Facilities for The Royal Saudi Land Forces Artillery Corps (RSLF‐ AC) Project  

 
Weekly Report # C5 as of 12 May  2019 
 
The Employer: The United States Army Corps of Engineers (USACE)  
The Contractor: Al Yamama Company for Trading & Contracting (AYC) 
Contract date: 01 Dec. 2018  
Project duration: 01 Dec. 2018 TO 30 Nov 2020 (730 DAYS) (including Design & Mobilization)  
Project Completion Date: 30 Nov 2019  
 

As per Original Baseline Schedule BL‐00, following is the construction Progress: 
 

 
As of 12 May 2019 as per BL‐00 
Planned Progress  9.31%
Actual Progress  4.39%
Variance   ‐4.92%
Days lapsed   163
Days remaining   567
Days lapsed %  22.33%
 
As per proposed Updated – Modified ‐ Schedule BL‐01, following is the construction Progress 
As of 12 May 2019 as per BL‐01 
Planned Progress  4.92%
Actual Progress  4.39%
Variance   ‐0.53%
Days lapsed   163
Days remaining   567
  Days lapsed %  22.33%

As BL‐00  As BL‐01
 
Spot from Mobilization Schedule  

 
Spot from Design Schedule  

 
Causes of Delay: 
 
Delay according to the update of the BL‐00 = ‐4.92% 
 
Activities   Share of Delay 
Mobilization         ‐0.920% 
Design         ‐0.205% 
Soil improvement (General)  ‐0.947%    
           =  ‐3.793% 
Soil improv. (Earth Work) (Zone 2)  ‐2.846%    
Total   ‐4.918% 
 