You are on page 1of 8

TAKING OFF LIST

ITEM DESCRIPTIONS UNIT MYCESMM 2 Codes & Rules

CLASS A - GENERAL ITEMS

A Topographic survey and setting out Sum A310 - A10

B Site clearance upon completion Sum A360 - C9

CLASS F - EARTHWORKS

C Excavation, stripping top soil m2 F111-C1,M1,M6, A5, A6

D Excavate, cut & dispose, earth m2 F131-C1,C2,D1, A1

E Excavate, in rock (Provisional) m3 F133 - D3

CLASS R - ROADS & PAVINGS

F Sub-grade preparation m2 R110-M1, D1, C2

G Sub-base m2 R221-D2,A2,M1

H Roadbase m2 R320- D4,A3,M1

J Surfacing, tack coat m2 R530 - D5, D6,C8,A6,A8

K Surfacing, prime coat m2 R520 - D5, D6,C8,A6,A8

L Surfacing, binder course m2 R541 - D5, D6,C8,A6

M Surfacing, wearing course m2 R551 - D5, D6,C8,A6

N Road kerb m R710 - C13, A16, A17, C1

CLASS D - SITE INVESTIGATION WORK

R Soaked CBR Test nr. D635 - D6, C14, A18


Query List

No. Question Answer


1 Please confirm the thickness of topsoil 150mm thick topsoil
Please confirm the type of soil compaction the type of soil compaction test is soaked CBR test
2
test
Please confirm the volume of excavtion in The volume of excavation in rock is 1m3
3
rock
4 Please confrim the rate of tack coat The rate of tack coat is RM0.55 litre/m2
5 Please confrim the rate of prime coat The rate of prime coat is RM0.35 litre/m2
Please confrim the signage is under scope of
6 The signage is not under the scope of roadwork
roadwork construction
Please confrim the intermittent line is under The intermittent line is not under the scope of
7
scope of roadwork construction roadwork
Please confrim the type of road kerb
8 The type of road kerb is precast concrete road kerb
Query List
Item Code Descriptions Unit Qty Rate Amount
(RM) (RM)

ROAD AND PAVINGS

CLASS A : GENERAL ITEMS

A A310 Topographic survey and setting out by the sum


licensed surveyor upon given site possession

B A360 Clearance of site upon completion sum

CLASS F : EARTHWORKS

C F111 Excavation, stripping top soil, 150mm thick for m2 2592


disposal off site

D F131 Excavate, cut & dispose, earth commencing m3 1607


from underside of top soil 150mm thick

E F133 Excavation, cut and dispose, rock (Provisional) m3 1

CLASS R : ROAD & PAVINGS

F R110 Subgrade preparation, earth with minimum m2 2592


soaked laboratory California Bearing Ratio
(CBR) as shown on the Drawing No.
BTQS3034/ROADWORK/Details-1 not less than
5% as per JKR specification No. JKR 20800-
0183-14 Section P, sub-section 2.1

G R221 Sub-base, sand blinding, 200mm thick with CBR m2 2592


value as shown on the Drawing No.
BTQS3034/ROADWORK/Details-1 not less than
30% as per JKR specification No. JKR/SPJ/2008-
S4 Section 4, sub-section 4.2.1 /4.2.2

H R320 Road-base, crusher run, 300mm thick with CBR m2 2592


value as shown on the Drawing No.
BTQS3034/ROADWORK/Details-1 not less than
80% as per JKR specification No. JKR/SPJ/2008-
S4 Section a, sub-section 4.2.3
Item Code Descriptions Unit Qty Rate Amount
(RM) (RM)

CLASS R : ROAD & PAVINGS (Cont'd)

A R530 Surfacing, tack coat, bituminous at the rate of m2 2592


RM0.55 kg/m2 as per JKR specification No.
JKR/SPJ/2008-S4 Section 4, sub-section 4.3.2

B R520 Surfacing, prime coat, bituminous at the rate of m2 2592


RM0.35 kg/m2 as per JKR specification No.
JKR/SPJ/2008-S4 Section 4, sub-section 4.3.1

C R541 Surfacing, asphaltic concrete, binder course, m2 2592


65mm compacted thickness as per JKR
specification No, JKR/SPJ/2008-S4 Section 4,
sub-section 4.3.3

D R551 Surfacing, asphaltic concrete, wearing course, m2 2592


50mm compacted thickness as per JKR
specification No, JKR/SPJ/2008-S4 Section 4,
sub-section 4.3.3

E R710 Kerbs, channels and edgings, precast concrete m 558


kerbs; 150mm x 250mm high as per JKR
specification No. JKR 20800-0183-14 Section P,
sub-section 6.4 and as shown on drawing no.
BTQS3034/ROADWORK/details-1

CLASS D : SITE INVESTIGATION WORKS

F D635 Laboratory tests, soil compaction related, nr. 3


soaked CBR for subgrade, sub-base and road-
base
Taking-Off Paper
Page: 1
Index No: Job No: Road & Pavement (Road B)
Project: Measurement of Civil Engineering Works Drawing Ref:

Site Clearance Road & Paving (Cont'd)

Topographic survey and setting out by Subgrade preparation, earth with


the licensed surveyor upon given site minimum soaked laboratory California
possession Bearing Ratio (CBR) as shown on the
Drawing No.
A310 BTQS3034/ROADWORK/Details-1 not
SUM less than 95% as per JKR specification
No. JKR 1998- Section 2, sub-section
2.2.7
Clearance of site upon completion
A360
SUM 44.68 R110
9.30 415.52 Road B1
Excavation, stripping top soil, 150mm
thick for disposal off site 65.00
F111 9.30 604.50 Road B2
Road B1
Length (m) 79.00
44.68 9.30 734.70 Road B3

Road B2 90.00
Length (m) 9.30 837.00 Road B4
65.00 2591.72 m2

Road B3
Length (m)
79.00 Sub-base, sand blinding, 200mm thick
with CBR value as shown on the
Road B4 Drawing No.
BTQS3034/ROADWORK/Details-1 not
Length (m) less than 30% as per JKR specification
90.00 No. JKR/SPJ/2008-S4 Section 4, sub-
section 4.1.2 /4.2.2
Width (m)
Carridgeway 2*4 8.00
Add marginal way 2*0.5 1.00 R221
Add kerb width 2*0.15 0.30 44.68
9.30 9.30 415.52 Road B1

65.00
44.68 9.30 604.50 Road B2
9.30 415.52 Road B1
79.00
65.00 9.30 734.70 Road B3
9.30 604.50 Road B2
90.00
79.00 9.30 837.00 Road B4
9.30 734.70 Road B3 2591.72 m2
Road-base, crusher run, 300mm thick
90.00 with CBR value as shown on the
Drawing No.
9.30 837.00 Road B4 BTQS3034/ROADWORK/Details-1 not
2591.72 m2 less than 80% as per JKR specification
No. JKR/SPJ/2008-S4 Section a, sub-
section 4.2.3
Earthwork

Excavate, cut & dispose, earth


commencing from underside of top 44.68 R320
soil 150mm thick
9.30 415.52 Road B1
F131
65.00
Thickness (mm) 9.30 604.50 Road B2
Add kerb height 150
50 79.00
Add 65 9.30 734.70 Road B3
Add 300
Add 200 90.00
765 9.30 837.00 Road B4
ddt topsoil 150 2591.72 m2
615

Surfacing, tack coat, bituminous at the


44.68 rate of RM0.55 kg/m2 as per JKR
9.30 specification No. JKR/SPJ/2008-S4
Section 4, sub-section 4.3.2
0.62 257.62 Road B1

65.00 44.68
9.30 9.30 415.52 Road B1 R530
0.62 374.79 Road B2
65.00
79.00 9.30 604.50 Road B2
9.30
0.62 455.51 Road B3 79.00
9.30 734.70 Road B3
90.00
9.30 90.00
0.62 518.94 Road B4 9.30 837.00 Road B4
1606.87 m2 2591.72 m2

Surfacing, prime coat, bituminous at


the rate of RM0.35 kg/m2 as per JKR
Excavation, cut and dispose, rock specification No. JKR/SPJ/2008-S4
(Provisional) Section 4, sub-section 4.3.1
F133
1.00
1.00 44.68 R520
1.00 1.00 m3 9.30 415.52 Road B1

65.00
9.30 604.50 Road B2

79.00
9.30 734.70 Road B3
90.00
9.30 837.00 Road B4
2591.72 m2

Taking-Off Paper
Page:
Index No: Job No:
Project: Measurement of Civil Engineering Works Drawing Ref: Road & Pavement (Road B)

Road & Paving (Cont'd)

Surfacing, asphaltic concrete, binder


course, 65mm compacted thickness as
per JKR specification No,
JKR/SPJ/2008-S4 Section 4, sub-
section 4.3.3

R541
44.68
9.30 415.52 Road B1

65.00
9.30 604.50 Road B2

79.00
9.30 734.70 Road B3
90.00
9.30 837.00 Road B4
2591.72 m2

Surfacing, asphaltic concrete, wearing


course, 50mm compacted thickness as
per JKR specification No,
JKR/SPJ/2008-S4 Section 4, sub-
section 4.3.3

R551
44.68
9.30 415.52 Road B1

65.00
9.30 604.50 Road B2

79.00
9.30 734.70 Road B3
90.00
9.30 837.00 Road B4
2591.72 m2

Kerbs, channels and edgings, precast


concrete kerbs; 150mm x 250mm high
as per JKR specification No. JKR
20800-0183-14 Section P, sub-section
6.4 and as shown on drawing no.
BTQS3034/ROADWORK/details-1

R710
Length
278.68
= 278.68*2
= 557.36
557.36 557.36 m
Laboratory tests, soil
compaction related, soaked
CBR for subgrade, sub-base
and road-base

3 3 nr.
D635