Weekly Report # C5 as of 12 May 2019
The Employer: The United States Army Corps of Engineers (USACE)
The Contractor: Al Yamama Company for Trading & Contracting (AYC)
Contract date: 01 Dec. 2018
Project duration: 01 Dec. 2018 TO 30 Nov 2020 (730 DAYS) (including Design & Mobilization)
Project Completion Date: 30 Nov 2019
As per Original Baseline Schedule BL‐00, following is the construction Progress:
As of 12 May 2019 as per BL‐00
Planned Progress 9.31%
Actual Progress 4.39%
Variance ‐4.92%
Days lapsed 163
Days remaining 567
Days lapsed % 22.33%
As per proposed Updated – Modified ‐ Schedule BL‐01, following is the construction Progress
As of 12 May 2019 as per BL‐01
Planned Progress 4.92%
Actual Progress 4.39%
Variance ‐0.53%
Days lapsed 163
Days remaining 567
Days lapsed % 22.33%
As BL‐00 As BL‐01
Spot from Mobilization Schedule
Spot from Design Schedule
Causes of Delay:
Delay according to the update of the BL‐00 = ‐4.92%
Activities Share of Delay
Mobilization ‐0.920%
Design ‐0.205%
Soil improvement (General) ‐0.947%
= ‐3.793%
Soil improv. (Earth Work) (Zone 2) ‐2.846%
Total ‐4.918%