WELL: SD-25P-ST B I T R E C O R D Spud In: 30/11/06 10:30 hrs RIG: (PUMP) UpDated 8/6/2020 2:24
Water Depth : 47.2m RTE - MSL : 44.85m
BIT BIT IADC TYPE SERIAL Jets/32 DEPTH DEPTH DRLG HRS TOTAL ROP Parameters M U D DEV. DULL CODE
RUN SIZE CODE MFGR NO. or IN OUT Bit On REVS / M/Hr WOB FLOW PRES. Wt. Visc. PV/YP W/L Cutting Structure Gauge POOH
# (in.) TFA (s.i.) (M.) (M.) (M.) Bottom / BIT last Run (Klbs) RPM (GPM) (PSI) ppg Funnel cc Inner Outer DULL LOC Bearing (1/16") other Reason LITHOLOGY/REMARK
SW
1Used 33" 1.1.5 LSS1RGSPX Varel CH063 Open 161 172 11 0.50 4800.00 22.00 8klbs 80 700 450 SW SW SW 0.0 1 1 WT A E I NO TD Clean out Conductor + Rathole
KCL/Polymer
2 16" 1.1.5 T11 Reed EN3408 3 x 20 1 x 18 172 1370 1198 30.40 305.00 39.41 9.6-40klbs 105 1000 3300 9.5 68 18/24 1.0 10° 1 1 WT A E I NO TD Clyst, minor Sst
SOBM
3 12 1/4" M222 MRS91HPX Smith JW3927 3 x 16, 4 x 18 1370 2700 1330 64.20 716k 20.72 15-34klbs 135- 200 1000 4000 10.5 60 29/19 3.2 45° 1 3 CT S X I HC DTF Sst, Sltst, Clyst (2+3), Lst
4 12 1/4" M323 MRS519BHPX Smith JW1649 7 x 18 2700 3067 367 13.30 112k 27.59 10-20klbs 135 900 4200 10.5 63 32/21 3.8 56° 1 2 WT S/G X I NO TD
SOBM/BRINE/SW
5 8 1/2" 1.1.7 MXL-1 HTC 6043650 3 x 14 3023 3067 44 60° 1 1 NO A E I NO TD Drill cement and shoe track
6" DRLG
64%
DRILLING / Coring: 12.48 days .... B.O.B. (Bit On Bottom) 299.1 NOT INCLUDED TIME FOR D.O.C & H.O. INC Total Meterage Drilled / Cored = =J56-I13