 12
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Where the location of the water line is not clearly defined by dimensions
on the drawings, do not lay water line closer than 3.0 m, horizontally,
from any sewer line.
Provide at least 450 mm above the top (crown) of the sewer piping and the
bottom (invert) of the water piping whenever possible. Measure the
distance edge-to-edge. Where water lines cross under gravity sewer lines,
construct sewer line of AWWA compliant ductile iron water piping with
rubber-gasketed joints and no joint located within 3 m horizontally, of
the crossing.
3.2.1.1.7 Penetrations
SECTION 33 11 00 Page 13
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Only install flanged pipe aboveground or with the flanges in valve pits
unless otherwise indicated.
b. Allowable Deflection: Follow AWWA C600 and AWWA M41 for the maximum
allowable deflection. If the alignment requires deflection in excess
of the above limitations, provide special bends or a sufficient number
of shorter lengths of pipe to achieve angular deflections within the
limit set forth.
SECTION 33 11 00 Page 14
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Cut copper tubing with square ends; remove fins and burrs. Replace
dented, gouged, or otherwise damaged tubing with undamaged tubing. Make
solder joints using ASTM B32, 95-5 tin-antimony or Grade Sn96 solder. Use
solder and flux containing less than 0.2 percent lead. Before making
joint, clean ends of tubing and inside of fitting or coupling with wire
brush or abrasive. Apply a rosin flux to the tubing end and on recess
inside of fitting or coupling. Insert tubing end into fitting or coupling
for the full depth of the recess and solder. For compression joints on
flared tubing, insert tubing through the coupling nut and flare tubing.
3.2.1.5.1 Location
Connect water service piping to the building service where the building
service has been installed. Where building service has not been
installed, terminate water service lines approximately 1.5 m from the
building line at the points indicated; close such water service lines with
plugs or caps.
All service line connections shall be made using DI meeting standards set
herein for water distribution piping.
SECTION 33 11 00 Page 15
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
3.2.2 Flushing
3.2.4 Valves
Install gate valves, AWWA C500 and UL 262, in accordance with the
requirements of AWWA C600 for valve-and-fitting installation and with the
recommendations of the Appendix ("Installation, Operation, and Maintenance
of Gate Valves") to AWWA C500. Install gate valves, AWWA C509 or AWWA C515,
in accordance with the requirements of AWWA C600 for valve-and-fitting
installation and with the recommendations of the Appendix ("Installation,
Operation, and Maintenance of Gate Valves") to AWWA C509 or AWWA C515.
Install gate valves on PVC and PVCO water mains in accordance with the
recommendations for appurtenance installation in AWWA M23, Chapter 7,
"Installation." Make and assemble joints to gate valves as specified for
making and assembling the same type joints between pipe and fittings.
Install fire hydrants in accordance with AWWA C600 for fire hydrant
installation and as indicated. Make and assemble joints as specified for
making and assembling the same type joints between pipe and fittings.
Provide metal harness as specified under pipe anchorage requirements for
the respective pipeline material to which fire hydrant is attached.
Install fire hydrants with the 115 mm connections facing the adjacent
paved surface. If there are two paved adjacent surfaces, install fire
SECTION 33 11 00 Page 16
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
hydrants with the 115 mm connection facing the paved surface where the
connecting main is located.
All buried or partially buried concrete structures shall have that portion
of the concrete in contact with soil shall waterproofed per Specification
07 13 53 - SHEET WATERPROOFING which consists of a coat of Bitumen primer,
sheet membrane and protection board. Should protection board not be
practical to install, alternative protection for the installed membrane
will be allowed if approved by CO.
3.4.1 Tests
Test the water system in accordance with the applicable AWWA standard
specified below. Where water mains provide fire service, test in
accordance with the special testing requirements given in the paragraph
SPECIAL TESTING REQUIREMENTS FOR FIRE SERVICE. Test ductile-iron water
mains in accordance with the requirements of AWWA C600 for hydrostatic
testing. The amount of leakage on ductile-iron pipelines with
mechanical-joints or push-on joints is not to exceed the amounts given in
AWWA C600; no leakage will be allowed at joints made by any other
methods. Test PVC and PVCO plastic water systems made with PVC pipe in
accordance with the requirements of AWWA C605 for pressure and leakage
tests. The amount of leakage on pipelines made of PVC water main pipe is
not to exceed the amounts given in AWWA C605, except that at joints made
with sleeve-type mechanical couplings, no leakage will be allowed. Test
concrete water mains in accordance with the recommendations in AWWA M9,
"Hydrostatic Testing and Disinfection of Mains." The amount of leakage on
concrete pipelines is not to exceed 1.8 liters per 24 hours per millimeter
of pipe diameter per mile of pipeline. Test steel water mains in
accordance with applicable requirements of AWWA C600 for hydrostatic
testing. The amount of leakage on steel pipelines with rubber-gasketed
bell-and-spigot joints is not to exceed 1.8 liters per 24 hours per
millimeter of pipe diameter per mile of pipeline; no leakage will be
allowed at joints made by any other method. To stop leakage, repair
welded joints only by welding. Test water service lines in accordance
with requirements of AWWA C600 for hydrostatic testing. No leakage will
be allowed at copper pipe joints, copper tubing joints (soldered,
compression type, brazed), plastic pipe joints, flanged joints, and
screwed joints. Do not backfill utility trench or begin testing on any
section of a pipeline where concrete thrust blocks have been provided
until at least 7 days after placing of the concrete.
SECTION 33 11 00 Page 17
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
For leakage test, use a hydrostatic pressure not less than the maximum
working pressure of the system. Leakage test may be performed at the same
time and at the same test pressure as the pressure test.
3.6 CLEANUP
-- End of Section --
SECTION 33 11 00 Page 18
100% Site and Facility Design Submittal
CONTRACT DRAWINGS
1. IFC Drawings
2. Shop Drawings
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu100pn abby.hunkler 12/19/2019 5:18 PM
B
D
A
C
[]
[]
[]
FDC
CS
GEN
FP
[]
1
MV
[]
D
D
T FP
FP
D
UGE
[]
[]
MV
FIRE PUMP HOUSE
T FP W
[]
UGE
D
BRIGADE HEADQUARTERS
[]
[]
T
CS
D
MV
UGE
T MV MV T T MV
MV
W W W FP D W W FP W
E
E
GEN
[]
CS
MV
[]
UGE
2
GUARD HOUSE
[]
BM TT-2
T
TW
FP
BM TT-1
[]
S
FP
MV
UGE
[]
[]
WL T
FP
FP
MV
S
UGE
T
[]
D
W
[]
SCALE 1:2000
VP
LS
D
W
[]
UGE
UTILITIES PLAN
[]
CS
D
FM
GEN
FM
3
[]
OVERALL COMBINED
UGE
ET
[]
FM
FM
D
[]
L
T
W
UGE
[]
BATTALION HEADQUARTERS
FP
COMPANY
[]
L
[]
HEADQUARTERS/HOUSING
UGE
[]
[]
UGE
BM TT-3
4
[]
[]
[]
UGE
[]
106
111
127
122
117
112
107
5
108
KEY PLAN
KEY PLAN
APPR.
106 107 108 109 110
DATE
D
111 112 114
DESCRIPTION
117
122
APPR. MARK
127
SEP
MATCHLINE
12-19-19
DATE
SITE AND FACILITY DESIGN SUBMITTAL
DESCRIPTION
C
GENERAL NOTES
1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
MARK
100%
OTHERWISE INDICATED.
12-19-19
DECEMBER 19, 2019
SOLICITATION NO.:
3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
CONTRACT NO.:
0.5% UNLESS OTHERWISE INDICATED.
1:2
SA-459583--CU-106PN
4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
INDICATED.
FILE NAME:
CKD BY:
INDICATED.
JWH
CTJ
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
FOR CORROSION PROTECTION.
22 X 34
DWN BY:
MATCHLINE
SJW
SIZE:
7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
B DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
US Army Corps
of Engineers
FIRE PROTECTION
GATE VALVE WATER LINE
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
FP FP FP FP FP FP FP FP
COMBINED UTILITIES
SITE DESIGN
SA-459583
PLAN 106
GRAPHIC SCALE
FP
KEY PLAN
SMH-5
N: 2957105.690 ST-1
SMH-6 200 mm PVC @ 0.50% N: 2957095.244
N: 2957144.552 200 mm PVC E: 369469.869
INV = 6.622 160 mm PVC @ 1.50% RIM = 7.494 E: 369463.117
E: 369422.802 RIM = 7.622
RIM = 7.797 INV IN = 6.428 (NW)
INV IN = 6.366 (SW)
INV IN = 6.904MV
(SW) MV MV MV MV INV OUT = 6.423 (SW)
INV IN = 6.366 (NE)
S S S
APPR.
INV IN = 6.808 (W) 200 mm PVC @ 0.50% INV OUT = 6.291 (SE)
INV = 7.320 106 107 108 109 110
INV OUT = 6.733 (SE) SMH-4
160 mm PVC @ 1.60%INV = 7.170 GEN CS MV N: 2957085.302
DATE
100 mm PVC @ 1.82%
S
E: 369475.179
E
INV = 7.244
S
MV
D E
0+271 RIM = 7.293
160 mm PVC @ 1.50% 0+260 INV IN = 6.221 (NW) 111 112 114
INV = 7.308 INV OUT = 6.190 (SE)
E
100 mm PVC @ 2.00% T 100 mm FUTURE
S 200 mm PVC S
S
WATER SERVICE
SEWER CLEANOUT (TYP) INV = 6.877 0+2
MV
INV = 6.858
DESCRIPTION
FP FP FP 4 0 200 mm PVC
INV = 7.370 W W 117
FIRE HYDRANT (TYP) S
L
SMH-7
MV
N: 2957092.613
T
INV OUT = 7.40 INV = 7.350 100 mm DI 0+2
50 mm DI E: 369459.007
TYPICAL FOR BRIGADE RIM = 7.773 FP 20
HEADQUARTERS BRIGADE
INV IN = 6.841 (NW) INV = 6.516 122
HEADQUARTERS S
INV IN = 6.390 (SW) SMH-3 FP
W
INV OUT = 6.385 (NE) N: 2957050.585
APPR. MARK
150 mm DI E: 369491.867
L
S S RIM = 7.507 127
FP
T
SEP
MV
T T T T T INV = 7.370 INV IN = 5.997 (NW)
INV = 7.374
MATCHLINE
MATCHLINE
150 mm DI
MV
INV OUT = 5.966 (SE)
INV = 7.275
12-19-19
SMH-9
FP
DATE
160 mm PVC @ 1.50% N: 2957074.838
E: 369444.331 100mm DI
W
SEWER LINE (TYP)
RIM = 7.735
T
FP
DESCRIPTION
C L L
M
FP FP FP FP FP FP
V
MV
150 mm DI
T
GENERAL NOTES
L
L
FP GATE VALVE
T 1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
M
(TYP)
V
W
MARK
100%
OTHERWISE INDICATED.
FP
L
FP L
T
12-19-19
DECEMBER 19, 2019
W
SOLICITATION NO.:
MV
D
D 3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
CONTRACT NO.:
0.5% UNLESS OTHERWISE INDICATED.
1:2
SA-459583--CU-107PN
4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
INDICATED.
FILE NAME:
CKD BY:
INDICATED.
FP
T
T
JWH
L
L
CTJ
WATER LINE (TYP)
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
W W FIRE PROTECTION FOR CORROSION PROTECTION.
22 X 34
DWN BY:
L L
MATCHLINE
MATCHLINE
WATER LINE (TYP)
SJW
MV
SIZE:
7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
B DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
W
T
T
MV
L
L
FP
US Army Corps
L
of Engineers
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
W
W
L
MV
MV MV MV T T
FP FP FP FP FP
T
W W W W W W
L L L L L L
COMBINED UTILITIES
FP
W
M
V
SITE DESIGN
L
SA-459583
PLAN 107
GRAPHIC SCALE
T
T
FP
W
A
L
KEY PLAN
APPR.
106 107 108 109 110
DATE
D
111 112 114
100mm DI T
STUB FOR FUTURE
WATER CONNECTION
DESCRIPTION
(TYP) T MV 117
W
FP
T
122
T
FIRE
S
HYDRANT
0+2 (TYP)
00
APPR. MARK
FP W
T
S
FP 127
SEP
0+1
80 S
MATCHLINE
MATCHLINE
200
12-19-19
mm
DATE
FP PVC 150 mm DI
@0
0+1 S .50
60 % 100 mm PVC @ 2.00%
T
T
FP SEWER ALIGNMENT 1
MV
FP 40 N: 2956951.795
S E: 369546.930 INV = 8.030
DESCRIPTION
C RIM = 7.482
FP
0+1 INV IN = 5.401 (NW) ST-2 INV = 7.998
20 S INV OUT = 5.361 (SE) N: 2956835.101
T
FP E: 369625.662 D
RIM = 8.305
D
GENERAL NOTES
L
0+1 INV IN = 7.109 (NE)
00 1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
MV
T
FP S
INV IN = 7.109 (SE)
MARK
100%
FP
OTHERWISE INDICATED.
0+
FP 080 SMH-1
S
S
T
N: 2956862.507 2. SEWER COLLECTOR PIPES ARE 160mm PVC PIPES WITH A
12-19-19
E: 369596.698
SOLICITATION NO.:
60 3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
INV IN = 4.850 (NW)
CONTRACT NO.:
INV IN = 4.816 (SE) 0.5% UNLESS OTHERWISE INDICATED.
W
D
FP S
INV IN = 4.795 (W)
1:2
SA-459583--CU-108PN
0+0 INV OUT = 4.766 (SW) 4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
40
S
SEWER ALIGNMENT 2 INDICATED.
S
FP
T
5. ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE
0+0
FILE NAME:
CKD BY:
20 S INDICATED.
JWH
CTJ
FP FP
S. PAVLOWICH
SUBMITTED BY:
MV
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
0+000
L
FOR CORROSION PROTECTION.
T
200 mm PVC @ 0.50% S 0+040
22 X 34
DWN BY:
MATCHLINE
MATCHLINE
SJW
0+020 S
SIZE:
FIRE PROTECTION 0+000 7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
B WATER LINE (TYP) DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
STUB FOR FUTURE
FP
US Army Corps
VP
WATER LINE (TYP)
200 mm PVC @ 1.24% 200 mm PVC @ 0.50%
of Engineers
T
W
CONTROL
SEWER LIFT STATION
PANEL
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
LIFT STATION VALVE PIT
L
MV MV MV MV MV MV MV MV MV MV MV MV
T T T T T T T T T T T
FP FP FP FP FP FP FP FP FP FP FP FP FP FP
FM
W W W W W W W W W W W W W W W
FM
L L L L L L L L L L L L L
GATE
VALVE (TYP)
COMBINED UTILITIES
SITE DESIGN
SA-459583
SMH-11
PLAN 108
N: 2956834.215 GRAPHIC SCALE
E: 369623.594
RIM = 8.241
A INV IN = 6.988 (NE)
INV IN = 5.053 (SE)
INV OUT = 5.011 (NW)
KEY PLAN
APPR.
INV OUT = 8.10 106 107 108 109 110
TYPICAL FOR BATTALION
HEADQUARTERS
DATE
D
100mm DI
T 111 112 114
T SEWER
CS CLEANOUT
MV
W (TYP)
FP INV = 8.040
DESCRIPTION
INV = 7.998 117
T
160mm PVC @ 1.50%
FP
SMH-13
W
122
N: 2956860.714
E: 369677.330
RIM = 8.425
APPR. MARK
INV IN = 7.820 (NW)
T
HEADQUARTERS
127
SEP
INV OUT = 7.528 (SW)
S
MATCHLINE
MATCHLINE
E
FP
12-19-19
W
DATE
160 mm PVC @ 1.50%
200 mm PVC @ 0.50%
SMH-15
T
N: 2956825.976
DESCRIPTION
C REDUCER
FP
W
100 mm DI 0+040
INV = 6.580
100mm DI
GENERAL NOTES
INV = 7.845 100mm DI 1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
FP FP FP FP FP
MARK
100%
T T T T T OTHERWISE INDICATED.
INV = 7.416 GEN E E E E E
S 65mm DI
2. SEWER COLLECTOR PIPES ARE 160mm PVC PIPES WITH A
12-19-19
200 mm PVC @ 0.50%
75mm DI
SOLICITATION NO.:
INV OUT = 7.90 3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
FP
T
CONTRACT NO.:
FP
TYPICAL FOR COMPANY 0.5% UNLESS OTHERWISE INDICATED.
SEWER
ALIGNMENT 3 HEADQUARTERS
1:2
SA-459583--CU-109PN
4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
S
DATE:
0+020
S
FILE NAME:
CKD BY:
INV = 7.126 200 mm PVC @ 3.38% INDICATED.
JWH
CTJ
T
CONNECTION (TYP)
E
FP
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
INV = 7.010 FIRE HYDRANT (TYP) 100mm DI FOR CORROSION PROTECTION.
0+120
22 X 34
DWN BY:
S
MATCHLINE
MATCHLINE
S
0+080 S 0+140 S
SJW
SIZE:
S S
S S S S 0+177 7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
S
B 0+060 0+100 0+160 DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
0+000 SMH-16
FP
N: 2956758.170
T
US Army Corps
E: 369682.664
T
E: 369716.482
FP
FP
of Engineers
RIM = 8.203
W
150 mm DI RIM = 7.960
INV IN = 6.288 (SE)
INV IN = 5.753 (SE)
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
INV OUT = 5.703 (NW)
INV OUT = 6.233 (NW)
T
FP FP FP FP FP FP FP FP FP FP
FP FP W W W W W W W W W W W
W W W
T
T
L L L L L L L L L L L L L L L
D
D FIRE PROTECTION
COMBINED UTILITIES
75mm SDR 26 FORCE MAIN
SITE DESIGN
ST-3 WATER LINE (TYP)
SA-459583
SMH-14
PLAN 109
N: 2956806.399 GRAPHIC SCALE
FM
SMH-12 N: 2956805.676
FM
N: 2956820.117 E: 369658.945 E: 369662.565
E: 369643.811 RIM = 7.874 RIM = 7.923
RIM = 8.305 INV IN = 5.429 (NE) INV IN = 5.510 (SE)
A
INV IN = 7.265 (NE) INV IN = 5.330 (SE) INV IN = 5.510 (NE)
INV OUT = 7.215 (NW) INV OUT = 5.280 (NW) INV OUT = 5.435 (SW)
KEY PLAN
APPR.
106 107 108 109 110
DATE
D
111 112 114
DESCRIPTION
117
122
APPR. MARK
127
SEP
MATCHLINE
12-19-19
DATE
SITE AND FACILITY DESIGN SUBMITTAL
DESCRIPTION
C
GENERAL NOTES
1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
MINIMUM SLOPE OF 2.00% TO THE FIRST BEND UNLESS
SEE SHEET CU-109
MARK
100%
OTHERWISE INDICATED.
12-19-19
DECEMBER 19, 2019
SOLICITATION NO.:
3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
CONTRACT NO.:
0.5% UNLESS OTHERWISE INDICATED.
1:2
SA-459583--CU-110PN
4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
INDICATED.
FILE NAME:
CKD BY:
INDICATED.
JWH
CTJ
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
FOR CORROSION PROTECTION.
22 X 34
DWN BY:
MATCHLINE
SJW
SIZE:
7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
B DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
US Army Corps
of Engineers
150 mm DI
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
STUB FOR FUTURE
WATER CONNECTION (TYP)
FP FP FP
W W W W
L L L
COMBINED UTILITIES
SITE DESIGN
SA-459583
PLAN 110
GRAPHIC SCALE
FP
APPR.
106 107 108 109 110
DATE
FP
D
111 112 114
DESCRIPTION
117
FP
122
APPR. MARK
127
SEP
MATCHLINE
12-19-19
DATE
FP
GENERAL NOTES
1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
MARK
100%
OTHERWISE INDICATED.
FP
12-19-19
DECEMBER 19, 2019
SOLICITATION NO.:
INFILTRATION TRENCH 3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
CONTRACT NO.:
0.5% UNLESS OTHERWISE INDICATED.
851,800 L
1:2
SA-459583--CU-111PN
FIRE STORAGE TANK 4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
FP
INDICATED.
FILE NAME:
CKD BY:
INDICATED.
JWH
CTJ
INV = 7.550
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
FIRE PUMP HOUSE FOR CORROSION PROTECTION.
22 X 34
DWN BY:
MATCHLINE
FP
SJW
SIZE:
250 X 400 REDUCER 851,800 L 7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
FP
B
FR
FIRE STORAGE TANK DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
MANUFACTURER'S RECOMMENDATION.
FDC
US Army Corps
of Engineers
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
E
FIRE HYDRANT
TEE (TYP)
GEN
W
E
COMBINED UTILITIES
W
SITE DESIGN
45° BEND (TYP)
SA-459583
PLAN 111
GRAPHIC SCALE
T
MV MV MV MV MV MV MV MV MV
A
D
D
D
D
D
D
FP
T T T T T T T T T
W W W W W W W W
FP FP FP FP FP FP FP FP FP
DIM. NOTE & NORTH
COMBINED UTILITIES N
SHEET ID
ALL DIMENSIONS AND/OR DIMENSIONS
PLAN 111 SHOWN IN CALLOUTS/NOTES ARE IN -
SCALE 1:400
METERS UNLESS OTHERWISE NOTED
CU-111
1 2 3 4 5
MV
T
W
FP
APPR.
106 107 108 109 110
MV
T
DATE
L
D
W
111 112 114
FP
DESCRIPTION
T
MV
117
W
FP
122
T
WATER LINE (TYP)
APPR. MARK
MV
L
127
SEP
FIRE PROTECTION WATER LINE (TYP)
MATCHLINE
12-19-19
FIRE HYDRANT (TYP)
DATE
T
150 mm DI
FP
MV
DESCRIPTION
C
FP
GENERAL NOTES
L
MV
W
1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
MINIMUM SLOPE OF 2.00% TO THE FIRST BEND UNLESS
SEE SHEET CU-111
MARK
100%
OTHERWISE INDICATED.
T
2. SEWER COLLECTOR PIPES ARE 160mm PVC PIPES WITH A
12-19-19
DECEMBER 19, 2019
W
MV
SOLICITATION NO.:
3. ALL SEWER MAINS ARE 200mm PVC PIPE WITH A MIN. SLOPE OF
CONTRACT NO.:
0.5% UNLESS OTHERWISE INDICATED.
1:2
SA-459583--CU-112PN
4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
INDICATED.
FP
5. ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE
FILE NAME:
CKD BY:
INDICATED.
JWH
CTJ
MV
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
L
FOR CORROSION PROTECTION.
T
22 X 34
DWN BY:
MATCHLINE
SJW
SIZE:
7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
B DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
US Army Corps
MV
of Engineers
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:28 PM
TETRA TECH
T
FP
W
MV
150 mm DI
COMBINED UTILITIES
SITE DESIGN
SA-459583
PLAN 112
GRAPHIC SCALE
FP
T
MV MV MV MV MV MV MV
W
T T T T T T T
W W W W W W W W W
FP FP FP FP FP FP FP FP FP
MATCHLINE SEE SHEET CU-117 MATCHLINE DIM. NOTE & NORTH
COMBINED UTILITIES N
SHEET ID
ALL DIMENSIONS AND/OR DIMENSIONS
PLAN 112 SHOWN IN CALLOUTS/NOTES ARE IN -
SCALE 1:400
METERS UNLESS OTHERWISE NOTED
CU-112
1 2 3 4 5
FP FP FP FP FP
MATCHLINE
FP FP
SEE SHEET CU-112
FP FP
MATCHLINE KEY PLAN
W
FP
L
T
APPR.
106 107 108 109 110
MV
DATE
W
D
FP
T
111 112 114
150 mm DI
DESCRIPTION
117
W
FIRE HYDRANT
T
GUARD HOUSE LEACH FIELD
(APPROX. 4m X 5m) CS
FP
REFER TO DETAIL FOR 122
ADDITIONAL INFORMATION L L
APPR. MARK
GUARD HOUSE LEACH
W
T
FIELD DISTRIBUTION BOX INV = 7.379 127
SEP
INV ELEV IN: 6.593
INV ELEV OUT: 6.568
FP
12-19-19
L
DATE
100 mm PVC @ 2.00% INV = 7.416
100mm PVC @ 2.00%
W
SERVICE STOP
ST - 4
DESCRIPTION
L
C D
FP
N: 2956816.740
MV
E: 369150.011 D
T
RIM = 8.561
INV IN = 6.956 (SE) 25mm DI
GENERAL NOTES
W
INV OUT = 6.881 (NE) INV = 7.475
1. BUILDING SEWER OUTLET LINES ARE 100mm PVC PIPES WITH A
100mm PVC @ 2.00% MINIMUM SLOPE OF 2.00% TO THE FIRST BEND UNLESS
MARK
100%
FP
OTHERWISE INDICATED.
INV = 7.550
MV
T
2. SEWER COLLECTOR PIPES ARE 160mm PVC PIPES WITH A
12-19-19
W
CONTRACT NO.:
0.5% UNLESS OTHERWISE INDICATED.
FP
1:2
SA-459583--CU-117PN
4. ALL DOMESTIC WATER LINES ARE 200mm DI UNLESS OTHERWISE
DATE:
MV
INDICATED.
L
WATER LINE (TYP)
W
5. ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE
FILE NAME:
CKD BY:
INDICATED.
JWH
CTJ
FIRE PROTECTION WATER LINE (TYP)
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
6. ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WRAPPED
FOR CORROSION PROTECTION.
FP
T
22 X 34
DWN BY:
SJW
SIZE:
7. CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL
MV
B GATE VALVE (TYP) DUCTILE IRON PIPES 400mm IN DIAMETER OR LARGER PER
US Army Corps
of Engineers
T
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu101pn brandon.goold 12/19/2019 5:29 PM
TETRA TECH
STUB FOR FUTURE
MV CONNECTION (TYP)
150 mm DI
L
T
MV
COMBINED UTILITIES
W
SITE DESIGN
SA-459583
PLAN 117
GRAPHIC SCALE
A
T
MV
W
UNPAVED PAVED
APPR.
CAST IRON FRAME AND
COVER: TO READ "WATER"
OR "FIRE" AS APPLICABLE
DATE
D 1000 DIA x 210 CONCRETE COLLAR
(REFER TO SPECIFICATION 03 30 1000Ø x 210 CONCRETE
00.00 10 FOR CONCRETE COLLAR (REFER TO
SPECIFICATION 03 30 00.10 CAST IRON FRAME AND
STRENGTH)
FINISH GRADE FOR CONCRETE COVER; COVER TO
STRENGTH) READ "WATER"
16 Ø HOOP REINFORCING
DESCRIPTION
16 Ø HOOP REINFORCEMENT CENTERED IN COLLAR
CENTERED IN COLLAR
ADJUSTABLE CAST IRON COMPACT SUBGRADE VARIES (SEE PLANS)
VALVE BOX MIN DIA 135
POTABLE BUILDING
APPR. MARK
VALVE BOX MIN DIA 135 SERVICE
GATE VALVE STOP
SERVICE STOP
SEP
WATER LINE / FIRE LINE (BALL VALVE)
POTABLE
12-19-19
WATER LINE COPPER
DATE
SERVICE LINE
150
COPPER TUBING (TYP)
DESCRIPTION
C COMPACTED WASHED ANGULAR STONE NOTES:
WATER / FIRE MALE THREAD X 1. VALVE BOX NOT SHOWN FOR CLARITY
COMPRESSION 2. SEE CU-100 DRAWINGS FOR SERVICE SIZE
PROTECTION BURIED FITTING COUPLING WATER SERVICE LINE
GATE VALVE CONNECTION SECTION WATER SERVICE LINE
1 2
SCALE = NTS SCALE = NTS
CONNECTION PLAN
MARK
3
100%
SCALE = NTS
CONTRACT NO.:
UNPAVED PAVED
1:2
FINISH GRADE
SA-459583--CU521DT
DATE:
SEE ROADWAY/CONCRETE
WEDGE INDICATING 100X100 LOCATOR EXISTING GROUND DETAILS FOR PAVEMENT
DIRECTION OF POST WITH WEDGE SURFACE REQUIREMENTS
INSTALLED UTILITY PAINTED BLUE AND
CAP WITH "WATER"
FILE NAME:
CKD BY:
MARKED WITH W
MARKED ON IT
BET
JSR
S. PAVLOWICH
150mm CONCRETE 300
SUBMITTED BY:
DESIGNED BY:
COLLAR
22 X 34
DWN BY:
FINISH GRADE 450mm (MIN) TRENCH WIDTH. FOR PIPES LARGER THAN 150mm,
SCJ
SIZE:
WIDTH SHALL BE PIPE DIAMETER PLUS 230mm ON EACH SIDE
B
760 (MIN)
PLACE BURIED WARNING AND
US Army Corps
COVER
of Engineers
END CAP
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu521dt brandon.goold 12/24/2019 10:59 AM
SATISFACTORY MATERIAL
45°
MA
TETRA TECH
GATE COMPACTED TO 95% OF
X
300
VALVE MAXIMUM DRY DESNITY
(TYP ON TOP)
150 (TYP ON SIDES)
WATER DETAILS
SHEET 1 OF 6
SITE DESIGN
SA-459583
FUTURE WATER WATER / FIRE MAIN 1. ALL BURIED OR PARTIALLY BURIED CONCRETE STRUCTURES
SHALL HAVE THAT PORTION OF THE CONCRETE IN CONTACT
CONNECTION TRENCH DETAIL WITH SOIL SHALL WATERPROOFED PER SPECIFICATION 07 13 53 -
A 4 SCALE = NTS
5 SCALE = NTS SHEET WATERPROOFING WHICH CONSISTS OF A COAT OF
BITUMEN PRIMER, SHEET MEMBRANE AND PROTECTION BOARD.
SHOULD PROTECTION BOARD NOT BE PRACTICAL TO INSTALL,
ALTERNATIVE PROTECTION FOR THE INSTALLED MEMBRANE
WILL BE ALLOWED IF APPROVED BY CO.
UNLESS OTHERWISE
DIMENSIONS SHOWN NOTED,
ARE IN MILLIMETERS.
LINEAR
1 2 3 4 5
FIRE
HYDRANT
A
CU-522
1660
APPR.
830
BOLLARD (TYP)
CL WATER
DATE
3050 3050
D 830
920 150
MIN CONCRETE ENCASEMENT CL SEWER TYP
1660
SEWER
FIRE HYDRANT
DESCRIPTION
SEWER
CONCRETE
BOLLARD PLAN ENCASEMENT (SEE
1
MIN
MIN
450
450
SCALE = NTS NOTES)
PVC PIPE
BELL JOINT
WATER
830
WATER
APPR. MARK
610 1660
WATER CROSSING
SEP
FIRE HYDRANT
BOLLARD (TYP)
UNDER SEWER SECTION
12-19-19
A
DATE
3 SCALE = NTS CU-522 SCALE = NTS
DESCRIPTION
C NOTE:
1. REFER TO PLANS FOR LOCATION OF HYDRANTS. 2. REFER TO SPECIFICATION 33 11 00 WATER DISTRIBUTION AND 33 30 00 SANITARY SEWER FOR ADDITIONAL INFORMATION.
2. FIRE HYDRANT SHALL BE PLACED AT LEAST 1m FROM EDGE OF PAVEMENT. 3. WATER MAINS SHALL BE INSTALLED A MINIMUM 305 ABOVE SANITARY SEWER MAINS WHEN IT CROSSES OVER THE SEWER.
3. REFER TO PLANS FOR QUANTITY AND LOCATION OF BOLLARDS. 4. DI PIPE MAY BE USED IN LIEU OF PVC CONCRETE ENCASED PIPE
5. NO JOINT SHALL BE CLOSER THAN 920 FROM CENTERLINE OF WATER MAIN REGARDLESS OF WHETHER DI CONCRETE
FIRE HYDRANT
MARK
100%
ENCASED PVC IS USED.
BOLLARD ELEVATION
12-19-19
DECEMBER 19, 2019
SCALE = NTS
SOLICITATION NO.:
CONTRACT NO.:
1:2
SA-459583--CU521DT
DATE:
0.5 m
PAVEMENT OR FIRE
FILE NAME:
CKD BY:
FINISH GRADE HYDRANT
BET
JSR
(PAINT RED) FROM FIRE
S. PAVLOWICH
SUBMITTED BY:
PUMP HOUSE
DESIGNED BY:
FINISH GRADE
VALVE BOX FLOOR DRAIN
22 X 34
DWN BY:
& COVER
SCJ
SIZE:
B CONCRETE FINISH
GRADE
150
GEOTEXTILE FABRIC
US Army Corps
3000 (ON TOP AND SIDES)
of Engineers
MIN
1 m³ WASHED
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu521dt brandon.goold 12/19/2019 5:41 PM
TETRA TECH
D.I. FIRE 150 D.I. ANGULAR STONE
PROTECTION MAIN TEE PLACE 31 m³ OF ANGULAR
HYDRANT
1. TRENCH DIMENSIONS ARE 1m x 1m x 1m
SERVICE WASHED STONE FOR
2. SEE SPECIFICATION "33 30 00 - SANITARY SEWER"
RISER DRAINHOLES
FOR GEOTEXTILE INFORMATION
CONCRETE THRUST
BLOCK (SEE DETAILS)
FIRE PUMP HOUSE
NOTES:
INFILTRATION TRENCH DETAIL
WATER DETAILS
SHEET 2 OF 6
SITE DESIGN
SA-459583
WATER / SEWER MAIN HYDRANT 1. ALL BURIED OR PARTIALLY BURIED CONCRETE STRUCTURES
SHALL HAVE THAT PORTION OF THE CONCRETE IN CONTACT
SEPARATION DETAIL CONNECTION DETAIL WITH SOIL SHALL WATERPROOFED PER SPECIFICATION 07 13 53 -
A 4 SCALE = NTS
5 SCALE = NTS
SHEET WATERPROOFING WHICH CONSISTS OF A COAT OF
BITUMEN PRIMER, SHEET MEMBRANE AND PROTECTION BOARD.
SHOULD PROTECTION BOARD NOT BE PRACTICAL TO INSTALL,
ALTERNATIVE PROTECTION FOR THE INSTALLED MEMBRANE
WILL BE ALLOWED IF APPROVED BY CO.
APPR.
13 BARS
DATE
D 45° 45°
45° MAX. MAX.
MAX. H H
H
H 230mm
DESCRIPTION
D
W W
W W
CONCRETE THRUST
APPR. MARK
CONCRETE THRUST CONCRETE THRUST BLOCK AT RISER/FIRE CONCRETE BLOCK
BLOCK SECTION BLOCK AT CAP SUPPORT AT VALVE
SEP
A HYDRANT
CU-523 SCALE = NTS 1 SCALE = NTS
2 SCALE = NTS
3 SCALE = NTS
12-19-19
DATE
A
DESCRIPTION
C
13 BARS
13 BARS
MARK
100%
45°
MAX.
H
SOLICITATION NO.:
CONTRACT NO.:
L
1:2
W
SA-459583--CU521DT
DATE:
L
FILE NAME:
CKD BY:
CONCRETE THRUST
BET
CONCRETE THRUST
JSR
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
CONCRETE THRUST CONCRETE THRUST BLOCK AT VERTICAL BLOCK AT VERTICAL
22 X 34
DWN BY:
SCJ
BLOCK PLAN AT BEND BLOCK PLAN AT TEE CORNER UNDERBEND
SIZE:
B
4 5 6 7
US Army Corps
of Engineers
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu521dt brandon.goold 12/19/2019 5:41 PM
TETRA TECH
BLOCK FOR HORIZONTAL BENDS AND VERTICAL UNDERBENDS CONCRETEBLOCKING
BEARING AREA FOR VARIOUS DIAMETERS (m2)
DEGREE OF BEND FORVALVESUPPORT
SIZE OF
11.25° 22.5° 45° 90° TEE/CAP SIZE OF DEGREE OF BEND
PIPE (mm) SIZE OF VOLUME
PIPE W (mm)
PIPE (mm) (m3)
L (mm) H (mm) W (mm) L (mm) H (mm) W (mm) L (mm) H (mm) W (mm) L (mm) H (mm) W (mm) L (mm) H (mm) W (mm) (mm) 11.25° 22.5° 45° 90° TEE/CAP
200 582 436 236 839 602 402 1193 831 631 1815 1010 919 1815 1010 919 200 0.259 0.515 1.009 1.865 1.865 200 400 0.037
WATER DETAILS
SHEET 3 OF 6
SITE DESIGN
SA-459583
NOTES: GENERAL NOTES
1. ALL BURIED OR PARTIALLY BURIED CONCRETE STRUCTURES
A 1. THRUST BLOCK CALCULATIONS ARE FOR POTABLE WATER, SEWER FORCE MAIN, AND FIRE WATER DISTRIBUTION. SHALL HAVE THAT PORTION OF THE CONCRETE IN CONTACT
WITH SOIL SHALL WATERPROOFED PER SPECIFICATION 07 13 53 -
2. ALL ELBOWS, BENDS, AND CAPS SHALL BE BRACED WITH 14 MPa CONCRETE THRUST BLOCKS. JOINTS SHALL NOT BE SHEET WATERPROOFING WHICH CONSISTS OF A COAT OF
BITUMEN PRIMER, SHEET MEMBRANE AND PROTECTION BOARD.
ENCASED IN CONCRETE. SHOULD PROTECTION BOARD NOT BE PRACTICAL TO INSTALL,
ALTERNATIVE PROTECTION FOR THE INSTALLED MEMBRANE
3. PLACE AND COMPACT BEDDING AND BACKFILL PER SPECIFICATION 31 00 00 AND 33 11 00. WILL BE ALLOWED IF APPROVED BY CO.
2000
100Ø CAST IRON;
PROPOSED FINISH GRADE FRAME SHALL BE
100
APPR.
SECURED TO
CONCRETE AND
SEALED WATER TIGHT
DATE
D
APPLY BITUMASTIC
DAMPROOFING
COATING TO EXTERIOR
SEE MANHOLE
300
BACKFILL WITH
STEP DETAIL
1m MINIMUM
SHEET CU-502 SATISFACTORY
DESCRIPTION
MATERIAL COMPACTED
TO 95% OF MAXIMUM
DENSITY
FLOW
2600
2000
APPR. MARK
SEP
450
200mm DI PIPE
CAST-IN BOOT FOR
12-19-19
WATER TIGHT SEAL
DATE
(TYP.)
150
DESCRIPTION
C 200mm GATE VALVE (TYP)
NOTES: PLAIN CONCRETE PIPE SUPPORT (TYP)
(SEE XS DRAWINGS)
1. CHAMBER AND COVERS SHALL BE RATED FOR H20 LOADING.
2. PROVIDE PROVISIONS AS NECESSARY TO COUNTER ANY BUOYANCY FORCE
GENERATED WHEN THE WATER LEVEL IS AT GRADE.
3. CHAMBERS SHALL BE PRECAST PER SPECIFICATION 03 40 00.00 10 - PLANT-PRECAST
CONCRETE PRODUCTS FOR BELOW GRADE OR CAST-IN-PLACE PER XS-562
MARK
100%
A SECTION
CU-524 SCALE = NTS
SOLICITATION NO.:
COVER (H20 RATED)
CONTRACT NO.:
(760mm CLEAR OPENING)
1:2
SA-459583--CU521DT
DATE:
FILE NAME:
CKD BY:
BET
JSR
S. PAVLOWICH
SUBMITTED BY:
DESIGNED BY:
22 X 34
DWN BY:
SCJ
SIZE:
2000
B
200mm FLEX
US Army Corps
200mm DI PIPE
of Engineers
FLOW
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu521dt brandon.goold 12/19/2019 5:41 PM
TETRA TECH
A
CU-524
300
WATER DETAILS
SHEET 4 OF 6
SITE DESIGN
SA-459583
1. ALL BURIED OR PARTIALLY BURIED CONCRETE STRUCTURES
SHALL HAVE THAT PORTION OF THE CONCRETE IN CONTACT
WITH SOIL SHALL WATERPROOFED PER SPECIFICATION 07 13 53 -
A SHEET WATERPROOFING WHICH CONSISTS OF A COAT OF
BITUMEN PRIMER, SHEET MEMBRANE AND PROTECTION BOARD.
SHOULD PROTECTION BOARD NOT BE PRACTICAL TO INSTALL,
ALTERNATIVE PROTECTION FOR THE INSTALLED MEMBRANE
WILL BE ALLOWED IF APPROVED BY CO.
CU-063
CU-068 CU-064 CU-065 CU-066 CU-067
APPR
R'
R'
(GATE VALVE)
E 369470.788
E 369701.9524
N 2956890.9424 CU-069 CU-070
N 2957078.3467
(GATE VALVE)
E 369472.0883
E 369659.9822
N 2957077.2731
N 2956912.9062
(GATE VALVE)
E 369472.6192 E 369659.2068 06
4.41 1
100 mm DI
FP
N 2957076.8347 N 2956918.2056
E 369658.6657 X
N2
968 .426
E 36 956905
I.EL
=6
.50
400 mm DI
CU-071
E)
(GATE VALV N 2956916.2917
FIRE HYDRANT (TYP) O O E 369657.8956 mm
DI
DATE
400
400 mm DI
mm
N 2956913.5676 400
BRIGADE D I
FIRE HYDRANT (TYP)
E 369701.9375
N 2956885.4907
HEADQUARTERS X
E 3696 897.6608
FP FIRE
(GATE V .5013
ALVE)
HYDRANT
(GATE VALVE) (TYP)
CU-072
I.EL = 6.50
150 mm DI
53
E 369463.6229
5 6
FP
T' T' N 2957068.4474
9
DI
N2
400 m
mm 1 50 m
DI
FP
(G
N E 3 AT
FP E 369670.957
N 2956847.9688
29 69 E V (GA
HEADQUARTERS
400 mm DI
57 43 AL E 3 TE VA (GATE VALVE)
150mm DI
04 9.8 VE N 2 69580 LVE)
3,7
N 2956896.309
BATTALION
(GATE VALVE)
E 369654.5136
(GATE VALVE)
4. 77 ) E 369672.0909
400 mm DI
(GATE VALVE) E 369399.0296 93 3 956 .004
N 2956896.7006
E 369653.2364
FIRE HYDRANT (TYP) 27 899 N 2956847.0327
E 369353.4142 N 2957085.8009 .86
400 mm DI
I.EL = 6.50
ELBOW UP TO
74
N 2957116.5614 150 mm DI Q I.EL
3,4
(GATE VALVE)
E)
M I.EL = 5.50
FP I.EL = 5.50 400 mm DI
FP E 369437.9135 =5
FP
.50 E 369666.6596
E 369735.7243
N 2956789.2132
E 369748.4793
N 2956778.6818
N 2956861.1542
N 2956859.0945
P
U
LV 61 E 369398.3226 N 2956842.764
E 369626.2752
E 369626.6172
1
(GATE VALVE)
(GATE VALVE)
VA 2.64 638 E 369360.565 (GATE VALVE) N 2957084.9447 N 2957052.2559 E
N 369
E 369681.6265 (GATE VALVE)
E
AT 35 5.
3 N 2957116.1199 E 369397.6909 Q 29 4 Y N 2956839.1594 E 369735.0597
GATE VALVE (TYP) E 369749.0581
DESCRIPTION
FIRE HYDRANT (TYP)
(G 369 711 N 2957085.4663
GATE VALVE (TYP) 57 45 E 369682.2863 N 2956789.7619 N 2956778.2039
E 95 04 .85
2 M E 369438.4851
P 5. 75
F1 Z N 2956833.3351
N 2956850.5217
7,
N 2957046.2693 50
L N E 369750.7309
E 369617.4963
5
37 F1 FP400 mm DI
E 369671.9751
N 2956849.2019
FP I.EL = 6.50
FP
FP
4,
N 2956776.8225
(GATE VALVE)
Y
E1
6
20 A'100 mm DI
150 mm DI
6,54
50 .5 73
400
A'
100 mm DI
5. DI E
50
R
mm
53 5.44
I.EL = 6.50
N 369 (GATE VALVE)
5.
= 3 DI
L m 29 4
L
N 2956870.6897
69 11
=
.I E 0 m 57 38 E 369749.6695
E 369593.0699
E 3 957
(GATE VALVE)
I.E
40 04 .62 N 2956777.6999
D1 N
2 4. 42
81 E 369666.2075 Z
R
I.EL (GATE VALVE)
3 N 2956842.2165 (GATE VALVE)
=5
.50
FP W W E 369735.1323 E 369730.4597
E 369625.4026
N 2956860.0974
400 mm DI
N 2956788.4924
N 2956843.7582
E 369664.3404
N 2956755.6645
(GATE VALVE)
D1
I.EL = 5.50
400 mm DI
COMPANY E 369729.8594
N 2957011.8366
N 2956754.9359
E 369441.7731
HEADQUARTERS/HOUSING
E1
ELBOW UP TO
STUB FOR FUTURE
I.EL = 5.50
ELBOW DOWN TO
N 2957112.1687
E 369319.1866
ELBOW DOWN TO
FP
FIRE HYDRANT (TYP) CONNECTION (TYP)
I.EL = 5.50
E 36 400 mm DI
N 2 9583.2
956
878 818
FP (GATE VALVE)
STUB FOR FUTURE
CONNECTION (TYP)
I.EL = 5.50
.1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
E 369660.2336 (GATE VALVE)
K K .771
4 (GATE VALVE) E 369730.5181
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
4,6
E 369636.8655 N 2956787.4496 150 mm DI 400 mm DI
(GATE VALVE) N 2956754.3923
(GATE VALVE)
400mm DI
FIRE PROTECTION N 2956806.6791
I.EL = 6.50
8,02 E 369420.3775 E 369616.2229
WATER LINE (TYP)
I.EL = 6.50
N 2956985.9235 N 2956848.9794 ELBOW DOWN TO
D'
I.EL = 6.50
(GATE VALVE)
I.EL = 4.50
400mm DI
FIRE PROTECTION
O' O' FIRE PROTECTION
E 369419.2472
E 369543.4449 E 369605.3969
FIRE HYDRANT (TYP)
I.EL = 5.50 (GATE VALVE)
(GATE VALVE)
E 369821.9134
E' FIRE HYDRANT
N 2956835.8676
GATE VALVE WATER LINE
WATER LINE (TYP)
N 2956984.5544 S S (GATE VALVE) N 2956882.0086
(GATE VALVE) B' B'
E 369717.6049
N 2956740.085
(GATE VALVE) E 369779.0672
N 2956653.9555
GATE VALVE (TYP)
.3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
E 369198.1484 C' C' E 369776.8988
1,92
P' Q' E 369450.9104
REV.
S'
E 369158.9038 E 369387.5889 Q' V V 150 mm DI N 2956690.5018 150 mm DI
T
N 2957165.9307 N 2956689.2536
N 2957198.3426 E 369299.2423 J N 2957004.8195 I.EL = 5.50 400 mm DI N 2956958.4112 I.EL = 5.50 400 mm DI I.EL = 5.50 400 mm DI 400 mm DI
FP
400 mm DI
FP I.EL = 4.50
FP
400 mm DI I.EL = 4.50
FP N 2957088.0132 FP FP FP FP FP FP 400 mm DI
FP FP FP
I.EL = 5.50
FP FP FP 400 mm DI
FP
I.EL = 5.50
G1
E 369283.5681 E 369292.2265 E 369394.9109 (GATE VALVE) D' E 369777.5754 E 369820.9959
8,02
8,02
I1
N 2957095.3831 N 2957088.2322 N 2957004.6481
E 369659.3158
N 2956786.3379 E 369716.1082
E 369716.685
N 2956738.9701 N 2956688.695 N 2956652.8442 E'
(GATE VALVE) N 2956739.4463
T
J E 369602.9368
(GATE VALVE)
E 369635.3849
(GATE VALVE) FIRE PROTECTION (GATE VALVE) E 369843.6629
ELBOW DOWN TO
N 2956786.9991 N 2956652.1386
I.EL = 4.50
N'
S'
APPR
78 .6
93 993
I1
6
G1
3 6
E 295
FP
FP
N'
DI
m
m
0
59 9 40
51 6
31. .50
2
693 99
3 6
E 295
04-03-2020
400 mm DI
18-07-2020
N 2957144.5417
E 369112.1369
DATE
(GATE VALVE)
FP 400 mm DI
FP
N 2956953.7549 N 2956965.3324
(GATE VALVE)
N 2957123.4894
E 369094.7548
NOTES:
150 mm DI
FOR APPROVAL
M' M'
DESCRIPTION
N 2956953.0821
(GATE VALVE)
E 369298.9642
N 2956954.3316
(GATE VALVE)
E 369298.8175
I
D
m
m
FP
0
40 4,2
I.EL = 6.00
FP FIRE PROTECTION WATER LINE (TYP)
N 2957119.3764
E 369051.6828
PROTECTION.
OTHERWISE.
400 mm DI
400 mm DI
(GATE VALVE)
E 369048.6082
E 369032.9787 N 2957077.0659
N 2957088.0153 E 369047.8406 (GATE VALVE)
N 2957076.1366
I.EL = 5.50
REV.
E 369035.0864 851,800 L
N 2957088.2304
I.EL = 6.00
01
00
FP
FP
250x400 REDUCER
400 mm DI
300 mm DI
E 369020.7009
(GATE VALVE) N 2957081.8529 (GATE VALVE)
E 369036.4242 L' L'
FDC
851,800 L
E 369237.7292 N 2956877.8352
E 369020.2094
N 2957061.5769
E 369243.4491
AS SHOWN
(GATE VALVE) E 369019.7179
N 2957080.6624
300 mm Ø DI FIRE WATER RETURN
(GATE VALVE)
N 2956870.9075
E 369007.6602
(GATE VALVE)
TEE (TYP) E 369035.7873
N 2957060.8059
SOLICITATION NO.:
E 369006.7621
N 2957064.9711
N 2956860.3849
N 2956870.1872
150 mm DI
CONTRACT NO.:
(GATE VALVE)
E 369237.1344
400 mm DI
N 2956871.471
C1
E 369237.0467
E 369229.041
E 369005.669
N 2957063.6471
400 mm DI
(GATE VALVE)
PLOT SCALE:
K'
ISSUE DATE:
E 368993.6127 4,2
4,92
N 2956852.2929
N 2957049.0453
E 369214.5727
(GATE VALVE)
DI
m
0m
(GATE VALVE)
40
E 368995.5108 G
E 369219.5068
H
I.EL = 6.00
N 2957033.165 K'
E 369214.4352
N 2956850.7054
(GATE VALVE)
N 2956851.7169
E 369215.2704
REFERENCES : IFC.DRAWING.
F F
(GATE VALVE)
E 369194.1413
N 2956827.4341
M.AYESH
4,2
FILE NO.:
N 2956826.904
E 369194.7833
CKD BY:
(GATE VALVE)
N 2956825.529
E 369194.1719
SUBMITTED BY:
DI
m
0m
15
DESIGN BY:
DRAWN BY:
FIRE HYDRANT
A0
400 mm DI
IMRAN
SIZE:
ELBOW UP TO
N 2956812.8991
E 369192.2975
I.EL = 6.00
FP
[] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] []
I.EL = 5.50
B1 B1
4,2
D D
US Army Corps
E E
of Engineers
400 mm DI
FP
INVERT ELEVATION
N 2956744.3737
ELBOW DOWN / UP
N 2956744.232
E 369134.4275
E 369135.723
(GATE VALVE)
N 2956742.1946
E 369136.8951
VALVE CHAMBER
SECTION MARKS
LEGEND:
SAUDI TELECOMMUNICATION
COMPANY BUILDING
I.EL = 5.50
GATE VALVE
PROJECT DESIGNER
TETRA TECH
GATE VALVE (TYP)
DUCT IRON
C C B B
TYPICAL
150 mm DI
STUB FOR FUTURE
CONNECTION (TYP)
E 369135.1256
N 2956743.6556
FIRE HYDRANT
3) I.EL
4) TYP
1 ) FP
2) DI
6)
5)
8)
7)
SA-459583
A1 A1
ARCHITECT
STRUCTURAL
SHOP DRAWING
ELECTRICAL
SHEET ID
MECHANICAL
-
TELECOM
FIRE PROTECTION
CU-063
KEYPLAN:
APPR
R' CU-069 CU-070
DATE
E 369470.788
R' N 2957078.3467 CU-072
E 369472.0883
N 2957077.2731
(GATE VALVE)
DESCRIPTION
E 369472.6192
N 2957076.8347
100 mm DI
FP FP FP FP FP
O O
.1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE HYDRANT (TYP)
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
FP
400
mm
FP
.3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
REV.
FP DI
BRIGADE FIRE HYDRANT (TYP)
HEADQUARTERS FP
APPR
FP
FP
150 mm DI
E 369463.6229
T' T' N 2957068.4474
04-03-2020
18-07-2020
FP
DATE
FP
(G
E
N 3 AT
NOTES:
29 69 E V
mm DI
FP
04 9.8 VE
150mm DI
(GATE VALVE)
FOR APPROVAL
DESCRIPTION
E 369399.0296 4. 77 )
(GATE VALVE) FIRE HYDRANT (TYP) 93 3
400
FP
E 369353.4142 N 2957085.8009 27
N 2957116.5614 150 mm DI Q
3,4
)
M FP
I.EL = 5.50FP FP FP FP
I.EL
FP
= 5.50 FP FP
400 mm FP
DI
PROTECTION.
E
P
OTHERWISE.
V 61 E 369398.3226 E 369437.9135
FP
L
A .64 38 E
E 369360.565 N 2957084.9447 N 2957052.2559
FP
V
E 52 .36 (GATE VALVE) N 369
N 2957116.1199 Q
REV.
T
A 93 15 E 369397.6909 29 4
01
00
G
( 36 71 GATE VALVE (TYP) 57 45
FP
E 95 N 2957085.4663 04 .85
M E 369438.4851
2 P 5. 75
FP
7,
FP
N 2957046.2693 50
L N
5
AS SHOWN
37
6
4,
SOLICITATION NO.:
50 52 473 E3
5. DI .
5P0
CONTRACT NO.:
FP
F
5 N 69
.
= m
PLOT SCALE:
3 15
ISSUE DATE:
29 4
L
L 9
=
I.E 0 m 6 71 57 38
L
3
FP
.I E
40 E 95 04 .62
D1 N
2 4. 42
FP
FP
81
R
3
REFERENCES : IFC.DRAWING.
M.AYESH
FILE NO.:
CKD BY:
D1
I.EL = 5.50
SUBMITTED BY:
N 2957011.8366
E 369441.7731
DESIGN BY:
DRAWN BY:
A0
FP
ELBOW UP TO
FP
I.EL = 5.50
IMRAN
ELBOW DOWN TO
SIZE:
N 2957112.1687
E 369319.1866
I.EL = 5.50
MATCH LINE (CU-68)
K K
FP
US Army Corps
400mm DI
E 369420.3775
of Engineers
8,02
INVERT ELEVATION
ELBOW DOWN / UP
N 2956985.9235
VALVE CHAMBER
SECTION MARKS
I.EL = 4.50
400mm DI
LEGEND:
O' O' FIRE PROTECTION
FP
GATE VALVE
PROJECT DESIGNER
TETRA TECH
FP
E 369419.2472
DUCT IRON
WATER LINE (TYP) S S
TYPICAL
N 2956984.5544
E 369387.5889 P' Q' Q'
I.EL = 4.50
E 369299.2423
N 2957088.0132
J N 2957004.8195 I.EL = 5.50
FP FP
400 mm DI
FP
FP FP FP FP
3) I.EL
4) TYP
1 ) FP
E 369283.5681
2) DI
E 369292.2265 E 369394.9109
N 2957095.3831
6)
5)
N 2957088.2322
8)
7)
N 2957004.6481
(GATE VALVE)
SA-459583
(GATE VALVE)
89 P'
COORDINATION CLEARANCE
DIFP DEPARTMENT CONT. Q/C
m
m ARCHITECT
400 9
1 5 9
FP . 5 06 STRUCTURAL
E 29
MATCH LINE (CU-70) N MECHANICAL
SHEET ID
-
PLAN CU-064 TELECOM
APPR
CU-069 CU-070
CU-071
DATE
E 369701.9524 CU-072
N 2956890.9424
DESCRIPTION
400 mm DI
FP FP
.1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
.3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
REV.
400 mm DI
APPR
IN DIAMETER OR LARGER PER MANUFACTURERS RECOMMENDATION.
FP
04-03-2020
L = 6.50
18-07-2020
DATE
I.EFP
NOTES:
FOR APPROVAL
DESCRIPTION
HEADQUARTERS
FP
E 369672.0909
400 mm DI
N 2956847.0327
PROTECTION.
OTHERWISE.
(GATE VALVE) E 369735.7243 E 369748.4793
FP
REV.
N 2956842.764
01
00
E 369681.6265 (GATE VALVE)
MATCH LINE (CU-65)
Y N 2956839.1594 E 369735.0597
GATE VALVE (TYP) E 369749.0581
N 2956778.2039
AS SHOWN
E 369682.2863 N 2956789.7619
FP
Z N 2956833.3351
SOLICITATION NO.:
E 369671.9751
N 2956849.2019
400 mm DI I.EL FP
= 6.50
CONTRACT NO.:
MARCH 03, 2020
N 2956776.8225
FP FP FP FP FP FP FP
(GATE VALVE)
PLOT SCALE:
ISSUE DATE:
A'100 mm DI
6,54
A'
100 mm DI
I.EL
(GATE VALVE)
FP
FP
E 369749.6695
= 6.50
N 2956777.6999
REFERENCES : IFC.DRAWING.
Z
M.AYESH
E 369666.2075
FILE NO.:
CKD BY:
FP
SUBMITTED BY:
FP
400 mm DI
N 2956788.4924
N 2956843.7582
E 369664.3404
N 2956755.6645
DESIGN BY:
DRAWN BY:
(GATE VALVE)
A0
400 mm FP
COMPANY E 369729.8594
IMRAN
SIZE:
HEADQUARTERS/HOUSING N 2956754.9359
FP
ELBOW DOWN TO
DI
FIRE HYDRANT (TYP)
STUB FOR FUTURE
US Army Corps
E 369660.2336 (GATE VALVE)
FP
of Engineers
(GATE VALVE) N 2956787.4496
E 369730.5181
INVERT ELEVATION
E 369636.8655
ELBOW DOWN / UP
N 2956754.3923 150 mm DI 400 mm DI
FP
VALVE CHAMBER
SECTION MARKS
LEGEND:
N 2956806.6791
GATE VALVE
PROJECT DESIGNER
TETRA TECH
DUCT IRON
I.EL = 6.50
ELBOW DOWN TO
D'
TYPICAL
I.EL = 6.50
I.EL = 5.50 (GATE VALVE)
FP
FP
E 369717.6049 (GATE VALVE)
(GATE VALVE)
B' B'
FP
N 2956740.085 E 369779.0672
C' C' E 369776.8988
1,92
150 mm DI N 2956690.5018
3) I.EL
N 2956689.2536
4) TYP
1 ) FP
2) DI
400 mm DIFP I.EL = 5.50FP 400 mm DI 400 mm DI
G1
FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP FP
6)
5)
8)
7)
(GATE VALVE) D' E 369777.5754
I1
E 369659.3158 E 369716.685
SA-459583
PLAN CU-066
H1 H1 I1
G1
ARCHITECT
STRUCTURAL
SHOP DRAWING
ELECTRICAL
SHEET ID
MECHANICAL
-
TELECOM
FIRE PROTECTION
CU-066
MATCH LINE (CU-66)
FP FP
E 369820.9959
N 2956652.8442
I.EL = 5.50
150 mm DI
E 369821.9134
N 2956653.9555
(GATE VALVE)
E 369821.8504
N 2956652.1386
E'
E'
FP
FP
FIRE HYDRANT
E 369843.6629
GATE VALVE (TYP)
N 2956634.1287
FP
CONNECTION (TYP)
STUB FOR FUTURE
400 mm DI
SCAL 1:400
PLAN CU-067
NOTES:
LEGEND: REFERENCES : IFC.DRAWING.
1 ) FP 1. REFFER TO IFC DRAWINGS FROM CU - 100 TO CU - 526 .1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE PROTECTION LINE OTHERWISE.
2) DI DUCT IRON .2 - ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE INDICATED.
3) I.EL INVERT ELEVATION .3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
PROTECTION.
4) TYP TYPICAL
.4 - ALL SECTON MARKS SEE DRAWINGS NUMBER FROM CU-041 TO CU-137
CU-072
CU-071
CU-069 CU-070
5) GATE VALVE
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
6) ELBOW DOWN / UP
KEYPLAN:
TELECOM
ELECTRICAL
MECHANICAL
STRUCTURAL
7) SECTION MARKS
DEPARTMENT
FIRE PROTECTION
8) VALVE CHAMBER
OTHER TRADES
CONT.
Q/C
COORDINATION CLEARANCE
CU-068 CU-064 CU-065 CU-066 CU-067
ROYAL SAUDI LAND FORCES PROJECT DESIGNER DESIGN BY: ISSUE DATE:
MARCH 03, 2020
24th ARTILLERY BRIGADE
DRAWN BY: CKD BY:
SA-459583 SOLICITATION NO.:
TETRA TECH IMRAN M.AYESH
EASTERN PROVINCE, KINGDOM OF SAUDI ARABIA
-
US Army Corps
SHEET ID
CU-067
ELBOW DOWN TO
E 369094.7548 (GATE VALVE) I.EL = 4.50
N 2957123.4894 E 369112.1369
N 2957144.5417
FP
E 369158.9038
N 2957198.3426
FP
FP
FP
FP
FP
400 mm DI
FP
GATE VALVE
E 369198.1484
N 2957165.9307
SCAL 1:400
PLAN CU-064
FP FP
I.EL = 4.50
FP
400 mm DI
FP
FP
NOTES:
LEGEND: REFERENCES : IFC.DRAWING.
1 ) FP 1. REFFER TO IFC DRAWINGS FROM CU - 100 TO CU - 526 .1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE PROTECTION LINE OTHERWISE.
2) DI DUCT IRON .2 - ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE INDICATED.
3) I.EL INVERT ELEVATION .3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
PROTECTION.
4) TYP TYPICAL
.4 - ALL SECTON MARKS SEE DRAWINGS NUMBER FROM CU-041 TO CU-137
CU-072
CU-071
CU-069 CU-070
5) GATE VALVE
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
6) ELBOW DOWN / UP
TELECOM
ELECTRICAL
MECHANICAL
STRUCTURAL
7) SECTION MARKS
DEPARTMENT
FIRE PROTECTION
8) VALVE CHAMBER
OTHER TRADES
KEYPLAN:
CONT.
Q/C
CU-068 CU-064 CU-065 CU-066 CU-067
COORDINATION CLEARANCE
* DRAWING IS COORDINATED WITH
ROYAL SAUDI LAND FORCES PROJECT DESIGNER DESIGN BY: ISSUE DATE:
MARCH 03, 2020
24th ARTILLERY BRIGADE
DRAWN BY: CKD BY:
SA-459583 SOLICITATION NO.:
TETRA TECH IMRAN M.AYESH
EASTERN PROVINCE, KINGDOM OF SAUDI ARABIA
-
CU-068
A1
MATCH LINE (CU-071)
NOTES:
LEGEND: REFERENCES : IFC.DRAWING.
1 ) FP 1. REFFER TO IFC DRAWINGS FROM CU - 100 TO CU - 526 .1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE PROTECTION LINE OTHERWISE.
2) DI DUCT IRON .2 - ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE INDICATED.
3) I.EL INVERT ELEVATION .3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
PROTECTION.
4) TYP TYPICAL
CU-072
CU-071
CU-069 CU-070
TELECOM
ELECTRICAL
MECHANICAL
STRUCTURAL
7) SECTION MARKS
DEPARTMENT
FIRE PROTECTION
8) VALVE CHAMBER
OTHER TRADES
CONT.
Q/C
COORDINATION CLEARANCE
CU-068 CU-064 CU-065 CU-066 CU-067
ROYAL SAUDI LAND FORCES PROJECT DESIGNER DESIGN BY: ISSUE DATE:
MARCH 03, 2020
24th ARTILLERY BRIGADE
DRAWN BY: CKD BY:
SA-459583 SOLICITATION NO.:
TETRA TECH IMRAN M.AYESH
EASTERN PROVINCE, KINGDOM OF SAUDI ARABIA
-
CU-072
TEE (TYP)
300 mm Ø DI FIRE WATER RETURN
E 369006.7621
E 368993.6127
E 369005.669
E 369051.6828
(GATE VALVE)
N 2957064.9711
N 2957049.0453
E 369020.7009
E 369020.2094
N 2957063.6471
(GATE VALVE) E 369019.7179
(GATE VALVE) N 2957081.8529
N 2957119.3764
N 2957081.2577
FIRE PUMP HOUSE
N 2957080.6624
250x400 REDUCER
150 mm DI
4,92
FP
FP
FDC
FP
40
0
FR
FP
m
m
DI
300 mm DI
FP
300 mm DI
FR
FP
FP
400 mm DI
400 mm
(GATE VALVE)
400 mm DI
E 369032.9787
E 369035.0864
DI
E 369007.6602
N 2957088.0153
N 2957088.2304
FP
N 2957064.2296
E 368995.5108
N 2957033.165
400 mm DI
FP FP FP FP FP
FP
E 369094.7548 (GATE VALVE)
N 2957123.4894 E 369112.1369
(GATE VALVE)
E 369036.4242
N 2957144.5417
N 2957061.5769
MATCH LINE (CU-68)
E 369035.7873
(GATE VALVE)
E 369047.8406
N 2957060.8059
E 369048.6082
I.ELFP= 5.50
N 2957076.1366
(GATE VALVE)
N 2957077.0659
K'
K'
FP
851,800 L
851,800 L
E 369034.5967
N 2957000.893
(GATE VALVE)
(GATE VALVE)
FP
H
H
FIRE STORAGE TANK
I.EL = 5.50
FP
SCAL 1:400
PLAN CU-068
ELBOW DOWN TO
FP
C1
FP
C1
FP FP
I.EL = 6.00
FP
400
FP
FPFP
mm DI
4,18
FP
1 ) FP 1. REFFER TO IFC DRAWINGS FROM CU - 100 TO CU - 526 .1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE PROTECTION LINE OTHERWISE.
2) DI DUCT IRON .2 - ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE INDICATED.
3) I.EL INVERT ELEVATION .3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
PROTECTION.
4) TYP TYPICAL
.4 - ALL SECTON MARKS SEE DRWAINGS NUMBER FROM CU-041 TO CU-138
CU-072
CU-071
CU-069 CU-070
5) GATE VALVE
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
KEYPLAN:
6) ELBOW DOWN / UP
TELECOM
ELECTRICAL
MECHANICAL
STRUCTURAL
7) SECTION MARKS
DEPARTMENT
FIRE PROTECTION
8) VALVE CHAMBER
OTHER TRADES
CONT.
Q/C
CU-068 CU-064 CU-065 CU-066 CU-067
COORDINATION CLEARANCE
* DRAWING IS COORDINATED WITH
ROYAL SAUDI LAND FORCES PROJECT DESIGNER DESIGN BY: ISSUE DATE:
MARCH 03, 2020
24th ARTILLERY BRIGADE
DRAWN BY: CKD BY:
SA-459583 SOLICITATION NO.:
TETRA TECH IMRAN M.AYESH
EASTERN PROVINCE, KINGDOM OF SAUDI ARABIA
-
CU-069
FP
FP
FP
(GATE VALVE)
N 2956924.4904
E 369127.1312
FP FP
I.EL = 6.00
FP
FP
FP
FP
FP
FP
400 mm DI
L'
M'
(GATE VALVE)
FIRE HYDRANT (TYP)
E 369214.5727
N 2956852.2929
FP
(GATE VALVE)
M'
I
E 369298.8175
G
N 2956954.3316
L'
(GATE VALVE)
FIRE HYDRANT
I.EL = 6.00 E 369237.0467 I.EL = 6.00
4,2
400 mm DI 150 mm DI
SCAL 1:400
FP 40 N 2956871.471 FP FP
I.EL = 6.00 FP FP FP FP FP FP FP FP FP
DI
400 mm FP FP
PLAN CU-070
0m
FP m FP FIRE PROTECTION WATER LINE (TYP) (GATE VALVE)
4,2
(GATE VALVE) DI 150 mm DI E 369245.1589
E 369298.9642
G
400FPmm DI (GATE VALVE)
I
E 369214.4352 N 2956887.9162
3
N
6
N 2956953.7549 N 2956965.3324
6
1
E 369215.2704 E 369237.1344
9 99
E 369237.7292 N 2956877.8352
1
N 2956870.1872
3 2.
N 2956851.7169
N 2956870.9075
.5 506
E 369219.5068
MATCH LINE (CU-64)
59 9
N 2956856.8478
NOTES:
LEGEND: REFERENCES : IFC.DRAWING.
1 ) FP 1. REFFER TO IFC DRAWINGS FROM CU - 100 TO CU - 526 .1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE PROTECTION LINE OTHERWISE.
2) DI DUCT IRON .2 - ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE INDICATED.
3) I.EL INVERT ELEVATION .3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
PROTECTION.
4) TYP TYPICAL
.4 - ALL SECTON MARKS SEE DRWAINGS NUMBER FROM CU-041 TO CU-138
CU-072
CU-071
CU-069 CU-070
5) GATE VALVE
.5 - CONTRACTOR SHALL INSTALL MECHANICAL RESTRAINTS ON ALL DUCTILE IRON PIPES 400mm
6) ELBOW DOWN / UP
TELECOM
ELECTRICAL
MECHANICAL
STRUCTURAL
KEYPLAN:
7) SECTION MARKS
DEPARTMENT
FIRE PROTECTION
8) VALVE CHAMBER
OTHER TRADES
CONT.
Q/C
CU-068 CU-064 CU-065 CU-066 CU-067
COORDINATION CLEARANCE
* DRAWING IS COORDINATED WITH
ROYAL SAUDI LAND FORCES PROJECT DESIGNER DESIGN BY: ISSUE DATE:
MARCH 03, 2020
24th ARTILLERY BRIGADE
DRAWN BY: CKD BY:
SA-459583 SOLICITATION NO.:
TETRA TECH IMRAN M.AYESH
EASTERN PROVINCE, KINGDOM OF SAUDI ARABIA
-
CU-070
[]
[]
[]
FP
[]
[]
FP
[]
[]
FP
[]
[]
FP
[]
[]
FP
[]
[]
FP
[]
COMPANY BUILDING
[]
SAUDI TELECOMMUNICATION
INSET BUILDING
[]
FP
[]
[]
[]
FP
[]
[]
FP
E
B1
[]
C
[]
FP
FIRE HYDRANT
C
F
E
FP
(GATE VALVE)
(GATE VALVE)
E 369134.4275 E 369194.1413
G
B
N 2956744.232 N 2956827.4341
GUARD HOUSE
FIRE HYDRANT
I.EL = 6.00
4,2
E 369135.723
D
SCAL 1:400
N 2956744.3737 DI FP FP FP
PLAN CU-071
0 mm
15 FP E 369194.7833 (GATE VALVE)
G
N 2956826.904
4,2
E 369214.4352
[]
150 mm DI
I.EL = 5.50 400 mm DI 400 mm DI
FP FP FP FP FP
I.EL =FP5.50 FP FP FP
(GATE VALVE) N 2956850.7054
E 369135.1256 E 369192.2975
E 369136.8951 E 369194.1719 E 369215.2704
[]
B
N 2956743.6556 N 2956812.8991
N 2956742.1946 N 2956825.529 N 2956851.7169
D
MATCH LINE (CU-70)
ELBOW UP TO E 369219.5068
B1
NOTES:
LEGEND: REFERENCES : IFC.DRAWING.
1 ) FP 1. REFFER TO IFC DRAWINGS FROM CU - 100 TO CU - 526 .1 - ALL DIMENSIONS ARE IN MILLIMETERS & LEVELS, ELEVATIONS IN METERS UNLESS NOTED
FIRE PROTECTION LINE OTHERWISE.
2) DI DUCT IRON .2 - ALL FIRE PROTECTION LINES ARE 400mm DI UNLESS OTHERWISE INDICATED.
3) I.EL INVERT ELEVATION .3 - ALL DUCTILE IRON AND COPPER PIPE ARE TO BE POLY WARPPED FOR CORROSION
PROTECTION.
4) TYP TYPICAL
CU-072
CU-071
CU-069 CU-070
TELECOM
ELECTRICAL
MECHANICAL
STRUCTURAL
7) SECTION MARKS
DEPARTMENT
FIRE PROTECTION
8) VALVE CHAMBER
OTHER TRADES
CONT.
Q/C
CU-068 CU-064 CU-065 CU-066 CU-067
COORDINATION CLEARANCE
* DRAWING IS COORDINATED WITH
ROYAL SAUDI LAND FORCES PROJECT DESIGNER DESIGN BY: ISSUE DATE:
MARCH 03, 2020
24th ARTILLERY BRIGADE
DRAWN BY: CKD BY:
SA-459583 SOLICITATION NO.:
TETRA TECH IMRAN M.AYESH
EASTERN PROVINCE, KINGDOM OF SAUDI ARABIA
-
CU-071
21 DI Pipe Yes R
22 DI Fittings Yes R
23 Joints Material-Push on Joints Yes R
24 Joints Material-Flanged Joints Yes R
SECTION III - GOVERNMENT REVIEW REMARKS
Item #21, 22, 23, 24 - Code is (R)
- Government concur with DOR statement, but pipe, fitting and connections standards changed from AWWA to ISO and BSEN
standards shall fulfill all other installation, testing, commissioning and operation requirements of 33 11 00 section.
- All product/material connected to or part of potable or fire water networks such as valves shall be in compliance with the new pipe,
fittings and joints standards.
- All previously submitted and accepted material/product under section 33 11 00 in compliance with AWWA standard shall be
incompliance with the new ISO and BSEN standard. (Fire Hydrant, polyethylene sheet), resubmit if required
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the
general method of construction, materials, detailing and other information are satisfactory. This does not relieve the Contractor from
the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring
removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement
to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the
technical specifications so prescribe.
Technical Submittal for the Ductile iron Pipe, Fittings & Gaskets (Potable & Fire Water Line)
Material Approval. (SADIP- AMIANTIT)
Narratives:
Specification 33 11 00 Page 06 & 07 clause 2.1.1.1.1 & 2.1.1.1.2.a/c.
Complies with BSEN 545, IS0 2531/4633/8179/4179.
Attachments:
1. Narratives.
2. Project Specifications cut sheets.
3. Variation form
4. Technical Comparison sheet
5. RFI to DOR and USACE
6. Catalogue & Dimensional Data.
7. Storage, Laying instructions.
8. Certificates (ISO/SASO/FM/WRAS/NSF for gasket/Conformity
Certificates).
Note: Pipe and fittings are manufactured as per BS-EN & ISO, complies
with WRAS for lead content requirements which is equivalent to NSF
(refer page 89-90)
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.2 DEFINITIONS
Water mains include water piping having diameters 100 through 350 mm,
specific materials, methods of joining and any appurtenances deemed
necessary for a satisfactory system.
Water service lines include water piping from a water main to a building
service at a point approximately 1.5 m from building or the point
indicated on the drawings, specific materials, methods of joining and any
appurtenances deemed necessary for a satisfactory system.
1.3 SUBMITTALS
Connections; G M/R
Valves
Valve Boxes
SECTION 33 11 00 Page 4
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Fire Hydrants
Pipe Restraint
Tapping Sleeves
Bacteriological Samples; G M
Leakage Test; G M
Hydrostatic Test; G M
SD-07 Certificates
Lining
Valves
Fire Hydrants
Comply with NSF/ANSI 14 or NSF/ANSI 61 and NSF 372 for materials for
potable water systems; comply with lead content requirements for
"lead-free" plumbing as defined by the U.S. Safe Drinking Water Act
effective January 2014. Provide materials bearing the seal of the
National Sanitation Foundation (NSF) for potable water service.
Comply with NFPA 24 for materials, installation, and testing of fire main
piping and components.
Inspect materials delivered to site for damage. Unload and store with
minimum handling and in accordance with manufacturer's instructions.
Store materials on site in enclosures or under protective covering. Store
plastic piping, jointing materials and rubber gaskets under cover out of
direct sunlight. Do not store materials directly on the ground. Keep
inside of pipes, fittings, valves, fire hydrants, and other accessories
free of dirt and debris.
SECTION 33 11 00 Page 5
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
1.5.2 Handling
This section covers both the potable water and fire water distribution
systems from the water source to facilities served. For the potable water
system this includes piping and appurtenances from the municipal point of
connection to a point 1.5 m from the facility served including the fire
water tanks. For the fire water system this includes piping and
appurtenances connecting fire water tanks to the fire pump house and the
fire pump house to a point 1.5 m outside the facilities served. This
includes above grade piping at the fire water tanks and the above grade
piping running into the fire pump station and hydrants.
PART 2 PRODUCTS
2.1 MATERIALS
Pipe, except flanged pipe, AWWA C151/A21.51, Pressure Class 150 for
Potable Water lines and 200 for Fire Water Lines. Flanged pipe,
AWWA C115/A21.15. Fittings, AWWA C110/A21.10 or AWWA C153/A21.53;
fittings with push-on joint ends are to meet the same requirements as
fittings with mechanical-joint ends, except for the factory modified bell
design. Provide fittings with pressure ratings equivalent to that of the
pipe. Provide compatible pipe ends and fittings for the specified
joints. Provide cement-mortar lining, AWWA C104/A21.4, standard thickness
on pipe and fittings.
SECTION 33 11 00 Page 6
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Provide push-on joints or mechanical joints for pipe and fittings unless
otherwise indicated. Provide mechanical joints where indicated. Provide
flanged joints where indicated. Provide mechanically coupled type joints
using a sleeve-type mechanical coupling where indicated. Sleeve-type
mechanical couplings in lieu of push-on joints are acceptable, subject to
the limitations specified in the paragraph SLEEVE-TYPE MECHANICAL
COUPLINGS.
a. Push-On Joints: Shape of pipe ends and fitting ends, gaskets, and
lubricant for joint assembly as recommended in AWWA C111/A21.11.
Provide ASTM B88M, Type K copper tubing. Provide AWWA C800 fittings.
AWWA C800 includes ASME B1.20.3, ASME B1.20.1, ASME B16.18 solder-type
joint fittings.
2.1.2 Valves
b. AWWA C509 or AWWA C515: nonrising stem type with mechanical-joint ends
or resilient-seated gate valves 80 to 300 mm in size
SECTION 33 11 00 Page 7
100% Site and Facility Design Submittal
RFI NO. PAGE NO.
Request for Information Report (RFI) RFI-0024 Page 1 of 1
CONTRACT NO. CONTRACT TITLE PRIME CONTRACTOR
W912ER19C0001 NA Artillery Brigade Base RSLF-AC Saudi Al Yamama Company for Trading
US Army Corps
and Contracting
of Engineers
N0003543
Contractor's Request for Information
REQUESTED BY DATE REQUESTED POTENTIAL COST IMPACT Yes
Theodoros Stergiopoulos - March 03, 2020 POTENTIAL SCHEDULE IMPACT Yes
theo@yc.com.sa
RFI SUBJECT Ductile Iron Pipes and Fittings
SPECIFICATION SECTIONS 33 11 00
DRAWINGS
SUBCONTRACTOR
Information Requested
As per the above mentioned specs it is recommend to follow AWWA standards (Pipe, except flanged pipe, AWWA C151/A21.51, Pressure Class
150 for Potable Water lines and 200 for Fire Water Lines. Flanged pipe, AWWA C115/A21.15. Fittings, AWWA C110/A21.10 or AWWA
C153/A21.53.).
Ductile iron pipes and fittings following AWWA standards are not available on the local market, and importing them from outside will cause adverse
delay to the project.
RFI was raised to the project DOR in this regard and after review with the related codes, it was accepted to follow BESN and ISO by the DOR.
(Attached Copy)
Contractor Recommendation
AYC recommend to change the standard to be following BSEN and ISO as per the attached RFI.
The acceptance to change to the local available material with applicable standard codes will actively support to finish the project eventually.
Contractor Attachments
Document Package: March 03, 2020
RFI-0024 - RFI-M-0006.pdf
Government Response
ANSWERED BY DATE RECEIVED DATE ANSWERED
TITLE March 05, 2020 March 05, 2020
- Submit the proposed product data with the required information per SECTION 01 33 00.12 10, Para. 3.6 with the new required new design
analysis and drawings
We believe that the above response represents a "NO COST" clarification that does not require any adjustment to the existing terms of the
contract. If you believe that the above response represents a change to the terms of the contract, you are hereby requested to immediately notify
the Contracting Officer, in writing, prior to taking any action regarding the subject of this RFI response. If you do not provide a written notification
within five (5) calendar days, indicating your position, and providing your request for an equitable contract adjustment associated with the above
response, it will be assumed that you agree that this is a "NO COST" clarification and that an adjustment to the contract price and/or duration is
not required; in which case, we will consider this matter closed.
Government Attachments
Document Package:
March 05, 2020
RFI-0024 Response - RFI_Form.PDF
RFI FORM
Saudi Arabian Ductile Iron Pipe
Co. Ltd (SADIP)
Ductile Iron Pipes, Fittings and Accessories
Table of Contents
3
1 AMIANTIT – 2 Introduction
Group of Companies
The AMIANTIT Group is a leading global industrial SADIP Saudi Arabian Ductile Iron Pipes Co. Ltd
organisation that manufactures high quality pipe (SADIP) is one of AMIANTIT Group of Companies.
systems, researches, develops, owns and licenses It was established in 1988 when a joint venture
advanced pipe technologies and provides water between AMIANTIT Group and Saint Gobain (Pont
management services. A. Mousson) was made.
4
4
7 Technical Comparison
10
10
8 Maximum Pressures
The maximum pressures for SADIP pipeline components are indicated in the table below (The components are
designed to accept the following values):
Values given in the table Values given in the table + 20% Values given in the table + 50%
All SADIP pipes and fittings are subjected to factory hydrostatic test pressure 100% as follows:
Pipes Fittings
p in bar
600
500
Measured
400 bursting
pressure
300
Calculated
200 bursting
pressure
100 Maximum
allowable
pressure
DN 100 150 200 250 300 350 400 450 500 The graph shows that bursting pressure is more
than double the maximum allowable pressure.
11 11
9 Pipe Joints
The standard joints for the pipes are designed so Pipes Deflection
that contact pressure between the gasket and the
metal increases as the water pressure increases, SADIP socket – spigot joints permits angular deflection
thus a perfect seal is guaranteed. which gives the following advantages:
The rubber gasket for the pipes is standard type where • Accommodation of ground movements as shown
a triduct gasket is offered for fittings which similar to in the diagrams below.
tyton joint. These gaskets are EDPM rubber according
to ISO 4633. • Allowing adjustment while installation.
DN DN DN DN DN
80 – 150 200 – 300 350 – 600 700 – 800 900 – 1600
5˚ 4˚ 3˚ 2˚ 1˚ 30
Ground level
Contact
pressure
tact
Con ure
s
pres
Safety
ter re
Wa essu
pr
12
12
10 Product Range
10.1 Pipe
Ductile iron (socket & spigot) pipes are manufac- External Coating
tured by centrifugal process to meet in every aspect
the requirements of International standard ISO 2531, Pipes are coated externally by pure metallic zinc
BSEN 545. (minimum 99.995 purity) at a rate of 200 g/m 2 , which
represents 50 % more than the requirement of ISO 8179
The standard e ective length of the pipe is 6.0 meters. (DN 1100 mm and above 130 g/m 2 or 200 g/m 2 as per
However, 10% of the pipes can be supplied shorter than customer request).
6 meters as per ISO 2531. Zinc is then covered by 120 microns of bituminous paint
as per ISO 8179-1.
SADIP can o er any di er
Internal Coating per customer requirement.
13 13
10.2 Coating
Zinc coating
DN 100 (4 inch) 75
DN 125 (5 inch) 91
DN 150 (6 inch) 107
DN 200 (8 inch) 140
DN 250 (10 inch) 173
DN 300 (12 inch) 205
DN 350 (14 inch) 238
DN 400 (16 inch) 270
DN 450 (18 inch) 302
DN 500 (20 inch) 335
DN 600 (24 inch) 399
DN 700 (28 inch) 464
DN 800 (32 inch) 530
DN 900 (36 inch) * 386
DN 1000 (40 inch) * 428
DN 1100 (44 inch) * 471
DN 1200 (48 inch) * 513
DN 1400 (56 inch) * 598
DN 1500 (60 inch) * 640
DN 1600 (64 inch) * 682
* 130 g/m2
14
14
PU coating (internal and external) Cement lining
One hundred percent solids plural components Cement lining is applied internally by a centrifugal
polyurethane are protecting many different structures process, in which the mortar is introduced into the
today, such as storage tanks, oil and gas piping, pipe and rotated at high speed, giving excellent
water and wastewater tank internals, bridges, ships compaction.
and other marine facilities.
The lining is then cured under controlled temperature
The products have been effective because of their and humidity giving it the optimum mechanical strength
outstanding life expectancy and performance, and also producing a very smooth surface which
resistance to aggressively corrosive environments, high reduces head losses and guarantees long-term hydraulic
abrasion resistance, low temperature curing capability, efficiency.
strong adhesion, high film build, fast application, and
compliance with the most rigorous regulations on volatile
organic compound (VOC) emissions.
Type INTERNAL
Pipes Fittings
Type EXTERNAL
Pipes Fittings
Standard coating • Metallic zinc + bituminous paint • Metallic zinc + bituminous paint
Supplementary protection • Polyethylene sleeving (applied on site) • Polyethylene sleeving (applied on site)
Special coatings • Polyurethane • Different kinds of epoxy
• Different kinds of epoxy (F.B.E., ceramic, coal tar, etc...)
(F.B.E., ceramic, coal tar, etc...)
15 15
10.3 Pipes and Joints
10.3.1 Pipes
16
FLANGED PIPES (FABRICATED PIPES) – WELDING OR INTEGRALLY CASTED
Flanged pipes are class K9, centrifugally cast with welded The normal gasket can be improved by steel reinforced
rovide B16.1 class
re normally EPDM elastomer rubber 125 (for cast iron). Identical to ANSI B16.5 class 150 (for
as per ISO 4633. steel).
Double flange pipe w/puddle Flange spigot w/puddle Socket spigot w/puddle
* These pipes can be supplied in all lengths between 0.3 m and 5.9 m, where integrally case pipe max. length is 2.5 m
Above pipes can be supplied with diferent lengths, also one or more puddles can be made.
** Dimensions of flange pipes are subject to change without prior notice.
*** The masses indicated here are average values
18
18
10.4 Socket and Flange Fittings
Internal Coating
Fittings are lined internally with portland cement
(sulphate resistance type V) as per ISO 4179.
External Coating
Fittings are coated externally by pure metallic zinc
(minimum 99.995 purity) with thickness of 100 microns.
Zinc is then covered by 120 microns of bituminous
paint as per ISO 8179-2.
Marking
rdance with the
standard ISO 2531 & BSEN 545.
10.4.1 Bends
21 21
10.6 PE Sleeves
48
49
11 Storage and Laying Instructions
1. The storage area must be flat. The ground must 1. DN 300 pipes are bundled and protected with
not be marshy or unstable and it must not contain orange plugs on both socket and spigot.
any corrosive material.
2. DN > 300 pipes are not bundled
2. On arrival in storage area the goods must be
inspected and if there is any damage (degradation of
the internal or external coating), it must be repaired
before going into stock.
7. Precautions must be taken when the pipes have Storage of the Gaskets
special coating.
As in ISO 4633 and 2230: Mainly the ring shall be
stored in accordance with the following precautionary
Please consult SADIP for assistance. measures:
49 50
Stacking Arrangement
DN 80 100 150 200 250 300 350 400 500 600 700 800 900 1000
Case # 1 70 58 40 31 25 21 18 16 12 10 7 6 5 3
Case # 2 & 3 30 27 22 18 16 14 12 11 8 7 5 4 4 3
50
51
11.2 Assembly of Push-On Joint
1. Using a wire brush and a rag, carefully clean the 4. Center the spigot in the socket and hold the pipe
inside of the socket particularly the gasket recesses. in a position by resting it on two wedges of tamped
In particular, remove any deposits of earth, sand, etc. earth or better, gravel.
also clean the spigot of the pipe to be joined and the
gasket itself. Check the presence of the chamfer, as 5. Push in the spigot until the first mark disappears
well as the absence of any damage on the spigot of inside the socket. The second mark must still be
the pipe. (See fig 1& 2 ) visible after assembly. (see fig 6 )
2. Check the condition of the gasket and insert it into 6. Check that the gasket is correctly in position by
its recess, with the lips pointing towards the bottom inserting the end of a metal ruler through the annular
of the socket. Make sure that the gasket is correctly spigot and socket gap until it touches the gasket.
compressed all the way round. (See fig 3 ) The ruler must penetrate to the same depth around
the whole circumference.
3. Coat with lubricating paste recommended and
supplied by SADIP, the spigot end of the pipe and 7. Jointing must be done with well aligned pipes.
the exposed surface of the gasket (See fig 4 & 5 ). Make sure that the curvature after assembly does
The gasket recess must not be coated with not exceed the permissible angular deflection of
lubricating paste, except for small diameter pipes or particular joint.
fitting when problems arise on fitting the gasket.
51 52
11.4 Pipe Laying Equipments
Mechanical winches
• DN 150 to 300:
TIRFOR 516 winch with wire rope and protected hooks.
• DN 350 to 600:
TIRFOR 532 winch with wire rope and protected hooks.
• DN 700 & above:
2 TIRFOR 532 winches, diametrically opposite 2 wire
ropes and 2 protected hooks.
Mechanical winches
53 54
11.5 Polyethylene Sleeving
General
Application
Sleeving Preparation
Barrel sleeve
• Cut the barrel and join sleeves to the dimensions
indicated in the section (Material required &
dimensions)
• Before lowering the pipe into the trench, raise it up
and slip the pleated sleeving along the barrel.
54
55
Joint Sleeving
Joint Joint
sleeve sleeve
• Lower the pipe into the trench.
• Joint the pipe with appropriate equipment. The fold Soil
Sleeving of Fittings
Standard Joint
Joint
sleeve Adhesive
• Use the same polyethylene sleeving to protect Fastening
tape
fittings. Depending on their shape, two or three
Barrel
pieces of sleeving may be necessary. Application sleeve Adhesive
must comply with the same recommendations tape
Application
All socket tee dn < DN
Securing the
sleeve fold
3 plastic
coated Adhesive tapes
Bend
fastener
Final Assembly
Adhesive tape All socket tee dn < DN
(on top of barrel sleeve)
Plastic
coated
fastener
Plastic Adhesive
coated tapes
fastener
55 56
50 mm adhesive
tapes
I (flat width)
L I Lf I LJ E
m m m m m um m m kg kg
56
57
11.6 Cutting Pipes
Nominal
OD m n
Pipes must be cut on site as infrequently as possible diameter
mm mm mm
DN
by using disc-type cutter. Such operations, which
80 98 9 3
require particular care, must be carried out without
100 118 9 3
fail in a plane perpendicular to the pipe axis.
150 170 9 3
200 222 9 3
250 274 9 3
Before cutting, make sure that the OD of the new spigot 300 326 9 3
“cut area” is within the tolerance of the OD of the old 350 378 9 3
spigot. It’s advisable to use guage pipe for cutting on 400 429 9 3
site. Guage pipe has a special mark on the socket face. 450 480 9 3
After cutting the pipe, it is necessary: 500 532 9 3
600 635 9 3
• To restore the chamfer at the spigot end of the 700 738 15 5
800 842 15 5
cut faces of pipe.
900 945 15 5
1000 1048 15 5
• To execute the weld on site (if locked joint.)
Chamfer Restoration
Disc type cutters
After cutting, complete deburring is recommended.
It is essential to restore the chamfer on the cut faces
of standard pipes so as to facilitate the assembly
of the push-on joint and to prevent any damage to
the elastomer (rubber) gasket, which can result in a
leaking joint. The geometry of this chamfer must be in
accordance with the dimensions below.
Equipment necessary
• Electric welding set of 130 A minimum with
welders accessories (mask gloves, wire brush,
scaling hammer, etc.) “Nickel-iron electrode
(approx. 55% nickle.)
• Supplied by SADIP on request.
• One copper guide ring per DN.
• Electric pnuematic grinding machine with
accessories.
57 58
11.7 Repair of Cement Lining
Mixing Application
Equal quantity of the two parts are to be mixed well • Trowel or other devices are to be used for the
by trowel or other mixing devices. application to meet the required level.
• Surface can be finished smoothly by the use of
Tools Needed for Epoxy Application a paint brush dipped in water and by sand paper
• Brush rubbing.
• Trowel • Where a deep recess is to be filled, it may be
• Palette knife, or sleeker. necessary to build up a layer.
58
59
11.8 Depths of Cover
Range of Possibilities
The following illustration shows the maximum and
minimum depths of cover with:
• Traffic loading
• K9 pipes
• Type 3 laying in accordance with ANSI A21-50/
AWWA C 150 Standard.
3.6
2000
3.8
1800
3.9
1600
4.0
1500
4.1
1400
4.3
1200
4.4
1100
4.6
1000
4.7
900
4.8
800
5.1
600
5.6
400
7.4
200
10.3
150
30
m
60 100
ANSI A 2150
type 3 laying
59 60
DATE TRANSMITTAL NO.
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA
MATERIAL SAMPLES, OR MANUFACTURER'S 33 11 00-5
17-06-2020
CERTIFICATES OF COMPLIANCE
PROJECT TITLE Artillery Brigade Base RSLF-AC Saudi CONTRACT NO. PAGE
W912ER19C0001 Page 1 of 1
LOCATION Dammam, Saudi Arabia
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the
general method of construction, materials, detailing and other information are satisfactory. This does not relieve the Contractor from
the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring
removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement
to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the
technical specifications so prescribe.
Technical Submittal for the “Poly wrap Corrosion Protective film for D.I. pipes” Material
Approval (NAPCO).
Narratives:
Specification 33 11 00 Page 14 clause 3.2.1.2.c
Note: Clear polyethylene sleeve for Ductile Iron Pipe as recommended by the
DI pipe manufacturer SADIP.
Attachments:
1. Narratives.
2. Project Specifications.
3. IFC Drawings.
4. Variance Form.
Only install flanged pipe aboveground or with the flanges in valve pits
unless otherwise indicated.
b. Allowable Deflection: Follow AWWA C600 and AWWA M41 for the maximum
allowable deflection. If the alignment requires deflection in excess
of the above limitations, provide special bends or a sufficient number
of shorter lengths of pipe to achieve angular deflections within the
limit set forth.
SECTION 33 11 00 Page 14
100% Site and Facility Design Submittal
1 2 3 4 5
UNPAVED PAVED
APPR.
CAST IRON FRAME AND
COVER: TO READ "WATER"
OR "FIRE" AS APPLICABLE
DATE
D 1000 DIA x 210 CONCRETE COLLAR
(REFER TO SPECIFICATION 03 30 1000Ø x 210 CONCRETE
00.00 10 FOR CONCRETE COLLAR (REFER TO
SPECIFICATION 03 30 00.10 CAST IRON FRAME AND
STRENGTH)
FINISH GRADE FOR CONCRETE COVER; COVER TO
STRENGTH) READ "WATER"
16 Ø HOOP REINFORCING
DESCRIPTION
16 Ø HOOP REINFORCEMENT CENTERED IN COLLAR
CENTERED IN COLLAR
ADJUSTABLE CAST IRON COMPACT SUBGRADE VARIES (SEE PLANS)
VALVE BOX MIN DIA 135
POTABLE BUILDING
APPR. MARK
VALVE BOX MIN DIA 135 SERVICE
GATE VALVE STOP
SERVICE STOP
SEP
WATER LINE / FIRE LINE (BALL VALVE)
POTABLE
12-19-19
WATER LINE COPPER
DATE
SERVICE LINE
150
COPPER TUBING (TYP)
DESCRIPTION
C COMPACTED WASHED ANGULAR STONE NOTES:
WATER / FIRE MALE THREAD X 1. VALVE BOX NOT SHOWN FOR CLARITY
COMPRESSION 2. SEE CU-100 DRAWINGS FOR SERVICE SIZE
PROTECTION BURIED FITTING COUPLING WATER SERVICE LINE
GATE VALVE CONNECTION SECTION WATER SERVICE LINE
1 2
SCALE = NTS SCALE = NTS
CONNECTION PLAN
MARK
3
100%
SCALE = NTS
CONTRACT NO.:
UNPAVED PAVED
1:2
FINISH GRADE
SA-459583--CU521DT
DATE:
SEE ROADWAY/CONCRETE
WEDGE INDICATING 100X100 LOCATOR EXISTING GROUND DETAILS FOR PAVEMENT
DIRECTION OF POST WITH WEDGE SURFACE REQUIREMENTS
INSTALLED UTILITY PAINTED BLUE AND
CAP WITH "WATER"
FILE NAME:
CKD BY:
MARKED WITH W
MARKED ON IT
BET
JSR
S. PAVLOWICH
150mm CONCRETE 300
SUBMITTED BY:
DESIGNED BY:
COLLAR
22 X 34
DWN BY:
FINISH GRADE 450mm (MIN) TRENCH WIDTH. FOR PIPES LARGER THAN 150mm,
SCJ
SIZE:
WIDTH SHALL BE PIPE DIAMETER PLUS 230mm ON EACH SIDE
B
760 (MIN)
PLACE BURIED WARNING AND
US Army Corps
COVER
of Engineers
END CAP
p:\269162\127-269162-19001\cad\cad drawings\01_site design\civil\03_utilities\sa-459583--cu521dt brandon.goold 12/24/2019 10:59 AM
SATISFACTORY MATERIAL
45°
MA
TETRA TECH
GATE COMPACTED TO 95% OF
X
300
VALVE MAXIMUM DRY DESNITY
(TYP ON TOP)
150 (TYP ON SIDES)
WATER DETAILS
SHEET 1 OF 6
SITE DESIGN
SA-459583
FUTURE WATER WATER / FIRE MAIN 1. ALL BURIED OR PARTIALLY BURIED CONCRETE STRUCTURES
SHALL HAVE THAT PORTION OF THE CONCRETE IN CONTACT
CONNECTION TRENCH DETAIL WITH SOIL SHALL WATERPROOFED PER SPECIFICATION 07 13 53 -
A 4 SCALE = NTS
5 SCALE = NTS SHEET WATERPROOFING WHICH CONSISTS OF A COAT OF
BITUMEN PRIMER, SHEET MEMBRANE AND PROTECTION BOARD.
SHOULD PROTECTION BOARD NOT BE PRACTICAL TO INSTALL,
ALTERNATIVE PROTECTION FOR THE INSTALLED MEMBRANE
WILL BE ALLOWED IF APPROVED BY CO.
UNLESS OTHERWISE
DIMENSIONS SHOWN NOTED,
ARE IN MILLIMETERS.
LINEAR
Material Submittal with Variation from Contract
CONTRACT NO. CONTRACT TITLE PRIME CONTRACTOR
US Army Corps W912ER19C0001 NA Artillery Brigade Base RSLF-AC Saudi Al Yamama Company for Trading
of Engineers N0003543 and Contracting
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the
general method of construction, materials, detailing and other information are satisfactory. This does not relieve the Contractor from
the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring
removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement
to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the
technical specifications so prescribe.
SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)
TO: Saudi Area Office FROM: Al Yamama Company for Trading and CONTRACT NO. THIS IS A:
N011F00 Contracting W912ER19C0001 NEW TRANSMITTAL
First Street, Behind Dammam Tower, PO
Box 2110
Dammam Dammam31451
SPECIFICATION SEC. NO. (Cover only one section with each transmittal) PROJECTSaudiTITLEArabia
AND LOCATION 01 THIS TRANSMITTAL IS FOR: (Check one)
31 00 00-EARTHWORK Artillery Brigade Base RSLF-AC Saudi, Dammam, Saudi Arabia FIO GA DA CR DA/CR DA/GA S
Note: As per specs metallic piping warning tape section 31 00 00 para 2.2.1,
due to non-availability of material in local market contractor chosen
section 31 00 00 para 2.2.2 Detectable warning tape which is alternative
higher option in the project specs.
Attachments:
1. Narratives.
2. Project Specification.
3.Variation Letter.
4. Technical Data Sheet
I certify that the above submitted items have been reviewed in detail and
are correct and in the strict conformance with the contract drawings and
specifications except as otherwise stated.
ENG FORM 4025-R, JUL 2015 Page 1 of 1 REPLACES EDITION OF MAR 2012, WHICH IS OBSOLETE
Project: Royal Saudi Land Forces Artillery Brigade Base
Contract #: W912ER-19-C-0001
Technical Submittal for Identification and Detectable Warning Tape for Utilities.(ELFIT ARABIA)
Narratives:
Specification 31 00 00 Page 07 & 8 clause
Note: As per specs metallic piping warning tape section 31 00 00 para 2.2.1,
due to non-availability of material in local market contractor chosen section
31 00 00 para 2.2.2 Detectable warning tape which is alternative higher
option in the project specs.
Attachments:
1. Narratives.
2. Project Specification.
3. Compliance with Project specification.
4. Variation Letter.
5. Technical Data Sheet
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Offsite Borrow
Testing; G M
SD-07 Certificates
Testing
PART 2 PRODUCTS
Test offsite soils brought in for use as backfill for Total Petroleum
Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and
full Toxicity Characteristic Leaching Procedure (TCLP) including
ignitability, corrosivity and reactivity. Backfill shall contain a
maximum of 100 parts per million (ppm) of total petroleum hydrocarbons
(TPH) and a maximum of 10 ppm of the sum of Benzene, Toluene, Ethyl
Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH
concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX
concentrations by using EPA SW-846.3-3 Method 5030/8020. Perform TCLP in
accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing
for TPH, BTEX and TCLP from a composite sample of material from the borrow
site, with at least one test from each borrow site. Do not bring material
onsite until tests have been approved by the Contracting Officer.
SECTION 31 00 00 Page 7
100% Site and Facility Design Submittal
RSLF Artillery Brigade Al Yamama
Eastern Province, Kingdom of Saudi Arabia
Red Electric
2.3.2 Rock
2.3.3 Grout
SECTION 31 00 00 Page 8
100% Site and Facility Design Submittal
Material Submittal with Variation from Contract
CONTRACT NO. CONTRACT TITLE PRIME CONTRACTOR
US Army Corps W912ER19C0001 NA Artillery Brigade Base RSLF-AC Saudi Al Yamama Company for Trading
of Engineers N0003543 and Contracting
P.O.BOX: 4118.Kingdom Saudi Arabia, Riyadh. TEL: +966 (ll) 4043633 FAX: +966 (f l) 4024S86
Mechanical Properties
Tensile Strenqth LW / CW Kglcm2 ASTM-882-97 300/250 Not Lower
Bond Strenqth qi1 5mm CFP-4 150 Not Lower
Detectable Capacity 920mm
Thermal Properties
Heat Resistance OC cFP-11 Pass Ink heat resistance
Chemical Properties
Sulphate 5% No effect
Chlorate 5% No effect
Alkali 10% No effect
Soap 10% No effect
Other Properties
RoIIWUOD Meters/Feet NA 1 000feet o.k.
Core lD mm NA 76 Standard
Note: lmprinted Warning message is "buried" or Encased to prevent ink rub-off, and is
impervious to acids, alkalis and otherdestructive elements found in soil. -. .:.- ;
:l
Dear Sir,
Please find the attached Datasheet & Tape Artwork.
/
METHOD STATEMENT & CHECKLIST
MOS FOR INSTALLATION
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
➢ Contract #: W912ER19C0001
As Per latest
00 06/11/2020 Spec updated
Joefrey L. Castillas Shahabuddin Ahmed Afroz Theodoros
Ansari Stergiopoulos
TABLE OF CONTENTS
1. Purpose
2. Scope
3. References
4. Definitions
5. Material Approvals
6. Subcontractors Approvals
8. Equipment
9. Tools
16. Attachments
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
1. PURPOSE
This document defines the methodology, sequence, control measures, safety, quality control requirements
and equipment intended to be used for installation of external works Fire Protection Water Line &
Domestic Water Line Artillery brigade base RSLF-AC, Saudi Arabia” project as per the project
specifications and other relevant reference documents.
2. SCOPE
The scope of work described in this method statement is applicable for installation of ductile iron pipes and
fittings, associated with “Artillery brigade base RSLF-AC, Saudi Arabia”.
3. REFERENCES
• Project Specification
1) Para 3.1; Section 33 11 00 Water Utility Distribution Piping
4. DEFINITIONS
5. MATERIAL APPROVALS
8. EQUIPMENT
1. Boom truck
2. Flat bed Trailer
3. Mobile crane
9. TOOLS
The Project Manager is responsible for the general overall execution of the project. He shall ensure the
availability of all plant and equipment available for the progress. Co-ordinates with safety and quality
managers to ensure the works are carried out in safe and related quality procedures.
The Site Superintendent shall be responsible for the overall construction activities at the site, including
quality and production. He ensures the implementation of method statement, AHA and ensures that all
involved site construction personnel are aware of this method statement, IFC drawings and shop drawings
are followed. He shall ensure that the execution of work shall be carried out in a safe manner. He shall be
responsible for over-all direction, monitoring coordination and control of all the construction activities and
ensure activities area accomplished as per the construction program.
The Field Mechanical Engineer shall ensure that the works are carried out according to the design,
approved shop drawings and procedures. He shall be responsible on behalf of the contractor to coordinate,
check and follow up the work with relevant parties and ensure that proper sequence of activities is followed
in order to achieve target completion. He shall ensure that safe work practices are followed for all work
under his care.
The CQC Manager has overall responsibility and authority for the administration of all CQC Program
related to activities. He shall ensure that the works are carried out according to the quality plan, contract
documents, approved drawings and procedures. He shall ensure the effective implementation of three
phase inspection system for the quality and safety of each definable features of work (DFOW). He shall
ensure the effective quality control sub-contractors and suppliers to correspond with the quality plan. He
shall review and coordinate submittals and approvals for contractor furnished materials and equipment,
conduct tests, and follow-ups of subcontractor's work as required ensuring compliance with contract plans
and specifications.
The CQC Engineer shall ensure that the works are carried out according to the quality plan, contract
documents, approved drawings and procedures. He shall ensure the requirements of three phase
inspection system for the quality and safety of each definable features of work (DFOW) are met using AHA
and checklist. He shall co-ordinate with the contracting officer for inspection and testing of each DFOW. He
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
shall ensure the materials and test are conducted as per the requirement of contract plans and
specifications.
The Site HSE Manager shall monitor and implement all HSE related issues. He shall ensure that all
necessary requirements regarding health, safety, environmental concerns, risk assessments are met and
adhered to. The SSHM all permits and authorization are on hand, he shall ensure the effective
implementation of project Accident prevention plan and Activity hazard analysis are effectively implemented
for each definable features of work.
The Site safety health officers shall be responsible to conduct work site inspection related to safety and
to ensure that the activities are performing as per USACE procedures, standards and other related
standards. He shall maintain all relevant valid documents related to the activity and involved equipment’s.
He shall lead HSE communication with workforce to encourage reporting of incidents including near-miss
incident, hazard identification, risk management and emergency preparedness. He shall investigate and
report all reportable accidents/incidents to contracting officer and safety manger with recommendation to
improve control measures for prevention of the recurrence. He shall be the authority to stop the site
activities due to an existence of unsafe condition. He shall ensure that all personnel are attended HSE
induction prior to the site assignment and strictly following HSE regulations.
The Foreman/Supervisor shall be responsible for the direct execution of works involved in the excavation
and backfilling process according to the plan and shall directly control and give instruction to the working
personnel. He shall also ensure that works are performed with proper tools/equipment, PPE and good
housekeeping around the working area and that all equipment has been safety checked and reported to
SSHO.
The Competent person for shall be responsible for correct installation procedure for all piping works. He
shall inspect the task each time beginning of work and shall be aware about the hazards related to
installation.
• All works shall be performed as per the approved Accident Prevention Plan,
• Engineers /SSHO shall ensure that PPE is mandatory for all personnel, PPE consist of safety boots
or shoes, safety helmets, safety gloves and coveralls. Other PPE’s requirements shall be
determined as the work proceeds with any foreseeable hazards and risks.
• Ensure the completion of preparatory phase inspection prior to start of work.
• Ensure to obtain installation permit from the contracting officer representative prior to start the
excavation.
• Prior to commencing an activity all the personnel’s involved shall be given site safety inductions by
SSHO’s. A daily Tool box talk and method statement briefing shall be given regarding the safe
working practices and procedures to be followed.
• Edge protection shall be provided for all sides of trench including safe access and egress prior to
start pipe laying/installation
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
• In the event of an accident notify the SSHO manager/Superintendent and CQC manager. Notify the
Contracting officer as necessary and investigate the accident and a report shall be completed by the
investigation team.
• Ensure necessary shop drawings, tools, materials, equipment and manpower required for the work
to be on site.
• Other PPE’s requirements shall be determined by Activity hazard analysis as the work proceeds
and other anticipated excavation hazards.
• Coordinate with Safety Manager / SSHO regarding the risks associated to the activity.
• Barricade the area, provide basic need for facilities & hygiene for people viz. shelter, toilet, drinking
water.
• In case of storm or rain De watering shall be done using centrifugal dewatering pump (diesel
pumps) with 3” suction pipe and then the water shall be discharged into the retention pond away
using 2” discharge hose.
• This Method Statement is general for all external works piping Fire water line, Domestic water line
and sewer water line.
• Permit shall be obtained from COR prior to commencing the activity.
• Equipment’s and vehicles involved for pipe laying and installation shall be checked by transport
department to ensure the suitability for the task.
12.3
Pipe laying and installation for Domestic & Fire Water Line
• The surveyor shall establish the line of piping as per the approved IFC drawings verified by the Field
engineer and QC Engineer.
• Prior to the commencement of activities operatives involved must be briefed about the safe way of
work.
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
• Workers shall stand away from equipment swing area and vehicle movement area while unloading
the pipe, fittings and accessories.
• Construction team shall ensure that adequate access and egress will be provided and ensure all
sides of trench will be appropriately barricaded with guard rails at least 1.6m from the edge of
excavation. Warning signs to be posted to restrict unnecessary access /unauthorized movements of
personnel.
• If the trench reaches the depth of 1.2m the reaches area shall be gas tested prior to each shift.
(excavation plan)
• Proper facilities for lowering sections of pipe into trenches shall be provided.
• Before lowering the pipe into the trench, raise it up and slip the pleated sleeving along the barrel.
• The sleeving must fit in the pipes as tight as possible; the barrel and joint sleeve overlaps must
provide total continuity of protection.
• Pipe, fittings and accessories shall be unloaded into the trench using mobile crane or boom truck.
• Prior to installation all fins and burrs from pipe and fittings shall be removed.
• All pipe, fittings and accessories, shall be clean up and maintain in a clean condition before placing
it in position.
• Pipe shall be cut cleanly, squarely, and accurately to the length established at the site and work into
place without springing or forcing.
• Blocking or wedging between bells and spigots is not permitted. Lay bell-and-spigot pipe with the
bell end pointing in the direction of lying.
• Pipe shall be grade in straight lines to avoid the formation of dips and low points.
• Pipe shall be supported at the design elevation and grade and shall be secure firm and uniform
support. Wood support blocking is not permitted.
• Pipe shall be laid so that the full length of each section of pipe and each fitting rests solidly on the
pipe bedding; Recesses shall be excavated to accommodate bells, joints, and couplings.
• Use the same polyethylene sleeving to protect fittings. Depending on their shape, two or three
pieces of sleeving may be necessary. Application must comply with the same recommendations
(Particularly fitting the sleeving as snugly as possible).
• Open ends of pipe shall be temporarily close with wood blocks or bulkheads at the end of each work
day.
• Pipe shall not be laid when conditions of trench or weather prevent installation. Provide a minimum
of 760 mm depth of cover over top of pipe.
• The testing will be repeated again after the installation of the valves.
• After installation pipes shall partially backfill and all joints shall remain open for the testing.
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
• Hydrotest, Backfilling, valve installation and its testing will be discussed in separate method
statement.
• The backfilling will be done leaving the valve area open (approx. 4 metre area will remain open)
12.5 INSPECTION
• The CQC Engineers shall ensure that the inspections are completed in accordance with the project
specification Quality control requirements. They will conduct random inspections as per the
requirements to verify compliance with the specification and design drawings.
• They shall ensure that the latest revisions of approved drawings/ documents will be used on site by
the Site Construction Team.
• Any discrepancies found during an inspection will be immediately communicated to the Construction
Superintend/Field Engineer for rectification and compliance with specified requirements.
Discrepancies should be rectified prior to the CQC Engineer’s final inspection and USACE
concurrence.
13. SPECIFIC TRAINING / INDUCTION TO BE GIVEN FOR EXECUTING THE WORK (IF REQUIRED)
AYC shall provide: 2Nos. Water coolers (cold with ice) - Shall be Replenished
regularly and as of demand.
1No. Rest Shelter / Tent
I have read the site-specific Method Statement, Activity Hazard Analysis and all supporting documentation
for my task or had it explained to me. I fully understand its contents and confirm that I shall adhere to all
instructions contained within. I agree that NO ATTEMPT shall be made to carry out any other works not
detailed on this Method Statement. Furthermore, I agree to abide by all site rules and shall stop work and
report any site conditions that have potential to cause injury, accident or ill health to myself or others.
16. ATTACHMENT
➢ Contract #: W912ER19C0001
As Per latest
00 07/18/2020 Spec updated
Shahabuddin
Ronillo A. Ros Ahmed Afroz Saleh Selim
Ansari
Date Date Date Date
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
METHOD STATEMENT FOR HYDROSTATIC
PRESSURE TESTING OF FIRE AND POTABLE
MS #: MS-AYC-RSLF- 00 PIPELINE Date: 18-JULY-2020
Rev #: 0
TABLE OF CONTENTS
1. Purpose
2. Scope
3. References
4. Definitions
5. Material Approvals
7. Equipment
8. Tools
9. Human Resource
15. Attachments
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
METHOD STATEMENT FOR HYDROSTATIC
PRESSURE TESTING OF FIRE AND POTABLE
MS #: MS-AYC-RSLF- 00 PIPELINE Date: 18-JULY-2020
Rev #: 0
1. PURPOSE
To ensure that hydrostatic testing for underground pipes are carried out in safety manner, in accordance
with good working practices, in compliance of project specification and requirement of scope of project and
intended to provide general application guidance and application establish control during hydro test and
final acceptance of pipe works within required system.
2. SCOPE
The scope of work described in this method statement is applicable for testing Ductile Iron pipes and fittings
installed for Firewater and Potable water line of Artillery brigade base RSLF-AC, Saudi Arabia.
3. REFERENCES
4. DEFINITIONS
5. MATERIAL APPROVALS
7. EQUIPMENT
8. TOOLS
1. Test Manifold with accessories (Valve, Check Valve ,PRV , Gauges, Pressure Hose)
2. Hand tools for tightening accessories and fittings
9. HUMAN RESOURCES
The Project Manager is responsible for the general overall execution of the project. He shall ensure the
availability of all plant and equipment available for the progress. Co-ordinates with safety and quality
managers to ensure the works are carried out in safe and related quality procedures.
The Site Superintendent shall be responsible for the overall construction activities at the site, including
quality and production. He ensures the implementation of method statement, AHA and ensures that all
involved site construction personnel are aware of this method statement, IFC drawings and shop drawings
are followed. He shall ensure that the execution of work shall be carried out in a safe manner. He shall be
responsible for over-all direction, monitoring coordination and control of all the construction activities and
ensure activities area accomplished as per the construction program.
The Field Mechanical Engineer shall ensure that the works are carried out according to the project
specification,design, approved shop drawings and procedures. He shall be responsible on behalf of the
contractor to coordinate, check and follow up the work with relevant parties and ensure that proper
sequence of activities is followed in order to achieve target completion. He shall ensure that safe work
practices are followed for all work under his care.
The CQC Manager has overall responsibility and authority for the administration of all CQC Program
related to activities. He shall ensure that the works are carried out according to the quality plan, contract
documents, approved drawings and procedures. He shall ensure the effective implementation of three
phase inspection system for the quality and safety of each definable features of work (DFOW). He shall
ensure the effective quality control sub-contractors and suppliers to correspond with the quality plan. He
shall review and coordinate submittals and approvals for contractor furnished materials and equipment,
conduct tests, and follow-ups of subcontractor's work as required ensuring compliance with contract plans
and specifications.
The CQC Engineer shall ensure that the works are carried out according to the project specifications,
quality plan, contract documents, approved drawings and procedures. He shall ensure the requirements of
three phase inspection system for the quality and safety of each definable features of work (DFOW) are
met using AHA and checklist. He shall co-ordinate with the contracting officer for inspection and testing of
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
METHOD STATEMENT FOR HYDROSTATIC
PRESSURE TESTING OF FIRE AND POTABLE
MS #: MS-AYC-RSLF- 00 PIPELINE Date: 18-JULY-2020
Rev #: 0
each DFOW. He shall ensure the materials and test are conducted as per the requirement of contract plans
and specifications.
The Site HSE Manager shall monitor and implement all HSE related issues. He shall ensure that all
necessary requirements regarding health, safety, environmental concerns, risk assessments are met and
adhered to. The SSHM all permits and authorization are on hand, he shall ensure the effective
implementation of project Accident prevention plan and Activity hazard analysis are effectively implemented
for each definable features of work.
The Site safety health officers shall be responsible to conduct work site inspection related to safety and
to ensure that the activities are performing as per USACE procedures, standards and other related
standards. He shall maintain all relevant valid documents related to the activity and involved equipment’s.
He shall lead HSE communication with workforce to encourage reporting of incidents including near-miss
incident, hazard identification, risk management and emergency preparedness. He shall investigate and
report all reportable accidents/incidents to contracting officer and safety manger with recommendation to
improve control measures for prevention of the recurrence. He shall be the authority to stop the site
activities due to an existence of unsafe condition. He shall ensure that all personnel are attended HSE
induction prior to the site assignment and strictly following HSE regulations.
The Foreman/Supervisor shall be responsible for the direct execution of works involved in hydro testing
activity according to the plan and shall directly control and give instruction to the working personnel. He
shall also ensure that works are performed with proper tools/equipment, PPE and good housekeeping
around the working area and that all equipment has been safety checked and reported to SSHO.
The Competent person for shall be responsible for correct installation procedure for materials and
accessories needed for the hydro test. He shall inspect the task each time beginning of work and shall be
aware about the hazards related to installation.
• Engineers /SSHO shall ensure that PPE is mandatory for all personnel, PPE consist of safety boots
or shoes, safety helmets, safety gloves and coveralls. Other PPE’s requirements shall be
determined as the work proceeds with any foreseeable hazards and risks.
• Ensure the completion of preparatory phase inspection prior to start of work.
• Ensure to obtain Hydro test permit from the contracting officer representative prior to start the test.
• Prior to commencing an activity all the personnel’s involved shall be given site safety inductions by
SSHO’s. A daily Tool box talk and method statement briefing shall be given regarding the safe
working practices and procedures to be followed.
• In the event of an accident notify the SSHO manager/Superintendent and CQC manager. Notify the
Contracting officer as necessary and investigate the accident and a report shall be completed by the
investigation team.
• Ensure necessary shop drawings, tools, materials, equipment and manpower required for the work
to be on site.
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
METHOD STATEMENT FOR HYDROSTATIC
PRESSURE TESTING OF FIRE AND POTABLE
MS #: MS-AYC-RSLF- 00 PIPELINE Date: 18-JULY-2020
Rev #: 0
• Other PPE’s requirements shall be determined by Activity hazard analysis as the work proceeds
• Coordinate with Safety Manager / SSHO regarding the risks associated to the activity.
• Barricade the area with Signage “Ongoing Hydro test” shall be placed on the test area covered
• Provide basic need for facilities & hygiene for people viz. shelter, toilet, drinking water.
• Test manifold must be tested prior of usage by applying 1.2 times the maximum test pressure
requirements. Test manifold shall be calibrated by third party testing company.
• Pressure Gauges must be calibrated prior to use. Calibration interval shall not exceed thirty (30)
days and calibration certificate shall be made available to inspection personnel prior to
commencement of pressure test. A minimum of two (2) pressure gauges are required for the test
system. One pressure Gauge shall be on the test manifold and the other on the test system.
• Pressure Relief Valve shall be calibrated, dated and tagged within two (2) weeks prior to pressure
test. Pressure relief valve is to set to relieve 5% above the hydro test pressure.
• Hydro test procedure is in accordance to project specs referring to AWWA C600 and NFPA 13.
• Prior to pressure testing, all joints shall be exposed and cleaned properly, and the rest of the length
will be backfilled with suitable material up to 300mm above pipe to serve as a support or
counterforce during the hydro test.
• Blind flange with ½ in. nipple provision will be used on both ends of the pipe to be tested. One end
with vent nozzles at highest point and the other end as a drain and connected to the Test manifold.
• Field Engineer should make sure that all joints are exposed and free of sand prior to start of
pressure test.
• Potable water shall be used for hydro testing and will be injected to the pipe line to be tested
through a water tanker.
• During the filling of water, the vent shall be open to remove the air accumulated during the water
filling. (AWWA C600)
• AYC to pressure test Fire water up to 200 PSI in accordance to NFPA 13 while Potable water line
will be tested 1.5 times the operating pressure in accordance to AWWA C600.
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
METHOD STATEMENT FOR HYDROSTATIC
PRESSURE TESTING OF FIRE AND POTABLE
MS #: MS-AYC-RSLF- 00 PIPELINE Date: 18-JULY-2020
Rev #: 0
• During the pressurization, proper control shall be observed and AYC to do 10 minutes hold time
after reaching 50% of the test pressure. During this time visual check will be done by Site
Supervisor /Field Engr. And CQC to check if there are any visible leaks occurred.
• After preliminary check of leaks, the pressure shall be increased in steps with at least 10 minutes
hold at each step to permit inspection for leaks and weaknesses. The pressure shall be increased to
the required test pressure in steps no greater than one fifth of the test pressure after the preliminary
check at the 50% Test pressure. Further pressurization shall not be continued until weakness have
been repaired and leaks have been stopped.
• The test pressure shall be hold for 2 hours as per (NFPA 13 & AWWA C600).
• Test pressure shall not vary by more than +/- 5 psi (34.5 kPa) for the duration of the test. (NFPA 13
& AWWA C600).
• During this stage, a keen visual inspection shall be done to monitor any leak on the system.
• Site Supervisor/Site Engineer to monitor if there is changes in pressure during the test duration.
• Testing allowance defined. Testing allowance shall be defined as the quantity of makeup water that
must be supplied into the newly laid pipe to maintain pressure within 5 psi (34.5 kPa) of the
specified test pressure after the pipe has been filled with water and the air has been expelled.
Testing allowance shall not be measured by a drop in pressure in a test section over a period of
time (AWWA C600)
• Testing allowance. No pipe installation will be accepted if the amount of makeup water is greater
than that determined by the following formula. (NFPA 13 & AWWA C600)
• Pressure test acceptance criteria is after reaching to the required test pressure and no leaks or
pressure drop within the criteria have been observed in the test duration.
• Should a test fail, locate the area of leakage and replace the leaking part with a new one, or repair
the line using an approve fitting by manufacturer.
• After pressure testing has been successfully completed and accepted by client, the following
procedures shall be observed.
Project: Artillery brigade base RSLF-AC
Project No: W912ER19C0001
METHOD STATEMENT FOR HYDROSTATIC
PRESSURE TESTING OF FIRE AND POTABLE
MS #: MS-AYC-RSLF- 00 PIPELINE Date: 18-JULY-2020
Rev #: 0
✓ Do not depressurized the system by loosening bolts in the flange, release the
pressure slowly on the vent to depressurize the system, then slowly remove water
from the drain nozzle.
✓ Properly release the water and don’t allow water to flood the tested area, it’s a best
practice to provide dewatering pump/suction pump to remove water from the trench.
✓ Properly keep and secure all test materials and accessories for the succeeding tests.
11.3 INSPECTION
• The CQC Engineers shall ensure that the inspections are completed in accordance with the project
specification Quality control requirements. They will conduct random inspections as per the
requirements to verify compliance with the specification and design drawings.
• They shall ensure that the latest revisions of approved drawings/ documents will be used on site by
the Site Construction Team.
• Any discrepancies found during an inspection will be immediately communicated to the Construction
Superintend/Field Engineer for rectification and compliance with specified requirements.
Discrepancies should be rectified prior to the CQC Engineer’s final inspection and USACE
concurrence.
12. SPECIFIC TRAINING / INDUCTION TO BE GIVEN FOR EXECUTING THE WORK (IF REQUIRED)
AYC shall provide: 2Nos. Water coolers (cold with ice) - Shall be Replenished
regularly and as of demand.
1No. Rest Shelter / Tent
I have read the site-specific Method Statement, Activity Hazard Analysis and all supporting documentation
for my task or had it explained to me. I fully understand its contents and confirm that I shall adhere to all
instructions contained within. I agree that NO ATTEMPT shall be made to carry out any other works not
detailed on this Method Statement. Furthermore, I agree to abide by all site rules and shall stop work and
report any site conditions that have potential to cause injury, accident or ill health to myself or others.
15. ATTACHMENT
Terminate the work covered by this section at a point approximately 1.5 SECTION 33 11 00
1
m from the building, Clause 3.2.1.1.1
Do not lay water lines in the same trench with gas lines, fuel lines, SECTION 33 11 00
2
electric wiring, or any other utility. . Clause 3.2.1.1.1
Do not install copper tubing in the same trench with ferrous piping
materials. Where nonferrous metallic pipe (i.e., copper tubing) crosses SECTION 33 11 00
3
any ferrous piping, provide a minimum vertical separation of 300 mm Clause 3.2.1.1.1
between pipes.
SECTION 33 11 00
4 Remove fins and burrs from pipe and fittings.
Clause 3.2.1.1.2
Before lowering the pipe into the trench, raise it up and slip the pleated Manufacturer's
6
sleeving along the barrel. Instruction Manual
With the pipe supported on two wooden blocks, spread the sleeving
along the whole length of the barrel and fit it snugly to the latter by Manufacturer's
7
folding it over at the top of the pipe. The sleeving must not move Soil or Instruction Manual
bulge
Cut pipe cleanly, squarely, and accurately to the length established at SECTION 33 11 00
9
the site and work into place without springing or forcing. Clause 3.2.1.1.2
Replace a pipe or fitting that does not allow sufficient space for SECTION 33 11 00
10
installation of jointing material. Clause 3.2.1.1.2
SECTION 33 11 00
11 Blocking or wedging between bells and spigots is not permitted.
Clause 3.2.1.1.2
Lay bell-and-spigot pipe with the bell end pointing in the direction of SECTION 33 11 00
12
laying. Clause 3.2.1.1.2
Grade the pipeline in straight lines; avoid the formation of dips and low SECTION 33 11 00
13
points. Clause 3.2.1.1.2
Lay pipe so that the full length of each section of pipe and each fitting
SECTION 33 11 00
15 rests solidly on the pipe bedding; excavate recesses to
Clause 3.2.1.1.2
accommodate bells, joints, and couplings.
SECTION 33 11 00
16 Provide anchors and supports for fastening work into place.
Clause 3.2.1.1.2
SECTION 33 11 00
17 Make provision for expansion and contraction of pipelines.
Clause 3.2.1.1.2
SECTION 33 11 00
18 Keep trenches free of water until joints have been assembled.
Clause 3.2.1.1.2
At the end of each work day, close open ends of pipe SECTION 33 11 00
19
temporarily with wood blocks or bulkheads. Clause 3.2.1.1.2
Where the location of the water line is not clearly defined by dimensions
on the drawings, do not lay water line closer than 3.0 m, horizontally,
from any sewer line.
a. Normal Conditions: Lay water piping at least 3.0 m horizontally from
sewer or sewer manhole whenever possible. Measure the distance
from outside edge to outside edge of pipe or outside edge of manhole.
When local conditions prevent horizontal separation install water piping
SECTION 33 11 00
23 in a separate trench with the bottom of the water piping at least 450 mm
Clause 3.2.1.1.5
above the top of the sewer piping.
Provide at least 450 mm above the top (crown) of the sewer piping and
the bottom (invert) of the water piping whenever possible. Measure the
distance edge-to-edge. Where water lines cross under gravity sewer
lines, construct sewer line of AWWA compliant ductile iron water piping
with rubber-gasketed joints and no joint located within 3 m horizontally,
of the crossing.
a. Normal Conditions: Provide a separation of at least 450 mm between
the bottom of the water piping and the top of the sewer piping in cases
where water piping crosses above sewer piping.
REMARKS:
Al Yamama Co. / Third-Party AYC
Construction Department representative QC Engineer
Work is Complete and Ready for Inspection: QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
INSPECTION CHECKLIST
Project Name Artillery Brigade base RSLF-AC DOR Tetra Tech
Client US army Corps of Engineer's Contractor Al-yamama company
Checklist Title Checklist #
Related Dwgs
During the filling of water, the vent shall be open to remove the air
2 AWWA C600
accumulated during the water filling.
During the pressurization, proper control shall be observed and the hold
3 time shall be 10 minutes after reaching 50% of the test pressure. During Method of Statement
this time visual check will be done.
Test pressure shall not vary by more than +/- 5 psi (34.5 kPa) for the
6 Method of Statement
duration of the test.
Manufacturer's
7 visual inspection shall be done to monitor any leak on the system.
Instruction Manual
3. Mobilization of Heavy 1 Defective or damaged equipment & No 1 Inspect the equipment as per the H
Equipment. pre-inspection done. checklist prior to work start.
2 Non certified operator 2 The operator should possess SAG
3 Parking area not identified / obstruction operating license.
4 Traffic accident / property damage. 3 Vehicle Should be parked in designated
5 Blind spot area.
6.Visibility 4 Provide trained flagman for controlling
the traffic.
5 Follow approved traffic control plan.
6 Follow speed limit 20 km/h inside site.
7 Provide proximity Device for each heavy
equipment.
8 Reverse alarm and Revolving beacon
Light in operable condition.
4.Excavation Work 1 Damage to underground and other 1. Take work permit prior to work start. H
existing utilities /utilities not marked and 2. Pre-excavation checklist need to be
identified on the As-built drawings. filled before the activities start
2 Excavation wall collapse / Cave-in. 3. Identify the underground utilities by
3 Fall of person into excavated pit available drawing & underground utility
4 No Access & Egress scanner or detector.
5 Inhalation of dust 4. Mark the location of any known or
6 Personnel struck by Moving equipment suspected underground utilities
and damage to property. 5. Prior to commencement of work
7, Visibility personnel shall be informed about the
8.Troppling of Dump truck into excavated identified Utilities.
pit 6. Mechanical excavation is not allowed
9) Water accumulation within 3M (10ft) from known underground
10) Fall person during Night hours utilities.
11) Toxic Gas 7. Provide proper sloping or benching or
shoring according to the soil classification
8. Excavated soil should be kept at least 2
m away from the edge of excavated pit
9. Provide barricading 1 M away from the
excavated pit to restrict unauthorized
entry of person.
10. Provide inspected ladder for access
and shall fixed properly at least 1M above
the top landing point.
11. Ladder shall be spaced at least every
15M (50ft) along a trench.
12. Dust control by the use of water truck
to continuously spraying the area.
13. Workers shall be provided with 3M N-
95 dust mask and safety glass.
14. Heavy equipment shall be kept 2m
away from the edge of excavation
15. Provide hard barricading & warning
signage’s "Deep Excavation".
16. Flagman to control the movement of
vehicle.
17. Provide dewatering pumps if
required.
18. Post reflective warning signs &
warning lights.
19.Follow the procedures for confined
space entry for excavation greater than
1.2 m ( 4ft)
Deep.
20. Gas test should be conduct before
entering inside the excavation.
21.Trained flagman /Banks man shall be
utilized to assist operators in their
operation
22. All heavy equipment shall be
equipped with proximity device and
flagman with personal device to liaison
with operator.
5. Installation of fire & Domestic 1) Slip & trip 1) Only trained personnel with relative H
water systems/installations. 2) Fall of Material experience shall be allowed to handle this
3) Property Damage work
4) Personal Injury 2) all field personnel will use appropriate
PPE for their tasks.
3) Appropriate Safety sign boards,
barriers shall be provided.
4) Follow safe manual handling while
shifting materials.
5) Tools appropriate to the task being
undertaken are chosen and used
according to safe working practices.
6) Follow safe lifting operations while
laying the pipes into pit before installation.
7) Shall maintain good housekeeping
around work area.
6) Manual Excavation 1) Personal injury. 1) Provide proper PPE like Hard hat, H
2) Slip ,Trip Safety shoes, Safety goggles, hand
3) Dust inhalation gloves, cover all, high visible vest Dust
4) Access and Egress mask.
2) Provide proper and correct tools.
3) Provide proper barricading around
excavation area.
4) Provide ladder at intervals.
5) Provide good work place
7.Confined Space Entry 1) Toxic Gas 1.1) Gas test shall be performed by H
trained gas tester in all level of confined
2) No Access & Egress space i.e. at point of an entry, bottom, mid
3) Untrained person and top level.
4) Poor Supervision 1.2) Oxygen content, flammable and toxic
5) Lack of Oxygen and presence of gas reading shall be:
a) Oxygen: concentration is b/w 20.0% -
hazardous airborne. 23.5%
6) Faulty Gas detector b) Flammable gas: less than 5% of the
LEL.
c) CO is at below 35 parts per million (
PPM)
d) H2S is at or below 10 PPM.
1.3) Gas test shall be performed and
recorded:
Prior to entry
a) After breaks or other interruption in
the work.
b) If condition of confined space have
changed.
c) At periodic interval (e.g. every 2 hours
)
1.4) Take confined space Entry permit
from SA approved permit issuer.
2) Tripod system should be used for
rescue purpose.
3 ) Only Confined Space trained person
is allowed to enter inside CS
4 ) Trained Standby men and Entry
supervisor should be available until the
completion of work
5.1) Mechanical Ventilation ( air blower )
shall be used to ensure the removal of
hazardous
airborne contaminants
5.2) Wear Self Compressed Breathing
Apparatus ( SCBA) if required
6) Use calibrated gas detector.
8. Heat Stress Procedures 1) Heat Stroke 1) Avoid working indirect sunlight when M
possible
2) Dehydration 2) Working in color part of the day if
3) Sunburn possible
3) Stay hydrated
4) Take frequency breaks
5) Drink plenty of water
6) Wear long sleeve clothes and long
pants
9. Housekeeping 1 Slips, trips and fall injuries 1 Stack and contain empty bags, M
2 Environmental Damage Container for rubbish, remove rubbish and
disposed in approved area.
2 To use poly thin bags and disposed
them to specified locations.
3 All unwanted or residual material will be
picked and disposed at waste container.
4. Remove all soil pile from work place.
10. Emergency 1 Injury to person 1 Work should be take place under direct H
2 De-hydration due to Excess heat supervision of competent engineer &
3 Suffocation safety officer.
2 Emergency vehicle & certified first aider
will be readily available in site.
3 First aid kit should be available with
sufficient medicines.
4 Drink plenty of water & take rest during
excess heat.
5 Supervisor should be trained on BLS &
First aid.
6 All person should be trained on the
emergency response procedure
7 Rescue team should be readily
available.
8 Emergency Contact Number should be
displayed on site.
11. Environmental 1 Dust Inhalation 1 Spray water to minimize the dust. M
2 Heat Stress 2 All personnel in the region must wear
3 Bad Weather(Sand, Storm and Heavy appropriate dust mask.
rain) 3 Drink plenty of water or hydration drink.
4 Take frequent break.
5 Wear hat and light color cloths.
6 Stop the work in time interval and take
rest in shaded area.
Rev Date Prepared by HSE Checked by: Reviewed by: Approved by Project
Superintendent CQC Manager Manager
00 19 July Engr.Ahson Samad Engr.Isravel Engr.Ahmed Afroz Engr.Saleh Selim
2020 Subbunadar
Activity Hazard Analysis (AHA)
Activity/Work Task:
HYDRO TEST FOR Overall Risk Assessment Code (RAC) (Use highest code)
DRINKING/FIRE WATER LINE
Project Location:
US ARMY, RSLF DAMMAM Risk Assessment Code (RAC) Matrix
Contract Number:
W912ER19C0001 Probability
Date Prepared: Severity
20/07/ 2020 Frequent Likely Occasional Seldom Unlikely
Prepared by Catastrophic E E H H M
AHSON SAMAD – HSE ENGINEER Critical E H H M L
Reviewed by Marginal H M M L L
AHMED AFROZ – CQC MNR Negligible M L L L L
Notes: (Field Notes, Step 1: Review each “Hazard” with identified safety “Controls”. Determine
Review Comments, etc.) RAC (See above)
Probability: likelihood the activity will cause
a Mishap (near miss, incident or accident).
Identify as Frequent, Likely, Occasional, RAC Chart
Seldom or Unlikely.
E = Extremely High
Severity: the outcome if a mishap occurred. Risk
Identify as Catastrophic, Critical, Marginal,
or Negligible. H = High Risk
Step 2: Identify the RAC (probability vs. M = Moderate Risk
severity) as E, H, M, or L for each “Hazard”
on AHA. Annotate the overall highest RAC L = Low Risk
at the top of AHA.
7. General Items, essential part of 1. Slips and Trips • All activities are required work permit. H
this work. 2. Electrical risk • Assign a qualified/Competent work
3. Danger area permit receiver to receive the work
1. Work permit 4. Plant Emergency permit.
2. Personal Protective • Acquire appropriate work permit.
Equipment (PPE) • Work permit issuer and receiver shall
3. Housekeeping conduct jobsite inspection before
4. Portable power tools & issuing the work permit.
Equipment’s • Follow the instructions / requirements
5. Area protection of work permit.
• Work permit receiver should monitor
the work in accordance with the work
permit system.
• Any unsafe act or any changing of
conditions the work permit receiver
should stop the work pull back the
work permit and immediately inform to
the work permit issuer.
• Work permit issuer and receiver shall
conduct jobsite inspection before
closing the work permit.
• Safety helmet, safety glass, gloves,
safety shoes, coverall and full body
harness with shock absorber and
double lanyard.
• Housekeeping should be done time to
time.
• Unwanted materials should be
removed from the job site.
• All the tools and equipment should be
kept in proper place after the use.
• Portable power tools are to be a
maximum 120 volt.
• Portable power tools are to be
protected with a GFCI.
• Provide proper grounding system.
• Review and follow the contents of this
AHA with all assigned personnel.
• Nobody is allowed to work the inside
the barricaded areas. The ground level
area should be protected with
barricade and sign.
• All employees should follow the
emergency response procedure.
8. Housekeeping 1 Slips, trips and fall injuries 1 Stack and contain empty bags, Container for M
2 Environmental Damage rubbish, remove rubbish and disposed in
approved area.
2 To use poly thane bags and disposed them to
specified locations.
3 All unwanted or residual material will be picked
and disposed at waste container.
4. Remove all soil pile from work place.
Rev Date Prepared by HSE Checked by: Reviewed by: Approved by Project
Superintendent CQC Manager Manager
00 20 July Engr.Ahson Samad Engr.Isravel Engr.Ahmed Afroz Engr.Saleh Selim
2020 Subbunadar